Agusan Del Sur Executive Summary 2018
Agusan Del Sur Executive Summary 2018
Agusan Del Sur Executive Summary 2018
A. Introduction
1. The Province of Agusan del Sur was created on June 17, 1967 by virtue of
Republic Act No. 4979 which provided for the division of the former Agusan
into what is now Agusan del Norte and Agusan del Sur. It formally came into
existence as an independent political entity in January 1970 when the first set
of provincial officials assumed office after the provincial election in November
1969. The same law provided that the capital of Agusan del Sur shall be the
Municipality of Prosperidad and the Government Center was then set up in
Barangay Patin-ay. Through the efforts and efficient management of the
Provincial Government, it is now classified as a first-class province comprising
of thirteen (13) municipalities, one component city and 318 barangays.
2. The audit was conducted in accordance with applicable legal and regulatory
requirements, and the Philippine Public Sector Standards on Auditing. Those
standards require that we plan and perform the audit to obtain a reasonable basis
for our conclusions.
3. The audit covered the accounts and operations of the provincial government for
the year 2018 and was aimed at ascertaining the propriety of financial
transactions, management’s compliance to prescribed rules and regulations and
the fairness of the presentation of the financial statements. Value for money
audit was also conducted on the selection and implementation of projects funded
out of the 20% development fund and other programs and projects to determine
whether the objectives of the projects were attained in the most efficient,
effective and economical manner.
B. Financial Highlights
Financial Position
(In Billions of Pesos)
2018 2017
9.00
8.00
7.00
6.00
5.00
4.00
3.00
2.00
1.00
0.00
Assets Liabilities Government Equity
The chart shows the comparison of the agency’s financial position for the
periods 2017 and 2018, clustered by elements - assets, liabilities and equity. It
can be observed in the graph above that in 2018, the assets, liabilities and
government equity increased by 22% from that of CY 2017.
In the chart below, we can also observe that in CY 2018 the revenue and
expenses is higher by 6% and17%, respectively, while the net income decreased
by 8% as compared to CY 2017.
Financial Performance
(In Billions of Pesos)
2018 2017
2.50
2.00
1.50
1.00
0.50
0.00
Income Expenses Net Income
5. For the above-mentioned audit observations which have caused the issuance of
a qualified opinion, we recommend the following:
ii. The Management to reconcile the PPE accounts with the records of the
Inventory Committee during the annual physical count. Moreover, the Public
Infrastructure accounts included in the Inventory records should also be booked
up in the book of accounts of the accounting office. Also, coordinate with the
accounting unit on the reconciliation of records between the report of result of
physical inventory, as against the Property, Plant and Equipment Ledger Cards
of the accounting office.
iii. The Management to follow the rules and regulations in granting fund transfers
to LGUs with unliquidated balances and send follow-up demand letters to
remind them of their obligation to liquidate.
6. The other audit observations and recommendations are as follows:
ii. Two infrastructure projects funded under the Conditional Matching Grant to
Provinces (CMGP) for Road Repair, Rehabilitation and Improvement in the
total amount of Php81,319,698.18 and one under the Philippine Rural
Development Project (PRDP) incurred negative slippages of 8% to 9.2%.
iii. Bank service charges in the total amount of Php5,200.00 were incurred due to
depository accounts with balances below the required minimum maintaining
balance causing unnecessary expenditures that resulted to loss and wastage of
government funds.
We recommended that the Management enjoin the Bids and Awards Committee
to expedite the procurement process so as to achieve the timely acquisition of
goods, works and services in support to the program implementation.
v. Some Contract Agreements and Purchase Orders were entered into by both of
the contracting parties beyond the maximum calendar days allowed for contract
preparation and signing activity.
vi. The BAC did not send a notification to observers during the Post-Qualification
stage of the procurement process of the Lowest Calculated Bid as mandated
under Section 13.1 of the Implementing Rules and Regulations (IRR) of
Republic Act (RA) No. 9184.
We recommended that BAC and TWG properly evaluate the surety bond issued
by an insurance company as either performance security or bid security and
ensure that a certification from the Insurance Commission is attached before the
recommendation of Award to the Head of the Procuring Entity, in compliance
to Item c of sections 27.2 & 39.2 of RA 9184.
viii. Bona fide suppliers cannot be properly ascertained considering that a registered
general merchandise and / or trading establishments were awarded with the PO
to supply all kinds of goods from a very simple supply to a high – end quality
merchandise.
ix. Unutilized appropriation for Local Disaster Risk Reduction Management Fund
(LDRRMF) in the total amount of Php3,154,765.51 aged five years and above
were not reverted to unappropriated surplus of the General Fund as mandated
under item 5.1.13 of COA Circular 2012 – 002 dated September 12, 2012.
xi. Some Acceptance and Inspection Reports were not submitted to the office of
the Auditor neither the office notified within 24 hours from acceptance of the
deliveries from suppliers of the goods delivered as mandated under COA
Circular No. 96 – 010 dated August 15, 1996.
We recommended that the Provincial General Services Office notify the office
of the Auditor within twenty four (24) hours from acceptance, the time, date and
place of delivery to give the audit team ample time in the conduct of inspection.
xii. The existing practice in the conduct of inspection by the head of the
requisitioning office casts doubts in the authenticity and propriety of goods
delivered by the suppliers.
We recommended that the Management follow the rules and regulations on the
payment of RATA to the position that is not authorized in an LGU staffing
pattern pursuant to item 9.1.1 of the LBC No. 103 dated May 15, 2013.
xiv. The Provincial Government paid Transportation Allowances in the total amount
of Php411,050.00 to personnel despite being assigned with government vehicles
contrary to Section 8.2 of Local Budget Circular No. 103 dated May 15 2013.
xvi. A deficiency in the total amount of Php6,686,024.30 for six contracts entered
into by/ and between PGAS and different contractors was noted in the technical
review and contract cost evaluation.
xvii. The physical accomplishment percentage of 32.07% during the year is far below
the expected utilization of the 20%PDF and physical accomplishments target,
thus depriving the intended beneficiaries of the timely benefits derived from the
project.
xviii. Optimal utilization of the Special Education Fund (SEF) was not fully achieved
as some of the Programs, Projects and Activities budgeted for the year with total
appropriation of Php56,279,979.18 were not fully implemented.
8. Out of the 22 audit recommendations in CY 2017 AAR, seven (7) were fully
implemented and 15 were partially implemented. Three (3) of the partially
implemented recommendations are reiterated in Part II of this report.