Control Panel Manual1X25
Control Panel Manual1X25
1
Volume
MHP
0
Schematic & Wiring
Diagrams
1
YT E K CON T R OLS, I NC.
1
Feature of Automatic
1
Chapter
Control Panel for HEP
A comprehensive Hydro Electric Plant’s
automation and governing system.
Eigenschaften
2
system includes self test diagnostic circuits and
programs, error handling routines and alarm
messages handling.
APPLICATION :INDOOR
OPERATION :SINGLE FRONT
TYPE :FIXED TYPE
ACCESS :FRONT OPERATED WITH FRONT AND REAR
OPEN
DEGREE OF PROTECTION :IP-54
INSTALLATION :FREE STANDING FLOOR MOUNTED
PAINT SHADE :EXTERNAL - GREY, INTERNAL - GREY,
BASE - BLACK, MOUNTING PLATE –
PURPLE/ORANGE
REAR SIDE :ACCESSIBLE
DOOR GASKET :FOAM RUBBER
3
FABRICATION :MS CRCA SHEET STEEL THICKNESS 14 SWG,
LOAD BEARING MEMBER – 14 SWG, BASE ISMC
– 75
DOOR LOCK :FRONT FEEDER DOOR WITH SPECIAL LOCK &
KEY OPERATION THE REAR BIG DOOR ON SIDE
HINGED OTHER SIDE LOCK
HARDWARE :ZINC PLATED AND PASSIVATED WITH ONE
SPRING WASHER AND TWO PLAIN WASHERS
CABLE ENTRY :INCOMMER - BOTTOM OUTGOING – BOTTOM
& SIDE
LEGEND PLATE :TYPE - ALUMINIUM BLACK COVER ANODISED /
PVC
SIZE – MAIN LEGEND – 200X50
FEEDER – 150X40
METER – 60X20
LIGHTS – 22.5 DIA/ 60X20
MCB’S – 35X20
TAGS – 12X20
ELECTRICAL
DOOR EARTHING :EVERY FEEDER HINGED DOOR WITH
WIRE
2.5 Sq.mm
VOLTAGE CIRCUITS – COPPER FLEXIBLE WIRE
1 Sq.mm
SLEEVE COLOUR :WHITE
4
CONTROL MIN. SIZE 2.5 Sq.mm
POWER TERMINAL STUD TYPE
CONTROL TERMINAL CLIP ON TYPE
MAIN BUS BAR E91E
ELECTROLYTIC GRADE :ALUMINIUM 50mm x 10mm FOR PHASE - BUS
50mm x 10mm FOR NEUTRAL –
BUS
SYSTEM OPERATION
5
As the system is switched to Auto Mode or main
system key is brought to on condition, Protection
status of the system is monitored for normal
conditions. Then on condition of all faults condition
clear, BFV are opened by manually pumping the
hydraulic unit. Turbine is allowed to rotate and
achieve appropriate rpm. When the appropriate rpm
are reached the ELC (Electronic Load Controller)
takes over and governs the speed of the turbine. For
Isolated mode frequency of the generator is regulated
at 50Hz. On achieving rated RPM/Frequency main
Breaker (MCCB) can be switched on by Pushing the
manual liver on MCCB.
A comprehensive metering is available to indicate
power, volts, current, power factor and ballast load.
6
Main trip relay RL4 breaks the closing circuit of
generator MCCB, closes BFV and sounds Hooter.
7
speed tries to increase beyond rated
speed/frequency ELC starts diverting load to
ballast heaters thus controls the speed.
It should be noted that ELC governs the speed
/frequency of the system by diverting the excess
load to heaters, which is actually wasting of
available water resources. At startup of system
operator can open water to accommodate
maximum load. Suppose there is tentative load of
40KW then water should be opened seeing ELM-
104 for reading of 50% (i.e. 50% of 54KW = 27KW).
When machine is already loaded and is in
operation, water through main inlet valve should
be opened in such a manner that ELM display is
between 15-25% which has been seen as optimum
for incomming load acceptance in operation.
8
be seen that all the MCBs are ON. If any MCB is
tripped it should be switched on, if it keeps on
tripping, heaters or wiring should be checked for
any faults.
INDEX OF DRAWINGS
SCHEMETICS
9
SINGLE LINE DIAGRAM 1 OF 20
SYSTEM CONTROL PANEL 2 OF 20
CONTROL PANEL DIMENSIONS & LAYOUT 3 OF 20
DC DISTRIBUTION BOARD DRAWING 4 OF 20
AC AUX. DISTRIBUTION DRAWING 5 OF 20
GEN THREE LINE DIAGRAM CT & PT 6 OF 20
RELAY CONTACT DETAILS 7 OF 20
MASTER TRIP RELAY 86G2 8 OF 20
BREAKER CLOSING AND TRIPING CIRCUIT 9 OF 20
BFV OPENING & CLOSING SCHEME 10 OF 20
ANNUNCIATOR SCHEMATIC 11 OF 20
ELC SCHEMETIC 12 OF 20
ELC DRIVER CARD SCHEMETIC 13 OF 20
ELC DRIVER I THYRISTOR SCHEMETIC 14 OF 20
THYRISTOR SCHEMETIC 15 OF 20
BALLAST LOAD SCHEMETIC 16 OF 20
BALLAST LOAD DIMENSIONS 17 OF 20
BATTERY CHARGER 18 OF 20
TERMINAL BLOCK ARRANGEMENT 19 OF 20
BILL OF MATERIAL PANEL 20 OF 20