Professional Documents
Culture Documents
Slide Flexus
Slide Flexus
SUITES
CONSTRUCTION MANAGEMENT
me Matrix No
ammad Amin bin Saniman 143013540
Muhammad Faiz bin Wan Salleh 153016028
iq Izzuddin bin Jaini 143013812
Mei Ting 143013755
Yu Xuan 143013754
Hong Shan 143013876
1.0 INTRODUCTION
LARGE PEOPLE
CONSTRUCTION
DELAY
TIME
SOURCES ISSUES
PROJECT DELIVERY
SYSTEM
1.1 PROJECT INFORMATION
onstruction Team : i. Permai Ihsan Sdn Bhd (Main Contractor) iii. Riana Dutamas
ii. Jaya Kian Seng S/B (Plumbing) iv. The Pano@Jalan Ipoh
umptions Approaches
Interview with project manager
ent
Finance and payments of completed work
Site visit
Slow decision making
nsultant
Preparation and approval of drawing
2.1 TRADITIONAL PROCUREMENT METHOD
1. Public
Surrounding public will feel that their health are affected by dust pollution cause by the
project.
Sound pollution has made the public feel annoying and hard to focus on work.
Delay of the project is given bad impression to the public.
2. Client
Due to project delay, client feel that the contractors working efficiency is low.
Client late moving in.
Late payment from client caused the contractor dissatisfied.
Conflicts may raise between client and contractor.
3.3 SCOPE AND PERSPECTIVE
SCOPE
LIENT Increase in cost for client due to extended Extra budget needed to cover the extra work done by co
construction time.
ONSULTANT Amendments are made for each changes instructed Requires more inspection for work done by contractor.
by the client.
ONTRACTOR More work force needed to complete the work in time Workers may need to work overtime .
or to prevent any further delays.
UPPLIER May increase in material cost to supply for Delivery for materials may need to be cancelled .
construction materials.
4.0 CONCLUSION
raditional project delivery system is not suitable for large construction project