Antelope Valley Solar Ranch: Difference between revisions
Mundanemetal (talk | contribs) →Electricity Production: added more data from the source listed to bring it up to date |
|||
(5 intermediate revisions by 5 users not shown) | |||
Line 14: | Line 14: | ||
| decommissioned = |
| decommissioned = |
||
| cost = $1.36 billion<ref>{{cite news | title=First Solar shares jump after Antelope Valley construction OKd | url=http://articles.latimes.com/2012/jun/23/business/la-fi-first-solar-20120623 | work=[[Los Angeles Times]] | access-date=3 July 2014 | archive-url=https://web.archive.org/web/20120625090048/http://articles.latimes.com/2012/jun/23/business/la-fi-first-solar-20120623 | archive-date=2012-06-25 | url-status=dead | quote=Shares of First Solar Inc. soared after the biggest maker of thin-film solar panels received permission to continue construction on a $1.36-billion power project in Los Angeles County. }}</ref><br/>(${{format price|{{Inflation|US-GDP|1.36e9|2012}}}} in {{Inflation-year|US-GDP}} dollars{{Inflation-fn|US-GDP}}) |
| cost = $1.36 billion<ref>{{cite news | title=First Solar shares jump after Antelope Valley construction OKd | url=http://articles.latimes.com/2012/jun/23/business/la-fi-first-solar-20120623 | work=[[Los Angeles Times]] | access-date=3 July 2014 | archive-url=https://web.archive.org/web/20120625090048/http://articles.latimes.com/2012/jun/23/business/la-fi-first-solar-20120623 | archive-date=2012-06-25 | url-status=dead | quote=Shares of First Solar Inc. soared after the biggest maker of thin-film solar panels received permission to continue construction on a $1.36-billion power project in Los Angeles County. }}</ref><br/>(${{format price|{{Inflation|US-GDP|1.36e9|2012}}}} in {{Inflation-year|US-GDP}} dollars{{Inflation-fn|US-GDP}}) |
||
| owner = [[ |
| owner = [[Constellation Energy]] |
||
| employees = 20{{ r | DOE }} |
| employees = 20{{ r | DOE }} |
||
| operator = |
| operator = |
||
Line 27: | Line 27: | ||
}} |
}} |
||
The '''Antelope Valley Solar Ranch 1''' ('''AVSR1''') is a 230 [[megawatt]] (MW<sub>[[Nominal power (photovoltaic)#Conversion from DC to AC|AC]]</sub>) [[photovoltaic power plant]] near [[Lancaster, California|Lancaster]] within [[Antelope Valley]], in the western [[Mojave Desert]], Southern [[California]]. It uses [[cadmium telluride photovoltaics|cadmium telluride modules]] made by the US [[thin film solar cell|thin-film]] manufacturer [[First Solar]]. The project was developed by [[First Solar]] and later bought by [[Exelon Corporation]] in 2011 |
The '''Antelope Valley Solar Ranch 1''' ('''AVSR1''') is a 230 [[megawatt]] (MW<sub>[[Nominal power (photovoltaic)#Conversion from DC to AC|AC]]</sub>) [[photovoltaic power plant]] near [[Lancaster, California|Lancaster]] within [[Antelope Valley]], in the western [[Mojave Desert]], Southern [[California]]. It uses [[cadmium telluride photovoltaics|cadmium telluride modules]] made by the US [[thin film solar cell|thin-film]] manufacturer [[First Solar]]. The project was developed by [[First Solar]] and later bought by [[Exelon Corporation]] in 2011.<ref name="greentech-2013-05-19">GreenTechMedia.com, Herman K. Trabish, [http://www.greentechmedia.com/articles/read/First-Solar-Cleared-to-Resume-Construction-in-Antelope-Valley First Solar Cleared to Resume Construction in Antelope Valley], 19 May 2013</ref><ref>GreenTechMedia.com, Herman K. Trabish, [http://www.greentechmedia.com/articles/read/Antelope-Valley-Solar-Ranch-One-the-Solar-Power-Plant-That-Could Antelope Valley Solar Ranch One: The Solar Power Plant That Could], 5 March 2012</ref><ref name="exelon">{{cite web|title=Antelope Valley Solar Ranch One|url=http://www.exeloncorp.com/powerplants/antelopevalleysolarranchone/Pages/Profile.aspx|publisher=Exelon|access-date=3 July 2014}}</ref> The solar facility was fully commissioned in April 2014.<ref name="DOE" /> |
||
==Overview== |
==Overview== |
||
Line 70: | Line 70: | ||
|- |
|- |
||
! 2021 |
! 2021 |
||
| 35,211 || 41,830 || 52,505 || 58,413 || 62,902 || 58,568 || 57,547 || 57,184 || 51,842 || |
| 35,211 || 41,830 || 52,505 || 58,413 || 62,902 || 58,568 || 57,547 || 57,184 || 51,842 || 47,535 || 41,120 || 29,030 |
||
! 651,255 |
|||
|- |
|- |
||
!2022 |
|||
⚫ | |||
| 41,120 || 43,984 || 53,269 || 58,266 || 62,542 || 59,217 || 60,502 || 57,296 || 50,528 || 49,547 || 40,547 || 29,569 |
|||
! 606,387 |
|||
|- |
|||
!2023 |
|||
| 30,340 || 36,653 || 45,638 || 58,446 || 58,241 || -|| -|| -|| -|| -|| -||- |
|||
! 229,318 |
|||
|- |
|||
⚫ | |||
|} |
|} |
||
Latest revision as of 01:39, 16 August 2023
Antelope Valley Solar Ranch | |
---|---|
![]() | |
Country | United States |
Location | Antelope Valley, California |
Coordinates | 34°46′30″N 118°25′30″W / 34.77500°N 118.42500°W |
Status | Operational |
Construction began | August 2011 |
Commission date | April 2014 [1] |
Construction cost | $1.36 billion[2] ($1.78 billion in 2023 dollars[3]) |
Owner(s) | Constellation Energy |
Employees | 20[1] |
Solar farm | |
Type | Flat-panel PV |
Site area | 2,100 acres (8.50 km2) |
Power generation | |
Units operational | 3,800,000 |
Nameplate capacity | 230 MWAC |
Capacity factor | 30.5% (average 2015-2017) |
Annual net output | 614 GW·h, 290 MW·h/acre |
The Antelope Valley Solar Ranch 1 (AVSR1) is a 230 megawatt (MWAC) photovoltaic power plant near Lancaster within Antelope Valley, in the western Mojave Desert, Southern California. It uses cadmium telluride modules made by the US thin-film manufacturer First Solar. The project was developed by First Solar and later bought by Exelon Corporation in 2011.[4][5][6] The solar facility was fully commissioned in April 2014.[1]
Overview[edit]
In September 2011, the U.S. Department of Energy issued a $646 million loan guarantee to support the project's construction.[1] This loan guarantee was part of the American Recovery and Reinvestment Act of 2009.[7] The project is expected to create 350 construction jobs and 20 permanent jobs.[1]
On February 20, 2013, the first 100 MWAC came online.[8] The plant will use approximately 3.8 million solar panels,[6] about 20% of which will be mounted on single-axis tracking racks.[1] When fully operational, the plant is expected to generate enough energy for 75,000 homes, displacing 140,000 tons of CO2.[8] The power generated by AVSR1 is being purchased by Pacific Gas and Electric Company (PG&E) under a 25-year Power Purchase Agreement.[1][8]
Electricity Production[edit]
Year | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2014 | 60,933 | 56,929 | 52,593 | 42,933 | 30,309 | 243,697 | |||||||
2015 | 37,018 | 44,005 | 54,695 | 58,280 | 62,283 | 57,808 | 61,724 | 61,790 | 53,927 | 47,614 | 43,426 | 36,838 | 619,408 |
2016 | 32,935 | 46,208 | 53,436 | 55,097 | 62,375 | 61,868 | 64,535 | 61,770 | 56,081 | 46,491 | 41,614 | 31,884 | 614,294 |
2017 | 32,470 | 35,964 | 54,112 | 55,959 | 61,980 | 61,839 | 60,944 | 58,500 | 55,398 | 53,005 | 39,893 | 37,885 | 607,949 |
2018 | 36,279 | 44,379 | 48,604 | 57,764 | 63,414 | 61,891 | 58,385 | 59,406 | 55,420 | 48,906 | 38,405 | 33,382 | 606,235 |
2019 | 29,889 | 35,096 | 50,802 | 56,509 | 57,218 | 60,036 | 60,504 | 61,467 | 54,174 | 45,567 | 37,007 | 27,365 | 575,634 |
2020 | 39,053 | 45,448 | 41,055 | 51,660 | 59,820 | 57,073 | 60,313 | 53,436 | 45,572 | 44,493 | 39,195 | 33,014 | 570,132 |
2021 | 35,211 | 41,830 | 52,505 | 58,413 | 62,902 | 58,568 | 57,547 | 57,184 | 51,842 | 47,535 | 41,120 | 29,030 | 651,255 |
2022 | 41,120 | 43,984 | 53,269 | 58,266 | 62,542 | 59,217 | 60,502 | 57,296 | 50,528 | 49,547 | 40,547 | 29,569 | 606,387 |
2023 | 30,340 | 36,653 | 45,638 | 58,446 | 58,241 | - | - | - | - | - | - | - | 229,318 |
Average Annual Production (2015-2022) | 606,412 |
See also[edit]
- Solar power plants in the Mojave Desert
- Solar power in California
- List of photovoltaic power stations
- Renewable energy in the United States
- Renewable portfolio standard
References[edit]
- ^ a b c d e f g "Exelon (Antelope Valley Solar Ranch)". US Department of Energy (DOE). Retrieved 3 July 2014.
- ^ "First Solar shares jump after Antelope Valley construction OKd". Los Angeles Times. Archived from the original on 2012-06-25. Retrieved 3 July 2014.
Shares of First Solar Inc. soared after the biggest maker of thin-film solar panels received permission to continue construction on a $1.36-billion power project in Los Angeles County.
- ^ Johnston, Louis; Williamson, Samuel H. (2023). "What Was the U.S. GDP Then?". MeasuringWorth. Retrieved November 30, 2023. United States Gross Domestic Product deflator figures follow the MeasuringWorth series.
- ^ GreenTechMedia.com, Herman K. Trabish, First Solar Cleared to Resume Construction in Antelope Valley, 19 May 2013
- ^ GreenTechMedia.com, Herman K. Trabish, Antelope Valley Solar Ranch One: The Solar Power Plant That Could, 5 March 2012
- ^ a b "Antelope Valley Solar Ranch One". Exelon. Retrieved 3 July 2014.
- ^ "American Recovery and Reinvestment Act (ARRA) Loans - Award Summary: AV Solar Ranch 1, LLC". Recovery.gov. The Recovery Accountability and Transparency Board. Archived from the original on 14 July 2014. Retrieved 3 July 2014.
- ^ a b c "AV Solar Ranch One Solar Power Plant Achieves 100 MW Milestone". First Solar. Archived from the original on 12 July 2014. Retrieved 3 July 2014.
- ^ "AV Solar Ranch One, Monthly". Electricity Data Browser. Energy Information Administration. Retrieved May 23, 2019.