Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Project Monitoring of Turnkey Projects A Study of Panipat Refinery

Project management of Turnkey Projects from an owners prospective involves special emphasis on Project Monitoring skills, critical interventions from time to time and induction of innovative steps to boost the project progress and keep the project on track. The case study of the success story of MS Quality Up-gradation Project at Panipat Refinery, Indian Oil Corporation Ltd., India, emphasizes the interesting issues pertaining to the means and methods the project was put back on track which was facing some rough weather during execution at one point of time and was successfully completed and commissioned as per target.
lans are only good intentions unless they immediately degenerated into hard work (Peter Drucker, Readers Digest, March 1998). To make such a transformation

possible is no easy task unless all-out efforts are made by the project team, and the client has an important role in this endeavor. A case study of MS quality up-gradation project depicts it all.

MS Quality Up-gradation Project: A Synopsis


The MS Quality Up-gradation Project was undertaken at Panipat Refinery to produce improved quality components for MS blend thereby enabling the refinery to

R E P O R T
Project Management
32
HYDROCARBON ASIA, OCT-DEC 2010 Visit our website at: http://www.safan.com

Figure 1. MSQUP Block Flow Diagram

produce MS products meeting Euro-III/ Euro-IV equivalent specs. The Euro norms basically give limiting values of emissions coming out of new vehicles under standard driving conditions with reference fuel. These norms aim at improving quality of fuel by achieving reduction in benzene, sulphur, olefins & aromatic contents and improvement in octane number. Quality up-gradation projects have followed time bound implementation as per judicial guidelines and have now become projects working on Operating Necessity model. Further quality being one of the key aspects of the companys new vision, these projects are in sync with the companys strategic objectives. Process involved in the project A block flow diagram of MSQUP project which gives a birds eye view of the processes involved in the project is presented in Figure 1.

Execution Methodology Adopted The plant was divided into two LSTK packages namely EPCC-I (ISOM Units: NHT, RSU & PENEX and off-sites facilities & Tankages) which was executed by M/s L&T and EPCC-II (PRIME-G+: FCC GDS) which was executed by M/s Toyo India. The Project Management consultant was M/s Jacobs Engineering India Pvt. Ltd. It was observed that the EPCC-I package execution was going on well but the EPCC-II package, which was lined up after seven months of EPCC-I go ahead, needed some special emphasis on project performance and to match the completion schedule of EPCC-I so that integrated commissioning of the MSQ plant could be achieved. The interface issues where the roles of PMC and Owner became extremely important especially involving common pipe rack and off-site facilities and execution philosophy of EPCC-II due to the compact design of FCC-GDS section.

Strategies and Implementation


Strategic approach during engineering, procurement, planning and execution phase is required from Owners perspective to speed up the progress of the project and guide the entire Project Team to achieve the objective of safe and timely completion of the project. The various strategies, along with meticulous monitoring, adopted and implemented in execution of MSQUP project at Panipat Refinery to speed up the projects progress, to overcome interface issues of different LSTK packages and to go for integrated commissioning of entire project are listed below. A. Project Monitoring and Controlling The construction progress backlog in EPCC-II LSTK package in February 2009 was observed to be hovering around 7% and the trend was increasing which was alarm-

HYDROCARBON ASIA, OCT-DEC 2010

33

ing. On IOCLs initiative, a series of brain storming sessions were done with LSTK agency and PMC to improve upon the progress and put the project on track. Project monitoring called for high level interaction with LSTK agency to bring forth concrete measures quickly to arrest further delays and cover up backlog in 3 to 4 successive months. This followed strategic actions and concurrent working on all fronts with meticulous planning which resulted into achievement of over 9 % construction progress consistently for four months (March 2009 to June 2009) which is a bench mark (Figure 2). B. Strategic Actions by Owner to Expedite Project Progress

Parallel works on various fronts - Concurrent construction activities were taken up to expedite job progress in tight project schedule. 1. After 20% piling work, civil foundation work started simultaneously with proper site planning. Structural work also started concurrently once sufficient front has been generated from civil foundation work. 2. Equipment erection started on getting the civil foundation front one by one. Pip-

ing fabrication work started along with start-up of structural work and piping erection activities were taken up as soon as the rack was ready. 3. Electrical & Instrument cable laying jobs also got advanced in similar fashion. Regular monitoring with respect to Contractors Mobilization vis--vis available front. 1. Regular monitoring of Contractors key skilled persons like welders, fitters, carpenters, masons and resources like piling rig, crane, welding machines etc. was carried out by IOCL project team with respect to available front and they were

Figure 2. Construction Progress curve of EPCC-II of MSQ

Projektleitung

34

HYDROCARBON ASIA, OCT-DEC 2010

Visit our website at: http://www.safan.com

regularly pressurized for adequate mobilization to expedite project progress. Equipment deliveries matched with readiness of equipment foundation at site. 1. Endeavour was made to erect the equipment directly on equipment foundation as soon as it is delivered at site. In close follow-up with LSTK agency, vendors were asked to advance the delivery schedule of equipments. Expediting actions were also taken at vendors works to expedite manufacturing and delivery. 2. Meticulous planning and even staggering of equipment deliveries to match with site erection plan of equipment was done to generate front for subsequent piping works to speed up the job progress. Formation of core-group in advance for better coordination in project. 1. Multi-disciplinary core group was formed around 6 to 8 months before mechanical completion of project for check-listing and coordinating pre-commissioning and commissioning activities and to facilitate smooth handing and taking over. Innovative methods used to advance project execution. 1. Use of pre-cast cable trench sections and pre-cast manholes in place of in-situ RCC casting to save time and generate front for subsequent project activities. 3. Use of ultrasonic testing (UT) in place of conventional radiography for dome roof

isomerate tank for welding quality assurance to expedite work progress. 4. Use of Total Stations for all surveying and layout works in place of Thedolite/ level instruments. 5. Use of more radiography sources of low curie for radiography of piping joints as the plant was compact and higher strength sources may cause radiography interference. Specialized agencies for critical jobs - LSTK agency was categorically instructed to deploy specialized agencies for critical and precision jobs like chemical cleaning of lines, refractory dry-out, catalyst loading in reactors, etc, to complete the safely in one go. C. Challenges Over come : Strategic Intervention by Owner Delay in completion of cooling water circuit was averted by deriving an alternate way of tapping cooling water. After brainstorming, it was thought prudent to go for HOT TAPPING from existing cooling water circuit for MSQ and later connect existing circuit with refinery network. This is how cooling water circuit was laid for MSQ timely. Supply of two long lead items namely MUG compressors and reactors of FCC GDS were kept under Owners scope and these were given as Free Issue Materials to LSTK agency. The deliveries were closely monitored and rigorous follow-up were done for timely delivery. Compressor motor was received at site from M/s Lohar, Germany in August 2009 just on time. Compressors were

HYDROCARBON ASIA, OCT-DEC 2010

35

finally received and erected in supervision of M/s BPCL, India who was supplier of compressor package. Compressors associated piping and instrumentation items were also lifted strategically from BPCLs work to site and fabricated and assembled to save project time. IOCL team monitored and reduced the manufacturing cycle time of reactors in close working with manufacturer (M/s ISGEC, India) and expedited with M/s ISGEC to complete the reactors phase wise matching with erection schedule at site. All reactors were received progressively at site (one by one) which helped the site team in erection and piping and structural jobs of reactors in time. Since there was a common PMC (M/s Jacobs, India), for both EPCC contracts, integrated approach could be followed and Golden Joints interface could be achieved. A lot of interphase issues of site as well as engineering issues could be immediately resolved due to common PMC. Dome roof storage tank of Isomerate (15000 KL capacity) involved huge quantum of radiography of weld joints which was time consuming and activity was on critical path. Issue was resolved by replacing radiography with phased array Ultrasound testing (UT) in consultation with PMC and LSTK agency and target was achieved well on time. The problem of different inert levels brought out the learning that practical feasibility of proposed facilities needs to be verified while executing jobs in an existing setup. It is beneficial for the project to

detect and resolve the problems before commissioning. Strategically, no load trial run of all motors was conducted with the help of construction power. It helped in motors health diagnosis at early stage. Similarly, heater dry out was also carried out by external arrangement (without system completion and burners in line) to save commissioning time. Integrated commissioning of all work packages results in reduction in commissioning time. In MSQUP at Panipat, integrated commissioning has taken place in both the EPCCs as a part of systematic unit wise commissioning plan to reduce commissioning time.

a watch guard of quality assurance and safety management at site. Project monitoring and strategic intervention by Owner from conceptualization phase to engineering and during execution phase help arrest project slippages and aids in securing successful timely completion of time bound projects like MS quality up-gradation project which have high stakes in business sustainability. This not only achieves the project objective of completing the project without cost and time over-run but also increases the confidence of operation group in smooth commissioning and reliability in operation thereafter.

References
1. P r o j e c t M a n a g e m e n t - A managerial approach, Jack R Meredith, Samuel J Mantel Jr. 6th edition 2008 2. Monthly Project progress reports of MSQ Project, PR,IOCL 3. Process data book of MSQ project, PR,IOCL HA

Conclusion
Participation of owners team acts as a catalyst not only in fast resolution of engineering issues but also speeding up the construction work progress safely. The project team of owner becomes

This publication thanks Mr. Arvind Kumar and Mr. PPS Paul for providing this article. Mr. Arvind Kumar is Chief Project Manager in Panipat Refinery of Indian Oil Corporation Ltd., India. He has worked for Indian Oil Corporation Ltd. for more than 20 years in different refinery units. Mr. Arvind Kumar has performed assignments in Design & Engineering and in Project Management. He has successfully executed various greenfield and revamp projects of refineries along with commissioning. He holds a B. Tech. degree in Mechanical Engineering from KNIT, Sultanpur, India and an MBA with specialization in Operation Management from IGNOU, New Delhi. He is a gold medalist in CPM (Project Management) from U21 Global, NUS, Singapore. PPS Paul is Dy. General Manager (Projects) in Panipat Refinery of Indian Oil Corporation Ltd., India. He has worked for Indian Oil Corporation Ltd. for more than 29 years in different refinery units. Mr. Paul has performed assignments in various greenfield and brownfield projects and in petroleum conservation and research fields. He holds a B.E. degree in Mechanical Engineering from Punjab University, Chandigarh, India with specialization in Operation Research.

Projektleitung

36

HYDROCARBON ASIA, OCT-DEC 2010

Visit our website at: http://www.safan.com

You might also like