MOS Waterproofing
MOS Waterproofing
MOS Waterproofing
Rev. Page
Doc.
Project Package Originator Discipline Unit n° Serial n°
Typ
1 1 / 17
1 - REJECTED
FOR
3 - PROCEED
Authorization to proceed does not relieve Contractor
/Supplier of its responsibility or liability under the
Contract and/or Purchase Order.
Signature :
Document Class : Z
11:48:52
2017.05.22 wct.my, c=MY
2017.05.22 11:49:18
+08'00'
11:56:48 +08'00'
+08'00'
1 22-May-17 IFC Issued for Construction Ervina@Zurinah Mutih Mohd Fazil Mohd Noh Ihsan Idris
0 19-Apr-17 IFC Issued for Construction Siti Rodhiana Mohd Fazil Mohd Noh Ihsan Idris
B 4- Mar-17 IFA-Issued for Approval Nur Najihah Wahab Mohd Fazil Mohd Noh Ihsan Idris
A 2-Feb-17 IFR Issued for Review Nur Najihah Wahab Mohd Fazil Mohd Noh Ihsan Idris
DATE WRITTEN BY
CHECKED BY
APPROVED BY
REV.
STATUS REVISION MEMO
DD-MMM-YY (name & signature) (name & signature)
(name & signature)
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 2 /18
RAPID P0014 0008 CON MST 0001 0109
CONTENTS
1. Introduction
..
.3
2. Acronym and Definition
..4
5. Resources Planning .4
6. Construction Procedures ...5
7. QAQC Aspect . .14
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 3 /18
RAPID P0014 0008 CON MST 0001 0109
1. INTRODUCTION
Integrated Development) to meet both domestic and Asia's energy and chemicals
demand. The RAPID PROJECT consists of a world scale integrated site which
includes Refinery with a deep conversion scheme, 300 000 barrels per stream day
capacity, Naphtha Steam Cracker of 1.28 million tons of ethylene per year capacity;
Complex (PIC) which also includes the following major projects; Pengerang
Water Supply Project (PAMER), Pengerang Deep Water Terminal (PDWT) and Air
Separation Unit (ASU) which provides oxygen and nitrogen gases to the Complex
and to the local market. The RAPID PROJECT is located at Pengerang, Mukim of
Pengerang, Kota Tinggi District, Johor and is in close proximity to the international
shipping lane connecting the Straits of Malacca, Singapore and the South China
Sea.
WCT has been contracted by PRPC Package 14-1702 of RAPID complex. The
Field Auxiliary Rooms, Operator Shelter Buildings and Local Control Building. This
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 4 /18
RAPID P0014 0008 CON MST 0001 0109
Management
PACKAGE means each package of works or supplies
PACKAGE
SUBCONTRACTOR means any company which EPCM
x To outline the sequence of work for Water Proofing and Expansion Joint Work.
The extent of work shall be in accordance with the contract documents inclusive
work.
x To outline preparation or coordination required before start work
x To outline quality plan or inspection test required during project implementation
x To perform safe working environment and compliance to the safety requirements.
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 5 /18
RAPID P0014 0008 CON MST 0001 0109
4. REFERENCE
Reference Description
5. RESOURCES PLANNING
2. Electric Stirrer
3. Squeegee
4. Roller
5. Brush/Broom
7. Glove
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 6 /18
RAPID P0014 0008 CON MST 0001 0109
1 Project Manager
2 Site Quality Manager
3 QAQC Engineer
4 QC Inspector
5 Site Supervisor / Coordinator
6 Safety Supervisor
6. CONSTRUCTION PROCEDURE
6.1.1 Submit for approval and ensure shop drawings have been approved.
6.1.2 Submit for approval and ensure materials have been approved.
6.1.3 Submit and ensure Method Statement, Inspection and Test Plan to
required for the works and ensure adequate water, lighting, power and
(ITP).
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 7 /18
RAPID P0014 0008 CON MST 0001 0109
x Ensure the structure in such condition that apart from final cleaning, it
x The concrete surface shall be smooth and clean. Any sharp projections
shall be removed.
Waterproofing Coating
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 8 /18
RAPID P0014 0008 CON MST 0001 0109
x Dilute one part XYLASTIC-500 to one part water and apply first or
2
0.30kg/m .
x When the first coat still wet or tacky, lay one layer of heavy duty fiber
cured for at least 24 hours beforehand. Plug off all outlets, down pipes
and etc. Then flood with min 25mm of water and leave for 24 hours prior
otherwise to contain the 25mm depth of water, the slab shall be induced
material.
x Lay one layer 0.25mm thick polythene sheet on top of insulation board.
x Place average 65mm thick concrete topping to fall and steel trowel to
x Place average 65mm thick concrete topping to fall and steel trowel to
panel and diamond cut 12mm wide x 8mm deep groove line.
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 9 /18
RAPID P0014 0008 CON MST 0001 0109
sealant.
x Ensure the structure in such condition that apart from final cleaning, it
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 10 /18
RAPID P0014 0008 CON MST 0001 0109
x The concrete surface shall be smooth and clean. Any sharp projections
shall be removed.
2
modified polyurethane waterproofing membrane at the rate of 0.5kg/m
Per coat onto proper prepared concrete surface, all in accordance with
manufacturers instruction.
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 11 /18
RAPID P0014 0008 CON MST 0001 0109
Surface preparations for both options are same. All surface must be
materials that will bond to the existing substrates and will allow TRITOflex
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 12 /18
RAPID P0014 0008 CON MST 0001 0109
well as for concrete and metal to create a superior bond with the
TRITOflex membrane.
Option 1
Application methods for external, internal and external wall in option 1 are
same. Supply and spray apply one layer of 1.5mm thick TRITOflex instant
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 13 /18
RAPID P0014 0008 CON MST 0001 0109
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 14 /18
RAPID P0014 0008 CON MST 0001 0109
Option 2
Application methods for external, internal and external wall in option 2 are
same. Supply and spray apply one layer of 2.0mm thick TRITOflex instant
bolt.
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 15 /18
RAPID P0014 0008 CON MST 0001 0109
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 16 /18
RAPID P0014 0008 CON MST 0001 0109
7. QAQC ASPECT
7.1 The purpose of the quality control is to provide a guideline for a proper
o All quality matters shall follows as per MS ISO 9001 : 2000 and Project
referenced RAPID-P0014-OUI-CON-PRC-0001-2006_0
x Safety and health aspects at site shall adhere strictly to the requirements
x All machinery and equipment are to be checked at the site to ensure that it
experience.
available at site.
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 17 /18
RAPID P0014 0008 CON MST 0001 0109
x All supervisor and workers are to use PPE safety requirements at site area
at all time. Where site condition is damp and wet the use of rubber boots in
which has been reinforced by steel not only in the toes but also in the soles
is essential.
x The site shall be kept clean and clear of unnecessary obstruction. First aid
areas.
and health plan for the project site shall be conducted to achieve a secure
working environment.
o 100% tie off while working at roof by using proper anchor point
(lifeline)
roof.
JV.
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization
Typ
1 18 /18
RAPID P0014 0008 CON MST 0001 0109
scaffold is erected.
o Adequate anchor points with life lines shall be provided for workers
stage.
during dismantling.
"In accordance with Article 41 of the Conditions of Contract, the ownership in this document shall vest in OWNER. No part of this document may be reproduced, stored in a retrieval
system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the OWNER.
CONFIDENTIAL Not to disclose without authorization