BILL OF QUANTITIES

REFERENCE NUMBER: 3161366


ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

Proposed Barangay Health Center, Barangay Cogon, Calceta., Tagbilaran City

Item Unit Price


Description/Scope of Works Quantity Unit Amount (Pesos)
No. (Pesos)

Proposed Barangay Health Center


I EQUIPMENT RENTAL 80.00 days 850.00 68,000.00
II EXCAVATION 65.45 cu.m. 1,300.00 85,085.00
III CONCRETE WORKS 51.27 cu.m. 20,000.00 1,025,400.00
IV MASONRY WORKS 325.00 sq.m. 1,400.00 455,000.00
V ROOFING SHEETS & ITS FRAMING 70.00 sq.m. 2,600.00 182,000.00
VI ELECTRICAL 61.00 outlet 2,000.00 122,000.00
VII FORMS & SCAFFOLDING 1.00 lot 153,372.00 153,372.00
VIII CEILING BOARDS & ITS FRAMING 140.00 sq.m. 1,000.00 140,000.00
IX DOORS & WINDOWS 1.00 lot 260,000.00 260,000.00
X PAINTING 460.00 sq.m. 300.00 138,000.00
XI SEPTIC TANK 10.20 sq.m. 6,000.00 61,200.00
XII PLUMBING, FIXTURES, FITTINGS & TILES 95.85 sq.m. 1,500.00 143,775.00
XIII SOIL POISONING 144.00 sq.m. 150.00 21,600.00
XIV RAILINGS 9.72 sq.m. 3,500.00 34,020.00
TOTAL P 2,889,452.00

Submitted by:

May 20, 2015


Date
MANUELITO F. VARQUEZ JR.
Name of Representative of the Bidder

OWNER/PROPRIETOR
Position

AL CHRIS CONSTRUCTION
Name of the Bidder
DETAILED COST ESTIMATE

REFERENCE NUMBER: 3161366


ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

Page 1
Unit Cost 850.00
DERIVATION OF UNIT COST
Quantity 80.00 days

Item of Work : I

Work Description : EQUIPMENT RENTAL


DESCRIPTION UNIT QUANTITY Unit COST AMOUNT
A. ESTIMATED DIRECT COST
1. MATERIAL COST
NONE

TOTAL OF MATERIAL COST: -


2. LABOR:
NONE

3. EQUIPMENT COST:
1 Jack Hammer day 4 800.00 3,200.00
1 Concrete Mixer day 14 800.00 11,200.00
1 Concrete Vibrator day 14 450.00 6,300.00
1 Compressor day 14 450.00 6,300.00
1 Dump Truck day 10 1,000.00 10,000.00
1 Welding Machine day 12 700.00 8,400.00
1 Manual Bar Cutter day 12 450.00 5,400.00

TOTAL OF LABOR AND EQUIPMENT: 50,800.00

TOTAL OF A (Estimated Direct Cost) 50,800.00


Plus:
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 2,540.00
Profit 7,374.29
2,294.29
TOTAL OF B 9,914.29
Plus
Value Added Tax (VAT) (12% of A & B) 7,285.71

TOTAL COST OF WORK ITEM 68,000.00


TOTAL UNIT COST (Total Cost of Work Item/Quantity) 850.00

Submitted by:

MANUELITO F. VARQUEZ, JR
Proprietor/Manager
AL CHRIS CONSTRUCTION
DETAILED COST ESTIMATE

REFERENCE NUMBER: 3161366


ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

Page 2
Unit Cost 1,300.00
DERIVATION OF UNIT COST
Quantity 65.45 cu.m.

Item of Work : II

Work Description : EXCAVATION


DESCRIPTION UNIT QUANTITY Unit COST AMOUNT
A. ESTIMATED DIRECT COST
1. MATERIAL COST
NONE

TOTAL OF MATERIAL COST: -


2. LABOR:
1 Project Engineer/Safety Officer days 18 500.00 9,000.00
1 Foreman days 18 400.00 7,200.00
14 Laborers days 18 250.00 63,000.00

3. EQUIPMENT COST:
Includes in Item I - Equipment Rental -

TOTAL OF LABOR AND EQUIPMENT: 63,000.00

TOTAL OF A (Estimated Direct Cost) 63,000.00


Plus:
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 3,150.00
Profit 9,818.75
3,518.75
TOTAL OF B 12,968.75
Plus
Value Added Tax (VAT) (12% of A & B) 9,116.25

TOTAL COST OF WORK ITEM 85,085.00


TOTAL UNIT COST (Total Cost of Work Item/Quantity) 1,300.00

Submitted by:

MANUELITO F. VARQUEZ, JR
Proprietor/Manager
AL CHRIS CONSTRUCTION
DETAILED COST ESTIMATE

REFERENCE NUMBER: 3161366


ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

Page 3
Unit Cost 20,000.00
DERIVATION OF UNIT COST
Quantity 51.27 cu.m.

Item of Work : III

Work Description : CONCRETE WORKS


DESCRIPTION UNIT QUANTITY Unit COST AMOUNT
A. ESTIMATED DIRECT COST
1. MATERIAL COST
Portland Cement bags 545.00 255.00 138,975.00
Sand cu.m. 72.00 1,300.00 93,600.00
Gravel cu.m. 36.00 1,100.00 39,600.00
20mm dia. Deformed Bars pcs 190.00 560.00 106,400.00
16 mm dia Deformed Bars pcs 70.00 390.00 27,300.00
12mm dia. Deformed Bars pcs 222.00 195.00 43,290.00
10mm dia. Deformed Bars pcs 540.00 150.00 81,000.00
#16 Tie Wire kls 160.00 60.00 9,600.00

TOTAL OF MATERIAL COST: 539,765.00


2. LABOR:
1 Project Engineer/Safety Officer days 30 500.00 15,000.00
1 Foreman days 30 400.00 12,000.00
1 Materials Lab. Tech. days 5 400.00 2,000.00
9 Mason / Carpenter days 30 350.00 94,500.00
5 Steel man days 30 350.00 52,500.00
14 Laborer days 30 250.00 105,000.00

3. EQUIPMENT COST:
Includes in Item I - Equipment Rental

TOTAL OF LABOR AND EQUIPMENT: 281,000.00

TOTAL OF A (Estimated Direct Cost) 820,765.00


Plus:
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 41,038.25
Profit 53,732.46
(28,344.04)
TOTAL OF B 94,770.71
Plus
Value Added Tax (VAT) (12% of A & B) 109,864.29

TOTAL COST OF WORK ITEM 1,025,400.00

TOTAL UNIT COST (Total Cost of Work Item/Quantity) 20,000.00


Submitted by:

MANUELITO F. VARQUEZ, JR
Proprietor/Manager
AL CHRIS CONSTRUCTION
DETAILED COST ESTIMATE

REFERENCE NUMBER: 3161366


ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

Page 4
Unit Cost 1,400.00
DERIVATION OF UNIT COST
Quantity 325.00 sq.m.

Item of Work : IV

Work Description : MASONRY WORKS


DESCRIPTION UNIT QUANTITY Unit COST AMOUNT
A. ESTIMATED DIRECT COST
1. MATERIAL COST
CHB pcs 4,080.00 16.00 65,280.00
Cement bags 445.00 255.00 113,475.00
Sand cu.m. 27.00 1,300.00 35,100.00
10mm dia. Deformed Bars pcs 237.00 150.00 35,550.00
Tie Wire kilo 35.00 60.00 2,100.00

TOTAL OF MATERIAL COST: 251,505.00


2. LABOR:
1 Project Engineer/Safety Officer days 30 500.00 15,000.00
1 Foreman days 30 400.00 12,000.00
4 Mason days 30 350.00 42,000.00
5 Laborer days 30 250.00 37,500.00

3. EQUIPMENT COST:
Includes in Item I - Equipment Rental

TOTAL OF LABOR AND EQUIPMENT: 106,500.00

TOTAL OF A (Estimated Direct Cost) 358,005.00


Plus:
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 17,900.25
Profit 30,344.75
(5,455.75)
TOTAL OF B 48,245.00
Plus
Value Added Tax (VAT) (12% of A & B) 48,750.00

TOTAL COST OF WORK ITEM 455,000.00

TOTAL UNIT COST (Total Cost of Work Item/Quantity) 1,400.00


Submitted by:

MANUELITO F. VARQUEZ, JR
Proprietor/Manager
AL CHRIS CONSTRUCTION
DETAILED COST ESTIMATE

REFERENCE NUMBER: 3161366


ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

Page 5
Unit Cost 2,600.00
DERIVATION OF UNIT COST
Quantity 70.00 sq.m.

Item of Work : V

Work Description : ROOFING SHEETS & ITS FRAMING


DESCRIPTION UNIT QUANTITY Unit COST AMOUNT
A. ESTIMATED DIRECT COST
1. MATERIAL COST
Rib Type Long Span (0.40 x 0.990 x LS) ln.m 80.00 480.00 38,400.00
Colored G.I. Flushing (0.4 x 0.305 x 2.44) sht 12.00 290.00 3,480.00
Blind Rivets pcs 350.00 0.60 210.00
Tek Screw pcs 700.00 1.75 1,225.00
Elastoseal qrts. 2.00 400.00 800.00
1/4" X 2" Flat Bar pcs 2.00 360.00 720.00
3/16" x 1 1/2" x 1 1/2" Angle Bar pcs 50.00 320.00 16,000.00
1/4" 1 1/2" 1 1/2" Angle Bar pcs 14.00 875.00 12,250.00
2" x 4" CEE Purlins (1.2mm) pcs 22.00 570.00 12,540.00
1/2" dia. X 30 Turn Buckle pcs 16.00 190.00 3,040.00
10mm dia. Def. Bars (Sag Rod) pcs 6.00 155.00 930.00
12 mm dia. Def. Bar (Cross Bracing) pcs 16.00 200.00 3,200.00
Welding Rod box 4.00 2,750.00 11,000.00
Red Lead gals 2.00 475.00 950.00
Aluminum Paint gals 2.00 645.00 1,290.00
Paint Thinner gals 2.00 360.00 720.00
Pain Brush 2" pcs 5.00 42.00 210.00
Touch-up Paint cans 2.00 175.00 350.00

TOTAL OF MATERIAL COST: 107,315.00


2. LABOR:
1 Project Engineer/Safety Officer days 12 500.00 6,000.00
1 Foreman days 12 400.00 4,800.00
2 Welder days 12 350.00 8,400.00
4 Laborer days 12 250.00 12,000.00

3. EQUIPMENT COST:
Includes in Item I - Equipment Rental

TOTAL OF LABOR AND EQUIPMENT: 31,200.00

TOTAL OF A (Estimated Direct Cost) 138,515.00


Plus:
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 6,925.75
Profit 17,059.25
3,207.75
TOTAL OF B 23,985.00
Plus
Value Added Tax (VAT) (12% of A & B) 19,500.00

TOTAL COST OF WORK ITEM 182,000.00

TOTAL UNIT COST (Total Cost of Work Item/Quantity) 2,600.00


Submitted by:

MANUELITO F. VARQUEZ, JR
Proprietor/Manager
AL CHRIS CONSTRUCTION
DETAILED COST ESTIMATE

REFERENCE NUMBER: 3161366


ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

Page 6
Unit Cost 2,000.00
DERIVATION OF UNIT COST
Quantity 61.00 outlet

Item of Work : VI

Work Description : ELECTRICAL


DESCRIPTION UNIT QUANTITY Unit COST AMOUNT
A. ESTIMATED DIRECT COST
1. MATERIAL COST
Utility Box pcs 20.00 24.00 480.00
Junction Box pcs 20.00 35.00 700.00
Electrical Pipe 1" dia. pcs 10.00 145.00 1,450.00
Electrical Pipe 1/2" dia. pcs 30.00 55.00 1,650.00
Flourescent Lamp set 24.00 330.00 7,920.00
No. 12 THHN Stranded Wire roll 5.00 4,550.00 22,750.00
No. 14 TW Stranded Wire roll 5.00 2,850.00 14,250.00
Panel Board set 1.00 1,650.00 1,650.00
Circuit Breaker pcs 5.00 600.00 3,000.00
Single Switch Flash Type set 2.00 72.00 144.00
2 Gang Conv. Outlet Flush Type set 24.00 133.00 3,192.00
2 Gang Switch Flush type set 28.00 112.50 3,150.00

TOTAL OF MATERIAL COST: 60,336.00


2. LABOR:
1 Foreman days 30 400.00 12,000.00
2 Electrician days 30 300.00 18,000.00

3. EQUIPMENT COST:
Includes in Item I - Equipment Rental

TOTAL OF LABOR AND EQUIPMENT: 30,000.00

TOTAL OF A (Estimated Direct Cost) 90,336.00


Plus:
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 4,516.80
Profit 14,075.77
5,042.17
TOTAL OF B 18,592.57
Plus
Value Added Tax (VAT) (12% of A & B) 13,071.43

TOTAL COST OF WORK ITEM 122,000.00


TOTAL UNIT COST (Total Cost of Work Item/Quantity) 2,000.00

Submitted by:

MANUELITO F. VARQUEZ, JR
Proprietor/Manager
AL CHRIS CONSTRUCTION
DETAILED COST ESTIMATE

REFERENCE NUMBER: 3161366


ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

Page 7
Unit Cost 153,372.00
DERIVATION OF UNIT COST
Quantity 1.00 lot

Item of Work : VII

Work Description : FORMS & SCAFFOLDING


DESCRIPTION UNIT QUANTITY Unit COST AMOUNT
A. ESTIMATED DIRECT COST
1. MATERIAL COST
2" x 2" x 12' Coco Lumber pcs 200 80.00 16,000.00
2" x 3" x 12' Coco Lumber pcs 200 115.00 23,000.00
2" x 3" x 8' Coco Lumber pcs 100 58.00 5,800.00
1/2" x 4' x 8' Marine Plywood shts. 50 760.00 38,000.00
No. 4" Common Nails box 4 2,200.00 8,800.00
No. 3" Common Nails box 1 2,200.00 2,200.00
No. 2" Common Nails box 1 2,200.00 2,200.00
No. 1" Common Nails kg 15.00 65.00 975.00

TOTAL OF MATERIAL COST: 96,975.00


2. LABOR:
1 Project Engineer/Safety Officer days 12 500.00 6,000.00
1 Foreman days 12 400.00 4,800.00
4 Laborers days 12 250.00 12,000.00

3. EQUIPMENT COST:
Includes in Item I - Equipment Rental

TOTAL OF LABOR AND EQUIPMENT: 22,800.00

TOTAL OF A (Estimated Direct Cost) 119,775.00


Plus:
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 5,988.75
Profit 11,175.54
(801.96)
TOTAL OF B 17,164.29
Plus
Value Added Tax (VAT) (12% of A & B) 16,432.71

TOTAL COST OF WORK ITEM 153,372.00


TOTAL UNIT COST (Total Cost of Work Item/Quantity) 153,372.00

Submitted by:

MANUELITO F. VARQUEZ, JR
Proprietor/Manager
AL CHRIS CONSTRUCTION
DETAILED COST ESTIMATE

REFERENCE NUMBER: 3161366


ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

Page 8
Unit Cost 1,000.00
DERIVATION OF UNIT COST
Quantity 140.00 sq.m.

Item of Work : VIII

Work Description : CEILING BOARDS & ITS FRAMING


DESCRIPTION UNIT QUANTITY Unit COST AMOUNT
A. ESTIMATED DIRECT COST
1. MATERIAL COST
1/4" Thick Cement Board sht. 52.00 525.00 27,300.00
2"x2"x10' S4S Matwood pcs 92.00 368.00 33,856.00
Ceiling Ventilation 4' pcs 10.00 325.00 3,250.00
Solignum Wood Preservaties gal 5.00 1,330.00 6,650.00
Paint Brush 2'' pc. 5.00 35.00 175.00
No. 2" Common Nails box 2.00 2,200.00 4,400.00
No. 3" Common Nails box 2.00 2,200.00 4,400.00
No. 1" Finishing Nails kg 7.00 65.00 455.00
No. 2" Finishing Nails kg 7.00 65.00 455.00

TOTAL OF MATERIAL COST: 80,941.00


2. LABOR:
1 Project Engineer/Safety Officer days 10 500.00 5,000.00
1 Foreman days 12 400.00 4,800.00
7 Laborers days 12 250.00 21,000.00

3. EQUIPMENT COST:
Includes in Item I - Equipment Rental

TOTAL OF LABOR AND EQUIPMENT: 30,800.00

TOTAL OF A (Estimated Direct Cost) 111,741.00


Plus:
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 5,587.05
Profit 7,671.95
(3,502.15)
TOTAL OF B 13,259.00
Plus
Value Added Tax (VAT) (12% of A & B) 15,000.00

TOTAL COST OF WORK ITEM 140,000.00


TOTAL UNIT COST (Total Cost of Work Item/Quantity) 1,000.00

Submitted by:

MANUELITO F. VARQUEZ, JR
Proprietor/Manager
AL CHRIS CONSTRUCTION
DETAILED COST ESTIMATE

REFERENCE NUMBER: 3161366


ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

Page 9
Unit Cost 260,000.00
DERIVATION OF UNIT COST
Quantity 1.00 lot

Item of Work : IX

Work Description : DOORS & WINDOWS


DESCRIPTION UNIT QUANTITY Unit COST AMOUNT
A. ESTIMATED DIRECT COST
1. MATERIAL COST
0.80x2.10Flush Door w/2"x4" DoorJamb set 7.00 3,500.00 24,500.00
0.70x2.10 PVC Door set 2.00 1,900.00 3,800.00
Anolok Frame Windows sq.m. 47.28 2,400.00 113,472.00
Door Lock pc. 9.00 400.00 3,600.00
3"x3" Lose Pin Hinges pairs 12.00 65.00 780.00
0.80x2.10m Anolok Frame Swing Door set 2.00 14,000.00 28,000.00

TOTAL OF MATERIAL COST: 174,152.00


2. LABOR:
1 Project Engineer/Safety Officer days 12 500.00 6,000.00
1 Foreman days 12 400.00 4,800.00
7 Laborers days 12 250.00 21,000.00

3. EQUIPMENT COST:
Includes in Item I - Equipment Rental

TOTAL OF LABOR AND EQUIPMENT: 31,800.00

TOTAL OF A (Estimated Direct Cost) 205,952.00


Plus:
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 10,297.60
Profit 15,893.26
(4,701.94)
TOTAL OF B 26,190.86
Plus
Value Added Tax (VAT) (12% of A & B) 27,857.14

TOTAL COST OF WORK ITEM 260,000.00


TOTAL UNIT COST (Total Cost of Work Item/Quantity) 260,000.00

Submitted by:

MANUELITO F. VARQUEZ, JR
Proprietor/Manager
AL CHRIS CONSTRUCTION
DETAILED COST ESTIMATE

REFERENCE NUMBER: 3161366


ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

Page 10
Unit Cost 300.00
DERIVATION OF UNIT COST
Quantity 460.00 sq.m.

Item of Work : X

Work Description : PAINTING


DESCRIPTION UNIT QUANTITY Unit COST AMOUNT
A. ESTIMATED DIRECT COST
1. MATERIAL COST
Acrytex Primer gal. 25.00 950.00 23,750.00
Flatwall Enamel gal. 2.00 690.00 1,380.00
Quick Drying Enamel gal. 2.00 760.00 1,520.00
Semi-Gloss Latex Interior Paint gal. 14.00 760.00 10,640.00
Oil Tinting Color 1/4 qrt 12.00 89.00 1,068.00
Elastomeric Paint gal. 16.00 890.00 14,240.00
Paint Thinner gal. 4.00 365.00 1,460.00
Acrytex Reducer gal. 14.00 500.00 7,000.00
4" Roller Brush w/ tray & Handle pc. 7.00 90.00 630.00
Paint Brush 2" pc. 7.00 50.00 350.00

TOTAL OF MATERIAL COST: 62,038.00


2. LABOR:
1 Foreman days 12 400.00 4,800.00
7 Painter days 12 400.00 33,600.00
4 Labor days 12 250.00 12,000.00

3. EQUIPMENT COST:
Includes in Item I - Equipment Rental

TOTAL OF LABOR AND EQUIPMENT: 50,400.00

TOTAL OF A (Estimated Direct Cost) 112,438.00


Plus:
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 5,621.90
Profit 5,154.39
(6,089.41)
TOTAL OF B 10,776.29
Plus
Value Added Tax (VAT) (12% of A & B) 14,785.71

TOTAL COST OF WORK ITEM 138,000.00


TOTAL UNIT COST (Total Cost of Work Item/Quantity) 300.00

Submitted by:

MANUELITO F. VARQUEZ, JR
Proprietor/Manager
AL CHRIS CONSTRUCTION
DETAILED COST ESTIMATE

REFERENCE NUMBER: 3161366


ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

Page 10
Unit Cost 261.72
DERIVATION OF UNIT COST
Quantity 460.00 sq.m.

Item of Work : X

Work Description : PAINTING


DESCRIPTION UNIT QUANTITY Unit COST AMOUNT
A. ESTIMATED DIRECT COST
1. MATERIAL COST
Durapats Body Filler gal. 15.00 630.00 9,450.00
Sphertex Primer gal. 20.00 745.00 14,900.00
Sphertex Reducer gal. 6.00 565.00 3,390.00
Roller No. 7 pcs 8.00 67.50 540.00
Brush No. 1 pcs 8.00 34.75 278.00
Roller Plate pcs 16.00 25.00 400.00
Sand Paper No. 120 pcs 4.00 14.00 56.00
Semi-Gloss Latex (final paint) gal. 14.00 851.00 11,914.00
Flat Latex Sphero gal. 12.00 620.00 7,440.00
-
-
-
-
-

TOTAL OF MATERIAL COST: 48,368.00


2. LABOR:
1 Foreman days 12 400.00 4,800.00
7 Painter days 12 400.00 33,600.00
4 Labor days 12 250.00 12,000.00

3. EQUIPMENT COST:
Includes in Item I - Equipment Rental

TOTAL OF LABOR AND EQUIPMENT: 50,400.00

TOTAL OF A (Estimated Direct Cost) 98,768.00


Plus:
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 4,938.40
Profit 3,787.39
(6,089.41)
TOTAL OF B 8,725.79
Plus
Value Added Tax (VAT) (12% of A & B) 12,899.25

TOTAL COST OF WORK ITEM 120,393.04

TOTAL UNIT COST (Total Cost of Work Item/Quantity) 261.72

Submitted by:

MANUELITO F. VARQUEZ, JR
Proprietor/Manager
AL CHRIS CONSTRUCTION
DETAILED COST ESTIMATE

REFERENCE NUMBER: 3161366


ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

Page 11
Unit Cost 6,000.00
DERIVATION OF UNIT COST
Quantity 10.20 sq.m.

Item of Work : XI

Work Description : SEPTIC TANK


DESCRIPTION UNIT QUANTITY Unit COST AMOUNT
A. ESTIMATED DIRECT COST
1. MATERIAL COST
Portland Cement bag 36.00 255.00 9,180.00
Riversand cu.m. 3.00 1,300.00 3,900.00
Gravel cu.m. 5.00 1,100.00 5,500.00
12mmΦ Def. Bars pcs 15.00 195.00 2,925.00
10mmΦ Def. Bars pcs 30.00 150.00 4,500.00
4" CHB pc. 350.00 15.00 5,250.00
# 16 G.I Wire kg. 4.00 60.00 240.00
Piping Accessories lot 1.00 1,700.00 1,700.00

TOTAL OF MATERIAL COST: 33,195.00


2. LABOR:
1 Mason days 12 400.00 4,800.00
1 Plumber days 10 400.00 4,000.00
2 Labor days 12 250.00 6,000.00

3. EQUIPMENT COST:
Includes in Item I - Equipment Rental

TOTAL OF LABOR AND EQUIPMENT: 14,800.00

TOTAL OF A (Estimated Direct Cost) 47,995.00


Plus:
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 2,399.75
Profit 4,248.11
(551.39)
TOTAL OF B 6,647.86
Plus
Value Added Tax (VAT) (12% of A & B) 6,557.14

TOTAL COST OF WORK ITEM 61,200.00


TOTAL UNIT COST (Total Cost of Work Item/Quantity) 6,000.00

Submitted by:

MANUELITO F. VARQUEZ, JR
Proprietor/Manager
AL CHRIS CONSTRUCTION
DETAILED COST ESTIMATE

REFERENCE NUMBER: 3161366


ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

Page 12
Unit Cost 1,500.00
DERIVATION OF UNIT COST
Quantity 95.85 sq.m.

Item of Work : XII

Work Description : PLUMBING, FIXTURES, FITTINGS & TILES


DESCRIPTION UNIT QUANTITY Unit COST AMOUNT
A. ESTIMATED DIRECT COST
1. MATERIAL COST
16"x16" Ceramic Floor Tiles pc. 430.00 96.00 41,280.00
8"x8" Ceramic Tiles pc. 700.00 20.00 14,000.00
Stainless Sink set 1.00 4,000.00 4,000.00
Portland Cement cu.m 30.00 255.00 7,650.00
Riversand cu.m 3.00 1,300.00 3,900.00
Tile Grout pack 35.00 70.00 2,450.00
Water Closet set 1.00 4,000.00 4,000.00
Lavatory set 1.00 2,800.00 2,800.00
Plumbing Lines & Fittings unit 1.00 3,000.00 3,000.00

TOTAL OF MATERIAL COST: 83,080.00


2. LABOR:
1 Foreman days 12 400.00 4,800.00
2 Mason days 12 400.00 9,600.00
1 Plumber days 10 400.00 4,000.00
4 Labor days 12 250.00 12,000.00

3. EQUIPMENT COST:
Includes in Item I - Equipment Rental

TOTAL OF LABOR AND EQUIPMENT: 25,600.00

TOTAL OF A (Estimated Direct Cost) 108,680.00


Plus:
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 5,434.00
Profit 14,256.54
3,388.54
TOTAL OF B 19,690.54
Plus
Value Added Tax (VAT) (12% of A & B) 15,404.46

TOTAL COST OF WORK ITEM 143,775.00


TOTAL UNIT COST (Total Cost of Work Item/Quantity) 1,500.00

Submitted by:

MANUELITO F. VARQUEZ, JR
Proprietor/Manager
AL CHRIS CONSTRUCTION
DETAILED COST ESTIMATE

REFERENCE NUMBER: 3161366


ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

Page 13
Unit Cost 150.00
DERIVATION OF UNIT COST
Quantity 144.00 sq.m.

Item of Work : XIII

Work Description : SOIL POISONING


DESCRIPTION UNIT QUANTITY Unit COST AMOUNT
A. ESTIMATED DIRECT COST
1. MATERIAL COST
Soil Poisoning sq.m. 144.00 120.00 17,280.00
(Including Labor)

TOTAL OF MATERIAL COST: 17,280.00


2. LABOR:

3. EQUIPMENT COST:
Includes in Item I - Equipment Rental

TOTAL OF LABOR AND EQUIPMENT: -

TOTAL OF A (Estimated Direct Cost) 17,280.00


Plus:
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 864.00
Profit 1,141.71
(586.29)
TOTAL OF B 2,005.71
Plus
Value Added Tax (VAT) (12% of A & B) 2,314.29

TOTAL COST OF WORK ITEM 21,600.00

TOTAL UNIT COST (Total Cost of Work Item/Quantity) 150.00


Submitted by:

MANUELITO F. VARQUEZ, JR
Proprietor/Manager
AL CHRIS CONSTRUCTION
DETAILED COST ESTIMATE

REFERENCE NUMBER: 3161366


ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

Page 14
Unit Cost 3,500.00
DERIVATION OF UNIT COST
Quantity 9.72 sq.m.

Item of Work : XIV

Work Description : RAILINGS


DESCRIPTION UNIT QUANTITY Unit COST AMOUNT
A. ESTIMATED DIRECT COST
1. MATERIAL COST
Railings sq.m. 9.72 2,750.00 26,730.00
(Including Labor)

TOTAL OF MATERIAL COST: 26,730.00


2. LABOR:

3. EQUIPMENT COST:
Includes in Item I - Equipment Rental

TOTAL OF LABOR AND EQUIPMENT: -

TOTAL OF A (Estimated Direct Cost) 26,730.00


Plus:
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 1,336.50
Profit 2,308.50
(364.50)
TOTAL OF B 3,645.00
Plus
Value Added Tax (VAT) (12% of A & B) 3,645.00

TOTAL COST OF WORK ITEM 34,020.00

TOTAL UNIT COST (Total Cost of Work Item/Quantity) 3,500.00


Submitted by:

MANUELITO F. VARQUEZ, JR
Proprietor/Manager
AL CHRIS CONSTRUCTION
REFERENCE NUMBER: 3161366
ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
CONSTRUCTION SCHEDULE AND S-CURVE
ITEM PAY ITEM COST PER ITEM Wt.
20 Days 40 Days 60 Days 80 Days
NO. DESCRIPTION PHP %
I Equipment Rental 68,000.00 2.35
II Excavation 85,085.00 2.94
III Concrete Works 1,025,400.00 35.49
IV Masonry Works 455,000.00 15.75
V Roofing Sheets & Its Framing 182,000.00 6.30
VI Electrical 122,000.00 4.22
VII Forms and Scaffolding 153,372.00 5.31
VIII Ceiling Boards & its Framing 140,000.00 4.84
IX Doors & Windows 260,000.00 9.00
X Painting 138,000.00 4.78
XI Septic Tank 61,200.00 2.12
XII Plumbing, Fixtures, Fittings & Tiles 143,775.00 4.97
XIII Soil Poisoning 21,600.00 0.75
XIV Railings 34,020.00 1.18
GRAND TOTAL 2,889,452.00 100.00

Submitted By:

MANUELITO F. VARQUEZ, JR. Date : May 20, 2015


Owner/Proprietor
AL CHRIS CONSTRUCTION
----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
UCTION SCHEDULE AND S-CURVE
80 Days 100 Days 120 Days

--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
REFERENCE NUMBER: 3161366
ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol

----------------------------------------------------------------------------------------------------------------------------------------------------------------------------

CASH FLOW BY QUARTER AND PAYMENT SCHEDULE

PARTICULAR % WT. 1ST QUARTER 2ND QUARTER


ACCOMPLISHMENT 25% 25%
CASH FLOW 722,363.00 722,363.00
CUMULATIVE ACCOMPLISHMENT 25% 50%
CUMULATIVE CASH FLOW 722,363.00 1,444,726.00

Submitted by:

MANUELITO F. VARQUEZ, JR.


Name & Signature of Bidder's Representative

OWNER/PROPRIETOR
Position

AL CHRIS CONSTRUCTION
Name of Bidder

----------------------------------------------------------------------------------------------------------------------------------------------------------------------------
alth Center )

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

Y QUARTER AND PAYMENT SCHEDULE

3RD QUARTER 4TH QUARTER


25% 25%
722,363.00 722,363.00
75% 100%
2,167,089.00 2,889,452.00

Date : May 20, 2015

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------