Bundelkhand Expressway

From Wikipedia, the free encyclopedia

This is an old revision of this page, as edited by Amartyabag (talk | contribs) at 06:12, 16 July 2022 (Inaugurated). The present address (URL) is a permanent link to this revision, which may differ significantly from the current revision.

Bundelkhand Expressway
Map
Bundelkhand Expressway in red
Bundelkhand Expressway 2022.png
The expressway passing through Jalaun, Uttar Pradesh
Route information
Maintained by Uttar Pradesh Expressways Industrial Development Authority (UPEIDA)
Length296.07 km (183.97 mi)
Existed16 July 2022[1]–present
Major junctions
North endKudrail village, Etawah district
South endGonda village, Chitrakoot district
Standort
LandIndien
StateUttar Pradesh
Highway system
State Highways in Uttar Pradesh

Bundelkhand Expressway is a 296 km long, 4-lane wide (expandable to 6) access-controlled expressway in the state of Uttar Pradesh, India.[2] It connects Gonda village on NH-35 in Chitrakoot district with Kudrail village on Agra–Lucknow Expressway in Etawah district.[3] Prime Minister Narendra Modi laid down the foundation stone of Bundelkhand Expressway on 29 February 2020 in Gonda village, Chitrakoot and inaugurated on 16 July 2022 by Narendra Modi.[4] The expressway will boost tourism to Chitrakoot Dham.

The project was launched in April 2017 by the Chief Minister of Uttar Pradesh, Yogi Adityanath.[5] It is being developed by the Uttar Pradesh Expressways Industrial Development Authority (UPEIDA) with a total project value of ₹14,716 crores, including the land acquisition cost.[6]

Route

Bundelkhand Expressway will connect Kudrail village on Agra–Lucknow Expressway in Etawah district with Gonda village on NH-35 in Chitrakoot district. It will pass through 7 districts of Uttar Pradesh i.e. (from north to south) Etawah, Auraiya, Jalaun, Hamirpur, Mahoba, Banda and Chitrakoot.[7]

Following is the route of the expressway from Kudrail village (Etawah) to Chitrakoot Dham:

Bauwesen

The construction work of 296 km long Bundelkhand Expressway is divided into 6 packages and awarded to 4 different contractors. Total 4 Railway-over-bridges (ROB), 14 major bridges, 268 minor bridges, 18 flyovers, 6 Toll Plazas, 7 Ramp Plazas and 214 underpasses will be constructed on this expressway.[8] Its construction cost is around 7,766 crores (excluding the cost of Land). The list of contractors is as follows:[9]

Sr. No Package Length in km Contractor
1. Gonda (Chitrakoot)–Mahokhar (Banda) 50.5 Apco Infratech
2. Mahokhar (Banda)–Kaohari (Mahoba) 50.3 Apco Infratech
3. Kaohari (Mahoba)–Baroli Kharka (Hamirpur) 49.0 Ashoka Buildcon[10][11]
4. Baroli Kharka (Hamirpur)–Salabad (Jalaun) 51.0 Gawar Construction
5. Salabad (Jalaun)–Bakhariya (Auraiya) 50.0 Gawar Construction
6. Bakhariya (Auraiya)–Kudrail (Etawah) 45.3 Dilip Buildcon[12]

Status updates

  • April 2017: Chief Minister of Uttar Pradesh Yogi Adityanath announces plan to build Bundelkhand Expressway.[13]
  • Aug 2017: Plan announced to connect upcoming Bundelkhand Expressway to Agra–Lucknow Expressway via Bateshwar.[14]
  • Nov 2017: Work related to route survey is started, which will be followed by preparation of Detailed Project Report (DPR).[15]
  • Jun 2018: Due to lack of funds, Uttar Pradesh government requests the Government of India to build Bundelkhand Expressway.[16]
  • Nov 2018: Government of Uttar Pradesh releases ₹ 640 crores for land acquisition.[17]
  • Dec 2018: Land acquisition started. The plan is to complete land acquisition in 2 months. Construction work to begin after 80% of the required land is acquired.[18]
  • Feb 2019: DPR prepared and 27% of required land has been acquired.[6]
  • May 2019: 60% of required land has been acquired. Bidding process to start after Lok Sabha Model Code of Conduct.[19]
  • Jun 2019: 79% of required land has been acquired.[20]
  • July 2019: ₹ 1,150 crore budget booster for Bundelkhand Expressway.[21]
  • Aug 2019: 90% of required land has been acquired. Construction work to start in October 2019.[22]
  • Oct 2019: Construction work of the expressway is divided into 6 packages. The government of Uttar Pradesh shortlisted 4 private firms for developing the expressway.[23]
  • Jan 2020: The construction work of all 6 packages started by contractors. Pace of construction work going slow in Mahoba district.[24]
  • Feb 2020: Prime Minister Narendra Modi laid the foundation of the expressway on 29 February 2020 in Chitrakoot.[25] 95% land is acquired, 2% of soil work completed.[26]
  • Apr 2020: Road construction work which was halted due to COVID-19, resumes in 3 out of 6 packages.[27]
  • Jun 2020: The expressway will pass through 182 villages across 7 districts. 3,483 out of 3,654 hectares (95.32%) of required land has been acquired till 15 June.[28]
  • Aug 2020: 14% of construction work completed ahead of schedule.[29]
  • May 2021: 90% of the earthworks and 60% of construction work completed. 581 out of total 818 structures completed as of 31 May.[30][31]
  • Aug 2021: 71% of construction work and 704 out of total 880 structures completed as of 31 August.[32]
  • Sep 2021: The expressway's section from Etawah to Jalaun is almost completed, and is expected to become operational by December 2021.[33]
  • Oct 2021: Uttar Pradesh Expressways Industrial Development Authority (UPEIDA) completes over 73% of construction work of the expressway.[34]
  • Jan 2022: 100% of earthwork and 820 structures out of 881 structures are completed, overall 83.30% of construction work of the expressway has been completed.[35]
  • April 2022: 92.58% of construction work and 866 out of 881 structures has been completed.[36][37]
  • May 2022: Over 94% of construction work has been completed.[38]
  • June 2022: Over 96% of construction work has been completed, and the inauguration date is now scheduled to the second week of July.[39]
  • July 2022: On 16 July 2022, Prime Minister Narendra Modi inaugurated this expressway from Jalaun. [40][41]

See also

References

  1. ^ "PM Narendra Modi to inaugurate Bundelkhand Expressway on July 16". Times of India. Retrieved 9 June 2022.
  2. ^ "About Bundelkhand Expressway". UPEIDA. Retrieved 12 July 2021.
  3. ^ Rawat, Virendra Singh (22 February 2019). "UP hits top gear to acquire land for Rs 14,700 crore Bundelkhand Expressway". Business Standard.
  4. ^ "PM Modi lays foundation stone; must-know facts about ambitious infrastructure project". Financial Express. 29 February 2020.
  5. ^ "Bundelkhand: Six-lane expressway to Delhi in the works, says CM Yogi Adityanath". 21 April 2017.
  6. ^ a b Rawat, Virendra Singh (22 February 2019). "UP hits top gear to acquire land for Rs 14,700-cr Bundelkhand Expressway". Business Standard India – via Business Standard.
  7. ^ "Uttar Pradesh: Bundelkhand Expressway to get operational by June 2022". The Times of India. 8 April 2022.
  8. ^ "60% construction work of Bundelkhand Expressway is complete". Amar Ujala. 2 June 2021.
  9. ^ "Bundelkhand: UPEIDA inks deal with Bank of Baroda-led bank consortium to fund the project". Financial Express. 26 August 2020.
  10. ^ "Ashoka Buildcon receives LoA for Bundelkhand Expressway project worth Rs 1079.52 crores". Business Standard. 28 November 2019.
  11. ^ "Ashoka Buildcon sets new milestones at Bundelkhand Expressway". Construction Week Online. 28 May 2021.
  12. ^ "Dilip Buildcon bags Bundelkhand Expressway project worth Rs 1,362 cr in UP". Business Standard. 29 November 2019.
  13. ^ "What is Yogi Adityanath's 'six-lane' plan to develop Bundelkhand: All you need to know". 21 April 2017.
  14. ^ "Vajpayee's birth place Bateshwar to be connected to Bundelkhand, Lucknow and Delhi | Agra News". Times of India. Retrieved 25 November 2017.
  15. ^ "Work on Bundelkhand Expressway to start from next year: Adityanath". thehansindia.com. 25 November 2017. Retrieved 25 November 2017.
  16. ^ Sharma, Aman; Arora, Rajat. "Uttar Pradesh asks NHAI to build Bundelkhand Expressway". The Economic Times.
  17. ^ "Bundelkhand Expressway: UP government looks to expedite work; releases Rs 640 crore for land acquisition". 18 November 2018.
  18. ^ "एक्सप्रेसवे के लिए जमीन अधिग्रहण शुरू". hindi.business-standard.com.
  19. ^ Rawat, Virendra Singh (12 May 2019). "UP aims to finish 2 highways before 2022 polls, steps up Land acquisition". Business Standard India.
  20. ^ Anshuman, Kumar. "Expressway in up: Yogi plans expressway to every region of UP by 2022". The Economic Times.
  21. ^ "Rs 1,150 crore budget booster for Bundelkhand e-way | Lucknow News - Times of India". The Times of India.
  22. ^ "Construction of Bundelkhand Expressway to start in October: UP Govt". Money Control. 20 August 2019.
  23. ^ Rawat, Virendra Singh (26 October 2019). "UP picks 4 developers for 2 Expressway projects worth Rs 20,000 crores". Business Standard.
  24. ^ "DM of Mahoba angry over slow progress on expressway project". Amar Ujala. 27 January 2020.
  25. ^ "उत्तर प्रदेश के चित्रकूट में आज पीएम मोदी 296.07 किलोमीटर लंबे बुंदेलखंड एक्सप्रेस-वे का शिलान्यास करेंगे". NDTV India. Retrieved 29 February 2020.
  26. ^ "Purvanchal Expressway likely to be ready by year-end". Hindustan Times. 2 February 2020.
  27. ^ "Uttar Pradesh: Work resumes on key Expressways". The Times of India. 21 April 2020.
  28. ^ "Land acquisition details of Bundelkhand Expressway" (PDF). UPEIDA. 16 June 2020.
  29. ^ "14% work of Bundelkhand Expressway ready before time". Times of India. 25 August 2020.
  30. ^ "60% work of Bundelkhand Expressway completed: CEO of UPEIDA". The Indian Express. 30 May 2021.
  31. ^ "Progress Report of Bundelkhand Expressway (May 2021)" (PDF). UPEIDA. Archived (PDF) from the original on 2 June 2021. Retrieved 31 May 2021.
  32. ^ "Progress Report of Bundelkhand Expressway (August 2021)" (PDF). UPEIDA. Archived (PDF) from the original on 3 September 2021. Retrieved 31 August 2021.
  33. ^ "दिसंबर से बुंदेलखंड एक्सप्रेस वे पर सफर कर सकेंगे लोग, जानें- क्या है सरकार का प्लान". ABP News (in Hindi). 7 September 2021. Retrieved 10 September 2021.
  34. ^ "Over 73% construction work of Bundelkhand Expressway completed: UPEIDA CEO". Hindustan Times. 13 October 2021. Retrieved 17 October 2021.
  35. ^ "UP Expressways Industrial Development Authority progress report" (PDF). upeida.in (in Hindi). 4 January 2022. Retrieved 4 January 2022.
  36. ^ "पीएम मोदी जून में करेंगे बुंदेलखंड एक्सप्रेस-वे का उद्घाटन, मंत्री नन्दी ने तय किया 100 दिन का एजेंडा". Hindustan (in Hindi). Retrieved 2 April 2022.
  37. ^ Singh, Surendra (2 April 2017). "bundelkhand: 300-km Bundelkhand e-way to be ready by June, will cut travel time to Delhi by 6 hours: Minister | India News - Times of India". The Times of India. Retrieved 2 April 2022.
  38. ^ "जनता को मिलने जा रहा बुंदेलखंड एक्सप्रेस-वे का तोहफा, पीएम मोदी करेंगे उद्घाटन -अनिल राजभर | News in Hindi". zeenews.india.com. Retrieved 15 May 2022.
  39. ^ "Bundelkhand Expressway". upeida.up.gov.in. Retrieved 17 June 2022.
  40. ^ "Bundelkhand Expressway". upeida.up.gov.in. Retrieved 5 July 2022.
  41. ^ Sharda, Shailvee (7 July 2022). "PM Narendra Modi to inaugurate Bundelkhand Expressway on July 16". The Times of India. Retrieved 9 July 2022.