    Photo Story: Fort McCoy East Barracks Project construction operations for August 2024, Part 1

    Fort McCoy East Barracks Project construction operations for August 2024

    Photo By Scott Sturkol | Contractors work on a new $27.3 million transient training troops barracks project...... read more read more

    Contractors continued working on a new $27.3 million transient training troops barracks project Aug. 7-8, 2024, at Fort McCoy, Wis.

    Contractors began in May 2024 getting the site set up for the fourth transient training troops barracks project at Fort McCoy, which was awarded in February 2024 to L.S. Black Constructors, LLC, for approximately $27.3 million.

    L.S. Black Constructors is a familiar name in the barracks construction history at Fort McCoy, having built the first two of the 60,000-square-foot transient training troops barracks on post.

    They also recently built the new brigade headquarters building located in the same block as the barracks buildings. The exact contract amount for the project was $27,287,735.

    In the award announcement, it states it was “for the construction of the barracks, which will provide housing for enlisted service members undergoing training at the installation.”

    The building will be able to house up to 400 people and will be more than 60,000 square feet when completed, according to the Army Corps of Engineers, which is managing the project.

    All of this work continues with the master plan for the 1600 block that will include not only the four barracks but also three 20,000-square-foot brigade headquarters buildings — one of which is done — and two 160-room officer quarters, said Master Planner Brian Harrie with the Fort McCoy Directorate of Public Works.

    The Fort McCoy Executive Summary, available at https://www.dvidshub.net/publication/issues/71646, also shows the installation makes continuous improvements to provide a plethora of training capabilities for service members.

    “Throughout the last decade, Fort McCoy experienced unprecedented facility modernization, training area development and expansion, increased training and customer support capability, and improved quality-of-life opportunities,” the summary states. “From unmanned aerial vehicles to urban training facilities, to live-fire ranges and virtual-training environments, Fort McCoy is prepared to meet the training needs of the Army in the 21st century.”

    Also to be completed soon, Army Corps of Engineer officials said earlier in 2024, is the awarding of a contract for one of the officer quarters buildings. Harrie has stated in previous news articles this entire transformation of this block at McCoy is known as the 1600 Block Transient Training Campus Plan.

    See more news about the U.S. Army Corps of Engineers by visiting https://www.usace.army.mil/Media/News.

    Fort McCoy’s motto is to be the “Total Force Training Center.”

    Located in the heart of the upper Midwest, Fort McCoy is the only U.S. Army installation in Wisconsin.

    The installation has provided support and facilities for the field and classroom training of more than 100,000 military personnel from all services nearly every year since 1984.

    Learn more about Fort McCoy online at https://home.army.mil/mccoy, on Facebook by searching “ftmccoy,” on Flickr at https://www.flickr.com/photos/fortmccoywi, and on X (formerly Twitter) by searching “usagmccoy.”

    Also try downloading the My Army Post app to your smartphone and set “Fort McCoy” or another installation as your preferred base. Fort McCoy is also part of Army’s Installation Management Command where “We Are The Army’s Home.”

    NEWS INFO

    Date Taken: 08.18.2024
    Date Posted: 08.18.2024 23:27
    Story ID: 478911
    Location: FORT MCCOY, WISCONSIN, US

    Web Views: 26
    Downloads: 0

    PUBLIC DOMAIN