ESTIMATE FOR THE HOUSE BALANCE WORK OF

Mrs. Ranjani Maddage

Item Description Amount


Rs. Cts.

Bill No. 1 FLOOR, WALL & CEILING FINISHES 1,478,025.00

Bill No. 2 ASPHALT / WATER PROOFING WORK 30,000.00

Bill No.3 WOOD WORK AND METAL WORK 280,000.00

Bill No. 4 PAINTING AND DECORATING WORK 492,575.00

Bill No. 5 FIXING SANITORY FITTINGS 428,350.00

TOTAL ESTIMATED CONSTRUCTION COST 2,708,950.00

……………………..…….. ………….………..……..
DATE NAME & SIGNATURE
BILL OF QUANTITIES

Rate Amount
Item Description Qty Unit
Rs. Cts. Rs. Cts.

1.00 FLOOR, WALL & CEILING FINISHES

UPPER FLOOR

Note:

Rate shall include for;

a. Proper preparation of backgrounds

b. Narrow widths and small quantities.

c. Temporary formwork and rules, screeds and edge


boards.
d. Laying or executing work in bays or between
division or panel strips.

e. Laying or finishing work to flat surfaces, slopes,


falls and currents.
f. Joints between differing types of work and
between new and old work, groin points and other
intersections of curved surfaces.

g. Equal margins, internal angles, fair edges and


arrises.

h. Internal angles and external angles, junctions,


stops and fair ends.

Measurement
The area measured is that in contact with the base.

600mm x 600mm Semi rough pocilain floor tiles


bedded and jointed in cement and sand 1:3 and
pointing with the tile grout to match the colour of tile, on
floor, inclusive of 3/4'' thk cement and sand 1:3
bedding to floors.

1.01 In Living room 310.00 ft2 1,400.00 434,000.00


1.02 In bed room 1 125.00 ft2 1,250.00 156,250.00
1.03 In bed room 2 140.00 ft2 1,250.00 175,000.00
1.04 In toilet 55.00 ft2 1,300.00 71,500.00

C/F
836,750.0

2
BILL OF QUANTITIES

B/F 836,750.0

Wall Finishes

Internally

6.06 300mm x 300mm Semi rough ceramic wall tiles bedded 180.0 ft2 1,150.0 207,000.0
and jointed in cement and sand 1:3 and pointing with
the tile grout to match the colour of tile, on toilet walls
up to 1800mm high, inclusive of 3/4'' thk cement and
sand 1:3 bedding to toilet walls

6.07 20mm thick cement and sand (1:5) plaster finished 1,915.0 ft2 95.0 181,925.0
smooth with lime putty to internal face of walls, columns
and beams.

6.08 -Ditto- Return or reveals not exceeding 75mm wide 185.0 ft2 45.0 8,325.0
Externally

6.09 20mm thick cement sand ( 1:5 ) plaster finished semi


rough with lime putty to external face of walls. 1,350.0 ft2 95.0 128,250.0

20mm thick cement and sand (1:5) plaster finished with 245.0 ft2 3,950.0
wire cut granite stone to external face of walls
6.10 -Ditto- Return or reveals not exceeding 75mm wide 145.0 lft 45.0 6,525.0

Ceiling finishes

plaster finished smooth with lime putty to soffit of


6.11 1,150.0 ft2 95.0 109,250.0
slab,sides and soffits of staircases.

Floor, wall & ceiling finishes carried to Collection 1,478,025.00

3
BILL OF QUANTITIES

Rate Amount
Item Description Qty Unit
Rs. Cts. Rs. Cts.

2.00 ASPHALT / WATER PROOFING WORK

Waterproofing Work

Application of waterproofing membrane " Baralastic " or


equivalent strictly as per manufacturer's specification.
(Unless otherwise specified protection screed
measured separately under wall & floor tilling work)

2.01 Toilet floor with 300mm high up stands and suitable 50.0 ft2 100.0 10,000.0
laps including preparation of concrete surface to
receive the water proofing material.

2.02 Toilet walls including 1:3 cement,sand plaster base to 150.0 ft2 100.0 20,000.0
receive water proofing material.

Asphalt / Waterproofing Work carried to Collection


30,000.0

4
BILL OF QUANTITIES

Rate Amount
Item Description Qty Unit
Rs. Cts. Rs. Cts.
3.00 METAL WORK

Notes in the upper Floor, under this heading apply to


this section as well

Rate shall include for;

a. Hoisting and placing steel stair material in position.

b. Straight cutting and waste.

c. All labour in framing, drilling for bolt etc. and fixing


in position, complete with all nails and screws.

Provide and fix exterior steel stair complete as shown Item 195,000.0
on the drawings, with two layers af antirust and three
layers of oil paint. Cost of needed excavation,
3.01 backfilling, concrete works will bepaid under relevant
items of this B.O.Q

Provide and fix steel 900mm heigh hand rail for exterior Item 85,000.0
steel stair complete as shown on the drawings, with two
layers af antirust and three layers of oil paint.
3.02

Metal works carried to Collection 280,000.00

5
BILL OF QUANTITIES

Rate Amount
Item Description Qty Unit
Rs. Cts. Rs. Cts.

4.00 PAINTING AND DECORATING WORK

Note:

Rate shall include for;

a. All preliminary preparatory work.

b. Touching up workshop or site primed ferrous


metalwork prior to undercoating.

c Rubbing down between coats.

d. All multi-colour work and cutting to line.

e. Removing all articles of ironmongery, hardware


and similar, before painting and replacing after
painting is complete.

f. Painting on beads, hinges, and other fittings,


brackets, bolts, lugs, and the like ( unless
detached from other paintwork or picked out in
different colour )

g. Protection of floor and fittings and cleaning upon


completion.

h. Painting of door and window reveals unless


otherwise measured seperately.

Painting on off-form concrete surfaces

" Off-form concrete surfaces shall mean concrete


surfaces left after removal of formwork. The rates for
painrting on off-form concrete surfaces shall include for
cleaning the exposed concrete surfaces of cement
laitance, removing all loose materials by wire brush or
scraper, removing any ribs or projections and for
rubbing down where these ribs or projections have
been removed, filling all voids with neat cement grout
to bring the entire surfaces to reasonably smooth even
planes.

Internally

4.01 Prepare surface and apply two coats of approved


colour emulsion paint to internal surface of walls. 1,915.00 ft2 155.00 296,825.00
(Including plastering work in damaged door window
reveals)

Externally

4.02 Prepare surface and apply two coats of approved


colour weather resistant emulsion paint to external
surfaces of walls.(Including plastering work in damaged 1,350.00 ft2 145.00 195,750.00
door window reveals)

Painting and decorating carried to Collection 492,575.00

6
BILL OF QUANTITIES

Rate Amount
Item Description Qty Unit
Rs. Cts. Rs. Cts.

5.00 PLUMBING AND DRAINAGE WORKS

INTERNAL PLUMBING

Sanitary Fittings

following sanitary Items will be supplied by


the client at his cost and the bidders to include
only the labour cost for fixing the same.

Low level water closet with cistern fittings & seat


cover, vanity basin, bath tub, wash basin with
pedestal basin, mixer tap, bath mixer tap, shower
mixer tap, bidet mixer, sink mixer tap, sink tap, bib Note
cock, bib tap, angle valves, shower heads, geyser
bi

Rates for all sanitary fittings fixing with necessary


fixing accessories supplied by client and complete Note
with connection to working order.

5.01 Installation of Wash basin , with 1/2'' dia.


chromium plated tap 1'' rubber plug and
chromium plated vitreous china waste water
supply and waste water connection including 1.00 Nr 45,000.00 45,000.00
plastic bottle trap all complete to working order.
white colour)

5.02 Installation Low level closet with low level cistern


fixed on complete with all connection to working
order. Rate shall include for 1/2'' dia. Chromium 1.00 Nr 65,000.00 65,000.00
plated stop cock. (white colour)

5.03 Installation of Chromium plated telephone shower


spout fix with arm and mixer tap including all 1.00 Nr 2,100.00 2,100.00
necessary accessories.

5.04 Installation of Chromium plated towel rail 2'-00''


long, bracket of same material fixed to wall with 1.00 Nr 2,000.00 2,000.00
chromium plated brass screws.

5.05 Installation of Chrome plate Soap tray fixed to wall


with fibre plugs and chromium plated brass
1.00 Nr 1,500.00 1,500.00
screws.

C/F 115,600.00

7
BILL OF QUANTITIES

Rate Amount
Item Description Qty Unit
Rs. Cts. Rs. Cts.
B/F 115,600.00

5.06 Installation Chrome plate Toilet paper holder - do - 1.00 Nr 1,250.00 1,250.00

5.07 Installation Tooth brush holder - do -. 1.00 Nr 1,500.00 1,500.00

5.08 Installation Chromium plated 1/2" dia. stop cock


1.00 Nr 1,500.00 1,500.00
complete as shower.

5.09 Installation Chromium plated swan neck garden


Bib tap 1/2'' dia. including base and overflow 1.00 Nr 2,100.00 2,100.00
connection to storm water drain.

5.10 Installation Hand bidet spray 1.00 Nr 2,250.00 2,250.00

5.11 Installation Bib tap 1.00 Nr 1,250.00 1,250.00

5.12 Installation of Glammable Mirror (Belgium) or


equivalent make comprising 2'-06'' x 3'-00'' glass
mirror with pencil edge and corners rounded with
1/4" wide sand blast boarder 1" away from the 1.00 Nr 4,000.00 4,000.00
edge fixed with brass screws capped with
chromium plated screw caps

5.13 Installation of Chromium plated shower rose 1.00 Nr 7,000.00 7,000.00

Pumps

5.14 Supply and install of one number transfer water


pump "Jinasena" with 1 Nos. float switches or level
sencer's together with associated control panel & 1.00 Nr 115,000.00 115,000.00
wiring required for fully automatic operation.

Gate Valves

5.15 11/4'' dia. gate valve 2.00 8,200.00 16,400.00

5.16 11/4'' dia. Non return valve imported best quality. 1.00 10,500.00 10,500.00

All plumbing works ( wash basin, kitchen sink,


gully traps,etc…) include the connection to the
nearest trap, WC to the nearest vertical sewage
5.17 header in the typical floors and WC in the GF to item 150,000.00
the nearest manhole and include all accessories
including PVC S and caps for all the ends of pipes
at parapet.

Internal Plumbing carried to collection 428,350.00

8
ESTIMATE FOR THE HOUSE BALANCE WORK OF
Mrs. H.A.DANUSHKA ROHAN, 233/82,
BLUEMOUNTAIN HOUSING SCHEME, MORAGODA,
GAMPAHA.