Appendix For Chiller MS Phase Rev.00 PDF
Appendix For Chiller MS Phase Rev.00 PDF
EQUIPMENT SCHEDULE
APPENDIX-B
Pre Startup Checklist
Must be completed, signed and provided to Daikin at atleast 2 weeks prior to startup request date
Job Details
Job name
Installation address
Purchasing contractor
Number of unit on site
Chiller model no.
Chiller serial no.
Chilled Water System Yes No N/A Remarks
Chiller installed as per IOM recommendation
Piping Completed
Water system flushed bypassing evaporator, filled & vented
Pumps installed and operational (rotation checked, strainers cleaned)
Controls operational (3-way valves, face/bypass dampers, bypass valves, etc.)
Water system operated and tested; flow meets unit design requirements
Strainer installed before evaporator inlet
Water flow switch installed as per recommendations
Condenser Water System (Water-cooled units)
Piping Completed
Water system flushed bypassing evaporator, filled & vented
Pumps installed and operational (rotation checked, strainers cleaned)
Controls (3-way valves, bypass valves, etc.) operable
Water system operated and flow balance to meet unit design requirements
Strainer installed in between Condenser inlet and Pump
Strainer installed before condenser inlet.
Water flow switch installed as per recommendations
Electrical
Power leads have been checked for proper phasing & terminates to chiller main switch
All interlock wiring complete and compliant with Daikin specifications
Pump starter and interlocks wired
Cooling tower fans and controls wired(For water cooled unit)
Incoming wire Details (size and Number of conductors) to Chiller Electrical isolator
Miscellaneous
Thermometers, wells, gauges, control, Flow switch etc., installed
Minimum system load of 80% capacity available for testing/adjusting controls
Warning: Under no condition should these units be started prior to authorize start-up by Daikin Service. Failure to follow this
warning may result in serious equipment damage All installation work has been completed as checked above, the system has been
inspected and unit is/will be ready for startup by__________________
Contractor Representative:
Name: _____________________
Sign:_ ____________________
Date:______________________
Phone/Email:_________________ Contractor Company stamp_____________
DAME/MB/PSC/REV02
APPENDIX-C
Power Quality Guidelines
Daikin strongly recommend to commission units on permanent electrical power supply as high risk
always associated with fluctuating frequency, voltage & other related parameters which might
affect adversely. However due to unavoidable circumstances if the contractor/customer still wishes
to operate on generator power ensure following guidelines:
Generator Made
Generator Type
Generator VA rating
Generator should be able to take Initial Starting current / maximum current of chiller without
dipping the voltage ( + /- 10% ).
Voltage imbalance between phases shouldn’t be more than ± 2%
Input Voltage and Frequency to chiller should be consistent during operation and within
design limit of chillers.
No phase change allowed, once the chiller commissioned on Generator.
Any input voltage, frequency deviation should be closely monitored.
Harmonics distortion should be ≤5%
Failing to maintain the above shall effect the performance & reliability of the chillers, any breakdown
due to the above shall not be covered by standard warranty.
Thanking you and assuring you of our best attention at all times
Contractor Representative:
Name: _____________________
Sign:_ ____________________
Date:______________________
Phone/Email:_________________ Contractor Company stamp_____________
DAME/MB/PSC/REV02
APPENDIX-D
Specification Compliances for CHILLER STARTUP SERVICE (SECTION 23 64 26.13 Section 3.4 )
Sl No Specification Compliances
A Engage a factory-authorized service representative to comply
perform startup service.
B Inspect field-assembled components, equipment comply
installation, and piping and electrical connections for
proper assemblies, installations, and connections.
C Complete installation and startup checks according to comply
manufacturer's written instructions and perform the
following:
1. Verify that refrigerant charge is sufficient and comply
chiller has been leak tested.
2. Verify that pumps are installed and functional.
3. Verify that thermometers and gages are installed.
4. Operate chiller for run-in period according to
manufacturer's written instructions.
5. Check bearing lubrication and oil levels.
6. Verify proper motor rotation.
7. Verify static deflection of vibration isolators,
including deflection during chiller startup and
shutdown.
8. Verify and record performance of chilled water
flow and low-temperature interlocks.
9. Verify and record performance of chiller
protection devices.
10. Test and adjust controls and safeties. Replace
damaged or malfunctioning controls and
equipment.
DEMONSTRATION
! $
' A E '
APPENDIX-F
Customer reference chiller#____
Job Details
Job name
Installation address
Purchasing contractor
Startup Engineer / Technician
Chiller Application
Number of unit on site
Startup date
SOR number
Unit Information
Measured Parameters
DAME/MB/SF/Screw/REV_03 P a g e |1
DAME/MB/SF/Screw/REV_03 P a g e |2
Actual operating parameters
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
DAME/MB/SF/Screw/REV_03 P a g e |4
APPENDIX-G
Chiller Safety Test Report
Result :
Pass Fail
2. Low Pressure Alarm
Result :
Pass Fail
1. Power Off
Criteria : Time from Power on and Water Flow Establish to Chiller Start = 35 Secs
Result :
Pass Fail
Customer ref. chiller#________
Date: _____________________
Job Details
Job name Location
Unit Model no. Unit Serial no.
Methodology: The scope is to test the “loss of flow” or “no flow safety” of chiller. Once the
chiller is running smoothly, the water flow to the chiller is manually stopped via the pumps.
The chiller will sense “no flow “via the flow switch located across the evaporator line. The
alarm will be raised and chiller will be “OFF” due to loss of flow. The microtech panel will
reflect the error code.
Test Yes/NO
Pump off, Flow loss Alarm in Panel
Section 1. Identification
GHS product identifier : Halocarbon 134a (1,1,1,2-Tetrafluoroethane)
Chemical name : 1,1,1,2-Tetrafluorethane
Other means of : ASPEN R134a, 1,1,1,2-Tetrafluoroethane; Ethane, 1,1,1,2-tetrafluoro-; 1,1,1,
identification 2-Tetrafluoroethane (Refrigerant gas R134A); HFC 134a; HCF 134a; HCFC-134a
Product use : Synthetic/Analytical chemistry.Refrigeration.
Synonym : ASPEN R134a, 1,1,1,2-Tetrafluoroethane; Ethane, 1,1,1,2-tetrafluoro-; 1,1,1,
2-Tetrafluoroethane (Refrigerant gas R134A); HFC 134a; HCF 134a; HCFC-134a
SDS # : 001055
Supplier's details : Airgas USA, LLC and its affiliates
259 North Radnor-Chester Road
Suite 100
Radnor, PA 19087-5283
1-610-687-5253
Date of issue/Date of revision : 5/27/2016 Date of previous issue : No previous validation Version : 0.01 1/11
Halocarbon 134a (1,1,1,2-Tetrafluoroethane)
Specific hazards arising : Contains gas under pressure. In a fire or if heated, a pressure increase will occur and
from the chemical the container may burst or explode.
Hazardous thermal : Decomposition products may include the following materials:
decomposition products carbon dioxide
carbon monoxide
halogenated compounds
Special protective actions : Promptly isolate the scene by removing all persons from the vicinity of the incident if
for fire-fighters there is a fire. No action shall be taken involving any personal risk or without suitable
training. Contact supplier immediately for specialist advice. Move containers from fire
area if this can be done without risk. Use water spray to keep fire-exposed containers
cool.
Special protective : Fire-fighters should wear appropriate protective equipment and self-contained breathing
equipment for fire-fighters apparatus (SCBA) with a full face-piece operated in positive pressure mode. For
incidents involving large quantities, thermally insulated undergarments and thick textile
or leather gloves should be worn.
Environmental precautions : Ensure emergency procedures to deal with accidental gas releases are in place to avoid
contamination of the environment. Avoid dispersal of spilled material and runoff and
contact with soil, waterways, drains and sewers. Inform the relevant authorities if the
product has caused environmental pollution (sewers, waterways, soil or air).
Date of issue/Date of revision : 5/27/2016 Date of previous issue : No previous validation Version : 0.01 3/11
Halocarbon 134a (1,1,1,2-Tetrafluoroethane)
Advice on general : Eating, drinking and smoking should be prohibited in areas where this material is
occupational hygiene handled, stored and processed. Workers should wash hands and face before eating,
drinking and smoking. Remove contaminated clothing and protective equipment before
entering eating areas. See also Section 8 for additional information on hygiene
measures.
Conditions for safe storage, : Store in accordance with local regulations. Store in a segregated and approved area.
including any Store away from direct sunlight in a dry, cool and well-ventilated area, away from
incompatibilities incompatible materials (see Section 10). Keep container tightly closed and sealed until
ready for use. Cylinders should be stored upright, with valve protection cap in place,
and firmly secured to prevent falling or being knocked over. Cylinder temperatures
should not exceed 52 °C (125 °F).
Appropriate engineering : Good general ventilation should be sufficient to control worker exposure to airborne
controls contaminants.
Environmental exposure : Emissions from ventilation or work process equipment should be checked to ensure
controls they comply with the requirements of environmental protection legislation. In some
cases, fume scrubbers, filters or engineering modifications to the process equipment
will be necessary to reduce emissions to acceptable levels.
Date of issue/Date of revision : 5/27/2016 Date of previous issue : No previous validation Version : 0.01 4/11
Halocarbon 134a (1,1,1,2-Tetrafluoroethane)
Date of issue/Date of revision : 5/27/2016 Date of previous issue : No previous validation Version : 0.01 5/11
Halocarbon 134a (1,1,1,2-Tetrafluoroethane)
Possibility of hazardous : Under normal conditions of storage and use, hazardous reactions will not occur.
reactions
Hazardous decomposition : Under normal conditions of storage and use, hazardous decomposition products should
products not be produced.
Hazardous polymerization : Under normal conditions of storage and use, hazardous polymerization will not occur.
Irritation/Corrosion
Not available.
Sensitization
Not available.
Mutagenicity
Not available.
Carcinogenicity
Not available.
Reproductive toxicity
Not available.
Teratogenicity
Not available.
Delayed and immediate effects and also chronic effects from short and long term exposure
Short term exposure
Potential immediate : Not available.
effects
Potential delayed effects : Not available.
Long term exposure
Potential immediate : Not available.
effects
Potential delayed effects : Not available.
Potential chronic health effects
Not available.
General : No known significant effects or critical hazards.
Carcinogenicity : No known significant effects or critical hazards.
Mutagenicity : No known significant effects or critical hazards.
Teratogenicity : No known significant effects or critical hazards.
Developmental effects : No known significant effects or critical hazards.
Fertility effects : No known significant effects or critical hazards.
Bioaccumulative potential
Product/ingredient name LogPow BCF Potential
1,1,1,2 - tetrafluoroethane 1.06 - low
Mobility in soil
Soil/water partition : Not available.
coefficient (KOC)
Date of issue/Date of revision : 5/27/2016 Date of previous issue : No previous validation Version : 0.01 7/11
Halocarbon 134a (1,1,1,2-Tetrafluoroethane)
Packing group - - - - -
Environment No. No. No. No. No.
Additional Limited quantity Product classified as - - Passenger and Cargo
Yes. per the following AircraftQuantity
information sections of the limitation: 75 kg
Packaging instruction Transportation of Cargo Aircraft Only
Passenger aircraft Dangerous Goods Quantity limitation: 150
Quantity limitation: 75 Regulations: 2.13-2.17 kg
kg (Class 2).
“Refer to CFR 49 (or authority having jurisdiction) to determine the information required for shipment of the
product.”
Special precautions for user : Transport within user’s premises: always transport in closed containers that are
upright and secure. Ensure that persons transporting the product know what to do in the
event of an accident or spillage.
Date of issue/Date of revision : 5/27/2016 Date of previous issue : No previous validation Version : 0.01 8/11
Halocarbon 134a (1,1,1,2-Tetrafluoroethane)
State regulations
Massachusetts : This material is not listed.
New York : This material is not listed.
New Jersey : This material is not listed.
Pennsylvania : This material is not listed.
International regulations
International lists
National inventory
Australia : This material is listed or exempted.
Canada : This material is listed or exempted.
China : This material is listed or exempted.
Europe : This material is listed or exempted.
Japan : This material is listed or exempted.
Malaysia : Not determined.
New Zealand : This material is listed or exempted.
Philippines : This material is listed or exempted.
Republic of Korea : This material is listed or exempted.
Taiwan : This material is listed or exempted.
Canada
WHMIS (Canada) : Class A: Compressed gas.
Date of issue/Date of revision : 5/27/2016 Date of previous issue : No previous validation Version : 0.01 9/11
Halocarbon 134a (1,1,1,2-Tetrafluoroethane)
Flammability 1
Physical hazards 0
Caution: HMIS® ratings are based on a 0-4 rating scale, with 0 representing minimal hazards or risks, and 4
representing significant hazards or risks Although HMIS® ratings are not required on SDSs under 29 CFR 1910.
1200, the preparer may choose to provide them. HMIS® ratings are to be used with a fully implemented HMIS®
program. HMIS® is a registered mark of the National Paint & Coatings Association (NPCA). HMIS® materials
may be purchased exclusively from J. J. Keller (800) 327-6868.
The customer is responsible for determining the PPE code for this material.
National Fire Protection Association (U.S.A.)
1 Flammability
Health 2 0 Instability/Reactivity
Special
Reprinted with permission from NFPA 704-2001, Identification of the Hazards of Materials for Emergency
Response Copyright ©1997, National Fire Protection Association, Quincy, MA 02269. This reprinted material is
not the complete and official position of the National Fire Protection Association, on the referenced subject
which is represented only by the standard in its entirety.
Copyright ©2001, National Fire Protection Association, Quincy, MA 02269. This warning system is intended to
be interpreted and applied only by properly trained individuals to identify fire, health and reactivity hazards of
chemicals. The user is referred to certain limited number of chemicals with recommended classifications in
NFPA 49 and NFPA 325, which would be used as a guideline only. Whether the chemicals are classified by NFPA
or not, anyone using the 704 systems to classify chemicals does so at their own risk.
Procedure used to derive the classification
Classification Justification
Press. Gas Liq. Gas, H280 Expert judgment
History
Date of printing : 5/27/2016
Date of issue/Date of : 5/27/2016
revision
Date of previous issue : No previous validation
Version : 0.01
Key to abbreviations : ATE = Acute Toxicity Estimate
BCF = Bioconcentration Factor
GHS = Globally Harmonized System of Classification and Labelling of Chemicals
IATA = International Air Transport Association
IBC = Intermediate Bulk Container
IMDG = International Maritime Dangerous Goods
LogPow = logarithm of the octanol/water partition coefficient
MARPOL 73/78 = International Convention for the Prevention of Pollution From Ships,
1973 as modified by the Protocol of 1978. ("Marpol" = marine pollution)
Date of issue/Date of revision : 5/27/2016 Date of previous issue : No previous validation Version : 0.01 10/11
Halocarbon 134a (1,1,1,2-Tetrafluoroethane)
Date of issue/Date of revision : 5/27/2016 Date of previous issue : No previous validation Version : 0.01 11/11
APPENDIX-I
R A < = 4 8 > > 5 < : F 5 > A 7 @ 8 7 @ 9 A 9 4 8 : = ; 9 5 @ A < B S : A T 5 > A = ; > < 5 @ 6 > ; 9 8 A 7 :
Y Z [ \ ] ^ _ ` a b c d e ] f Z d e c ] e Z e g ] h i a j i Z f f ]
k d l c a m n g c d o d c d ] l # ] ] $ \ p q a e c r \ p w ] Z i \ p % x ] Z l
a e Z \
s t A 9 5 u v
s t A 9 5 O v
y ] e ] i Z \ &
| \ ] g c i d g Z \ &
D 5 < 8 E B 9 4 ; 9 ; > > 5 > 5 = 9 < 8 = ; > 9 5 < T 8 7 ; > : ; < 5 9 8 @ 4 9 } 3 8 @ 4 9 5 7 8 E 7 5 = 5 : : ; < B
'
` ] m i d j ] i Z c d a e g d i g b d c &
D 5 < 8 E B < 5 E < 8 @ 5 < ; 7 9 E > A X 6 : 8 7 @ 9 4 5 > 8 U 6 8 ? : 8 @ 4 9 @ > ; : : } 8 @ 4 9 @ > ; : : E 6 > > '
a e ] e l ] i l ] g c d a e &
) * + , - .
/ 0 1 * 2 + 3 4 5 6 7 + 8 9 8 + 8 , - 8 2 7 4 : ; , 6 4 4 + 3 , < , , = 4 5 * 2 , - 0
> 0 ? 3 , 6 2 2 : 6 4 @ * A , 6 A 4 5 - , 6 - * 2 B 6 7 + 8 9 8 + 8 , - 8 2 7 4 : ; , 6 4 4 < , , = 4 5 6 2 ; C * 2 + 3 4 5 6 7 + 8 9 8 + 8 , - 0
D 0 E 2 8 + * F , A 6 + 8 2 G 9 6 4 : , - - 3 * : 4 ; H , A , 6 ; * 2 6 ; 6 8 4 5 H 6 - 8 - + 3 : - = , , F 8 2 G 3 8 G 3 * H - , A 9 6 + 8 * 2 - + 6 2 ; 6 A ; - 0
I 0 J 2 , 2 9 8 A * 2 C , 2 + - < 8 + 3 6 3 8 G 3 7 * 2 7 , 2 + A 6 + 8 * 2 * K 6 8 A L H * A 2 , F 6 A + 8 7 4 , - M 8 + C 8 G 3 + H , 2 , 7 , - - 6 A 5 + * 7 4 , 6 2 + 3 , 7 * 2 ; , 2 - , A H 6 2 = C * A , * K + , 2 0
N 0 O , F 4 6 7 , + 3 , * 8 4 K 8 4 + , A < 3 , 2 + 3 , F A , - - : A , ; A * F 6 7 A * - - 8 + A , 6 7 3 , - > 0 P H 6 A 0
Q 0 R 3 , 7 = K * A 6 2 5 ; 8 - - * 4 9 , ; C , + 6 4 - 0
S 0 ? T ) @ ? * + 6 4 T 7 8 ; ) : C H , A B . P M / P . ) * 6 7 + 8 * 2
£ U , + < , , 2 P 0 / P 6 2 ; P 0 / V . O , F 4 6 7 , 6 2 + 8 L 6 7 8 ; K 8 4 + , A - 6 2 ; A , L 7 3 , 7 = 6 K + , A / P P P A : 2 2 8 2 G 3 * : A - 0 R * 2 + 8 2 : , + * A , F 4 6 7 , K 8 4 + , A -
: 2 + 8 4 + 3 , ? T ) 8 - 4 * < , A + 3 6 2 P 0 / P 0
P M / V . O , F 4 6 7 , * 8 4 M * 8 4 K 8 4 + , A 6 2 ; K 8 4 + , A ; A 5 , A 0 W , A 8 K 5 6 + A , G : 4 6 A 8 2 + , A 9 6 4 - 0
>
d l h a l Z \
0 . ! %
K s u v ; > 6 5 u "
= 5 7 9 < 5 : Q
8 7 ? 8 = ; 9 5 ? A 7 9 4 5 6 7 8 9 7 ; T 5 H > ; 9 5 Q
Y Z [ \ ] ^ _ ` ^ a [ \ ^ b c d Z _ [ d ^ a ^ [ e ^ _ e e f c \ _ f b g c h g c \ c _ b ^ i [ _ e [ _ j f k k c g l Y Z c d f _ b c _ b d ^ _ _ f b i c Z c a e ^ \ c m h a [ d [ b a n f g [ ] h a [ d [ b a n j ` ^ g ^ _ b c c e ^ \ d f ] h a c b c o h g c d [ \ c f g g c a [ ^ i a c l p a a e ^ b ^ ^ _ e
\ h c d [ k [ d ^ b [ f _ \ d f _ b ^ [ _ c e Z c g c [ _ ] ^ n i c ] f e [ k [ c e q [ b Z f ` b _ f b [ d c l Y Z c e ^ b ^ d f ] ] ` _ [ d ^ b c e ^ b b Z c ] f ] c _ b f k b Z c f g e c g \ Z ^ a a Z f a e k [ g ] l
Y Z c ] ^ _ ` k ^ d b ` g c g \ Z ^ a a ^ \ \ ` ] c _ f a [ ^ i [ a [ b n q Z ^ b \ f c r c g k f g ^ _ n e [ g c d b f g [ _ e [ g c d b e ^ ] ^ j c o [ _ b Z c q [ e c \ b \ c _ \ c f k b Z c b c g ] o c _ \ ` [ _ j k g f ] f g d f _ _ c d b c e q [ b Z b Z c ` \ c ^ _ e s f g [ _ b c g h g c b ^ b [ f _
f k b Z [ \ ] ^ _ ` ^ a l
t c g c \ c g r c b Z c g [ j Z b b f ] ^ u c d Z ^ _ j c \ [ _ e c \ [ j _ ^ _ e d f _ \ b g ` d b [ f _ ^ b ^ _ n b [ ] c q [ b Z f ` b _ f b [ d c o b Z ` \ b Z c d f r c g h [ d b ` g c [ \ _ f b i [ _ e [ _ j l
➔ Unit description: Daikin air-cooled chiller with single screw compressor and R134a refrigerant. Color: Ivory White
{Munsell code SY7.5/1) {±RAL7044).
➔ Compressor : single-screw type with gate-rotor made with the latest high-strength fibre reinforced star material.
The compressor has an asymmetric slide regulation managed by the unit controller for infinitely modulating
capacity from 100% to 25%. An integrated high efficiency oil separator maximizes the oil separation and standard
start is Wye-Delta (Y-�) type.
➔ Evaporator : New generation of direct expansion shell&tube evaporator with refrigerant evaporating inside the
tubes and water flowing outside. The tubes are enhanced for maximum heat transfer and rolled into steel tube
sheet and sealed. shell and tube manufactured according to 97/23/EC directive (PED).
➔ Condenser : internally enhanced seamless copper tubes arranged in a staggered row pattern and mechanically
expanded into lanced and rippled aluminum condenser fins with full fin collars. An integral sub-cooler circuit
provides sub-cooling to effectively eliminate liquid flashing and increase cooling capacity without increasing the
power input.
➔ Condenser coil fans : The condenser fans are propeller type with high efficiency design blades to maximize
performances. The material of the blades is glass reinforced resin and each fan is protected by a guard. Fan motors
are internally protected from overtemperature and are IP54.
➔ Refrigerant circuit : Each unit has two independent refrigerant circuits and each one includes: Compressor with
integrated oil separator, Electronic expansion valve, Discharge line shut off valve, Liquid line shut off valve, Sight
glass with moisture indicator, Filter drier, Charging valves, High pressure switch, High pressure transducers, Low
pressure transducers, Oil pressure transducer, Suction temperature sensor.
➔ Electrical : Control panel Power and control are located in the main panel that is manufactured to ensure
protection against all weather conditions. The electrical panel is IP54 and (when opening the doors) internally
protected against possible accidental contact with live parts. The main panel is fitted with a main switch
interlocked door that shuts off power supply when opening.
➔ Controller : Latest generation MicroTech Ill Type. Providing monitoring and control functions required for an
efficient and trouble free operation of the chiller. Sophisticated software with predictive logic selects the most
energy efficient combination of compressor load and electronic expansion valve position keeping stable operating
conditions and maximizing chiller efficiency and reliability. Unit is compatible with Daikin on Site platform for
remote monitoring, preventive maintenance and system optimization.
0 �
t::::::i
� □□□------------------------------------
Specifications are subject to change without any prior notice 28/5/2020 CSS Web 10.23
Page 1/4
Power Consumption @ Design conditions
Cooling capacity = 1132kW / 3.516 = 321.9 TR
Power Input = 382.3 kW
Power consumption = 382.3 kW / 321.9 TR = 1.1876 kW / TR
APPENDIX-K
Technical data
Contact
E-mail Glanded standard single pump
Phone IL 100/260-11/4
Customer Project name
Project ID
Contact Installation location
E-mail Customer pos.no
Phone
Date 2020-06-08
HAZARD MODERATE 2 4 6 8 10 Hazard to be investigated in conjunction with Safety Rep. with a view to
>15
SEVERITY SERIOUS 3 6 9 12 15 reducing the risk
(S) MAJOR 4 8 12 16 20 Immediate action must be taken to eliminate the risk or Substantially
20<
CATASTROPHIC 5 10 15 20 25 reduce the risk.
HAZARD MODERATE 2 4 6 8 10 Hazard to be investigated in conjunction with Safety Rep. with a view to
>15
SEVERITY SERIOUS 3 6 9 12 15 reducing the risk
(S) MAJOR 4 8 12 16 20 Immediate action must be taken to eliminate the risk or Substantially
20<
CATASTROPHIC 5 10 15 20 25 reduce the risk.
PPE (Full Body Harness with
Lanyard) Training, Guardrails, Toe
Fall from height 3 5 15 Plates/Inspection of Equipment 2 2 4
(Ladder/Scaffolding etc) Following
SOP
Floor (uneven Maintenance/Signage/Workplace
2 3 6 1 2 2
surface) Inspection prior to start of job
Operator(s), Nearby
People, Property Use of Waist Tool Bags for carrying
Working at Height tools/Not throwing material up or
Fall of Material (Equipment/Tools/ 2 4 8 1 3 3
Building) down/Use of rope & pully to transfer
material/ Signage/Barricade
Ergonomic 3 3 9 Training 1 1 1
Inspection & Maintenance of
Scaffolding / Ladder Ladders/Inspection & Maintenance
3 4 12 2 2 4
failure of Scaffolding/Following
SOP's/Training
Groups Factors of
Date
Exposed Harm / Control measures
Risk to be Residual Risk
(Inc. Current Risk Implemented by
Activities Hazard Activiti Existing Control Measures Additional Control measures compl
Nos. & Rating
es eted
Patterns
L S R by L S R
)
Mobilization Unauthorize Prepare All TBT/DSTI to be conducted by 4 3 12 Daily safety inspection should be carried Prior to 2 3 6 Site Engineer /
d, untrained work workers the foreman/ safety officer prior and eliminate the hazard. start Supervisor /
workers area to work commencement the Foreman
Task specific safety training to be work
provided
Authorized personnel to
undertake the job.
HWI-APO-CN-MSS-0009-02 – METHOD STATEMENT SUBMITTAL FOR START-UP COMMISSIONING OF AIR COOLED CHILLERS
METHOD STATEMENT SUBMITTAL
(MTS)
Groups Factors of
Date
Exposed Harm / Control measures
Risk to be Residual Risk
(Inc. Current Risk Implemented by
Activities Hazard Activiti Existing Control Measures Additional Control measures compl
Nos. & Rating
es eted
Patterns
L S R by L S R
)
Manual Handling Incorrect Back All Any lifting tasks shall be carried 4 4 16 Deploy enough number of personnel for Prior 3 4 12 Site Engineer /
lifting of Injuries workers out by persons physically lifting shall be appointed to the task to Supervisor /
loads Cut to capable to do so depending upon the type of load to be start Foreman
Sharp finger No employee should be asked to lifted. the
edges. Strain carry loads above his capacity and Use easy mode of transport like trolley etc. wor
Placing the Musculo in any case no load shall exceed Area to be illuminated with adequate k
object while skeletal 23kg per man. lighting
fingers Injuries Mass of the load is more then to be Periodic trainings will be given for manual
underneath. equally shared handling techniques.
Slip/trip/fall Load not to be lifted above your Daily TBT.
( same shoulder height Rest timings in between the job if the job
level ) Keep your fingers away from time is too long.
Unsafe pinch point while placing the load
posture Proper personal protective
equipment to be used while
manual handling of materials and
loads.
Stacking and Unauthorize Crush All All materials shall be stored 4 3 12 Ensure the storage is enough for storing Prior 3 3 12 Site Engineer /
Storing d, untrained Cut and workers below 2 meter height. otherwise will get additional storing area. to Supervisor /
workers abrasion If the material is too heavy, use start Foreman
Material fall Damage hydraulic trolley to shift the Daily TBT. the
from height to material. wor
Improper property No storage of materials to be k
stacking done in the work place, only
Collapse required quantity to be taken for
the job.
• Personnel protective equipment
must wear at all time during the
activity. (Helmet, shoe, vest,
overall, gloves, goggles, mask.)
HWI-APO-CN-MSS-0009-02 – METHOD STATEMENT SUBMITTAL FOR START-UP COMMISSIONING OF AIR COOLED CHILLERS
METHOD STATEMENT SUBMITTAL
(MTS)
Groups Factors of
Date
Exposed Harm / Control measures
Risk to be Residual Risk
(Inc. Current Risk Implemented by
Activities Hazard Activiti Existing Control Measures Additional Control measures compl
Nos. & Rating
es eted
Patterns
L S R by L S R
)
Working with Slip, trip Crush All Don’t extend the spanner by 4 4 16 Defective tools should not be issued or Prior 3 4 12 Site Engineer /
Hand tools and fall Damage workers using a pipe as an extension bar used to Supervisor /
Damaged to Hand tools shall be free from oil, to perform the task, to be checked by start Foreman
warn out property grease & etc. store the
hand tools Fatigue Chisel’s head shall have safety keeper work
Flying Trigger cap to avoid finger injury. Never use a screw driver as a chisel
objects finger Never use a file as a lever Don’t work with oily or greased hands
Mushroom Cuts
Heads and Use right tools for the job. Use eye/ face protection when there is
flying materials hazard, wear gloves
Using abrasion while required to protect the hands
incorrect s
type Daily TBT
Working with Defective Eye All PTW to be applied and obtained 4 4 16 Prior 2 4 8 Site Engineer /
power tools equipment injury workers prior to start, If spark producing Don’t lay the cables around the access to Supervisor /
Electricity Crushi activity is performed way, it should be proper routing start Foreman
Improper ng Defective tools should not be Industrial distribution board and socket the
use of Back issued or used to perform a task. only to be used at site work
equipment injury Monthly inspection should be No joints shall be made in electrical
Poor Burns carried out by the electrician and cable.
maintenance Electro record to be kept at the store Cable hangers shall be used to avoid the
Untrained cution All portable power tools should direct contact of power tools cable with
workers be fitted with adequate fuse the scaffolding members.
Flying protection either in the tool body Electrical connection shall be routed
object or in its electrical plug through ELCB only.
Noise and The weight, size and type of tool Correct rate of ELCB should be used.
vibration should be selected to suit the job Only those persons who have been
Fire being carried out. adequately trained and experienced in the
Dust Tools should be stored and use of the tool should be allowed to use
maintained in good working the same.
condition. Periodic trainings will be given for safe
Appropriate PPE Should use use of electrical equipment.
Daily TBT.
Power tools shall have inspection
sticker.
Ensure the use of drip trays for
any hydraulic power tools.
HWI-APO-CN-MSS-0009-02 – METHOD STATEMENT SUBMITTAL FOR START-UP COMMISSIONING OF AIR COOLED CHILLERS
METHOD STATEMENT SUBMITTAL
(MTS)
Groups Factors of
Date
Exposed Harm / Control measures
Risk to be Residual Risk
(Inc. Current Risk Implemented by
Activities Hazard Activiti Existing Control Measures Additional Control measures compl
Nos. & Rating
es eted
Patterns
L S R by L S R
)
Working with Fall from Sprain All The ladder should extend 4 3 12 Ladder to be used for short duration Prior 3 3 9
ladder height and workers minimum one meter from the top works only limited to 15 min. to Site Engineer /
Over strain for safe movement Colour coded system to be implemented start Supervisor /
reaching Fracture Heavy materials should not be Inspection and maintenance to be the Foreman
Over Injury to carried registered and recorded by the store work
loading the Do not erect in slippery, uneven keeper
Obstructing person surface Defective ladder should not be used and
the access Should be set up with a 4 vertical report it immediately
way to 1 horizontal slope ( 4:1 ) Daily TBT
Slippery or Step ladder must fully open and Periodic trainings.
uneven lock and the devices to be as per
surface manufacturer
Do not work from the top of two
rungs
Remember the 3 point contact
Do not work in front of the door.
If work is carried then locked the
door or blocked off
Working on Uneven Sprain All Do not stack materials on to the 4 4 16 Visual inspection should carry before use Prior 3 4 12 Site Engineer /
mobile scaffold surface and workers scaffold to Supervisor /
Overhead strain Out rigger fitted and breaks are Safety harness to be used above 2mtr start Foreman
structure Fracture locked on height and anchored in above shoulder the
height at all time
and cable Spinal Only trained scaffolders shall be work
Materials cord involved in erection & Tagging system to be implemented
and worker damage dismantling activities. Keep walkways free of obstacles, tools
fall from Musculo No person to be on the scaffold and Equipment
height skeletal
Untrained, Injury
while it is being moved
Scaffold only use in on level and
Daily TBT
unauthorize Fatality surface area Periodic trainings.
d Workers Never stand and sit on the hand
Collapse of rails
scaffold
HWI-APO-CN-MSS-0009-02 – METHOD STATEMENT SUBMITTAL FOR START-UP COMMISSIONING OF AIR COOLED CHILLERS
METHOD STATEMENT SUBMITTAL
(MTS)
Start-up 1.Eye Sprain T&C All tools provided must be assessed 3 4 12 Whilst taking RPM readings on rotating Prior 2 4 8 Commissioning
Commissioni injury and Team to ensure that they are fit for equipment an assistant will man the isolator to to Manager
ng of Air 2.Injury to strain purpose, fit for the environment in allow the stopping of motors if contact occurs. start Com. Engineer
Fracture which they are to be used and they the Supervisor
Cooled hands, feet are in good condition.
Chiller and body Spinal work Safety Supervisor
Visual checks must be completed
3.Electrical cord by operatives on tools prior to their
Shock. damage use.
4.Fall from Musculo Tools are required to be suitable for
step skeletal the purpose for which they will be
ladders. Injury used.
Fatality Eye protection is to be provided and
5. Contact
used whenever work is done and
with there is the danger of dust being
rotating blown into the operatives’ eyes
during air system commissioning or
where test holes are being drilled in
ductwork and swarf can fall into the
operatives’ eyes.
Insulated tools must be used where
there is a possibility of live
electrical work.
Prior to taking amp readings on live
conductors the tightness of the
terminations will be checked with
the circuit dead to ensure no cables
come loose during live testing.
Prior to taking RPM readings on
rotating equipment the engineer will
check his clothing to ensure that
there are no loose pieces of material
which could become entangled in
rotating equipment.
HWI-APO-CN-MSS-0009-02 – METHOD STATEMENT SUBMITTAL FOR START-UP COMMISSIONING OF AIR COOLED CHILLERS
METHOD STATEMENT SUBMITTAL
(MTS)
Groups Factors of
Date
Exposed Harm / Control measures
Risk to be Residual Risk
(Inc. Current Risk Implemented by
Activities Hazard Activiti Existing Control Measures Additional Control measures compl
Nos. & Rating
es eted
Patterns
L S R by L S R
)
Emergency Unauthorize Fatality All Only qualified and trained 4 4 16 Emergency evacuation plan shall be Prior 3 4 12 Site Engineer /
procedure d/ untrained Property workers person to do the job. readily available according to site to Supervisor /
Person damage Emergency procedure to be condition and developed to the all start Foreman
Faulty Fracture briefed to all personnel prior to workforce. the
Instrument s start the activity. Trained first aider, fire warden and work
Improper Calibrated pressure gauge only emergency vehicle to be available at the
identificatio to be used and increase pressure site during the activity.
n
High
gradually. Daily TBT
Periodic trainings
pressure
While working at Poor Fatality All light post to be secured from fall 3 3 9 Daily TBT Prior 2 3 6 Site Engineer /
night shift illumination Cuts workers Proper cable management Periodic trainings to Supervisor /
Slip/trip/fall system to be followed start Foreman
Proper illumination to be provided.
All materials to be staged in the
proper manner without obstacles work
Working in hot Heat Dehydra All Drink plenty of water 4 3 12 Proper awareness of heat stress Prior 3 3 9 Site Engineer /
weather tion workers Avoid highly physical tasks symptoms to Supervisor /
Sunburn during the hottest part of the day Isotonic drinks to be provided start Foreman
Skin
Cancer
Daily TBT the
work
Periodic trainings
Work Poor Fire All General housekeeping. 4 4 16 Daily TBT Prior 3 4 12 Site Engineer /
Completion housekeepin Fatality workers Remove all surface, unwanted Periodic trainings to Supervisor /
g Cuts waste materials from the start Foreman
Slip/trip/fall Property building the
damage All necessary precautions will be work
Fracture adopted to prevent fire and
s work
compl
etion.
HWI-APO-CN-MSS-0009-02 – METHOD STATEMENT SUBMITTAL FOR START-UP COMMISSIONING OF AIR COOLED CHILLERS
APPENDIX-M
OPERATING MANUAL
MicroTech III ® Controller
MODBUS PROTOCOL INFORMATION SUMMARY
Application Software Name: ACZC-ACZH-ATLAS-AWS-EWWD-GIZMO-MNG-PFS-WATER STREAM
D-EOMOC002(04)09-15EN
D-EOMOC002(04)09-15EN - 1/35
Table of Contents
PREMISE .................................................................................................................................................................. 3
INTRODUCTION ...................................................................................................................................................... 4
Revision History .............................................................................................................................................................. 4
Reference Documents .................................................................................................................................................... 4
BASIC INFORMATION ............................................................................................................................................ 5
Compatibility ................................................................................................................................................................... 5
Configuring the Microtech III for Modbus Network .......................................................................................................... 5
Modbus Registers Addressing ........................................................................................................................................ 5
MINIMUM INTEGRATION ........................................................................................................................................ 6
DATA POINTS ......................................................................................................................................................... 7
Data Points for Chiller Models......................................................................................................................................... 7
Comprehensive Data Points List ..................................................................................................................................... 9
ALARM POINTS ....................................................................................................................................................18
Alarm Points for Chiller Models ....................................................................................................................................... 18
Comprehensive Alarm Points List ................................................................................................................................... 20
APPENDIX A – ASCII CHARACTERS CONVERSION TABLE ...........................................................................25
APPENDIX B – OVERALL REGISTERS TABLE .................................................................................................26
D-EOMOC002(04)09-15EN - 2/35
Premise
The Modbus protocol is a standardized Application Level (OSI Level 7) protocol used in interoperable
Industrial Control networks. Modbus provides the communication infrastructure necessary to integrate
products manufactured by different vendors and to integrate control services that are now independent.
D-EOMOC002(04)09-15EN - 3/35
Introduction
This document describes the present status of Modbus communication profile for all MicroTech III application
®
software, providing the necessary information to incorporate a MicroTech III Chiller Unit Controller into a
Building Automation System (BAS).
Modbus terms and principles are not defined. Refer to the appropriate specifications for definitions and
details.
Revision History
1) D-EOMOC00011-14EN November 2014 Created
2) D-EOMOC002(17)12-14EN 17 December 2014 Upgraded ATLAS Holding Registers 40025, 40026
3) D-EOMOC002(19)12-14EN 19 December 2014 Improved ATLAS Holding Registers 40900, 40901, 40902
Improved Appendix B
Upgraded Holding Registers 40011, 40034
Upgraded Revision History
4) D-EOMOC002(04)09-15EN 04 September 2015 Improved GIZMO units
Improved WaterStream units
Upgraded Table 2
Upgraded Table 3
Upgraded Table 4
Upgraded Table 5
Upgraded Table 5
Upgraded Revision History
Reference Documents
Ref.#1 www.Modbus.org
D-EOMOC002(04)09-15EN - 4/35
Basic Information
Compatibility
The MicroTech III Chiller Unit Controller conforms to the published Modbus standards. Controllers can
communicate on standard Modbus networks using ASCII or RTU transmission mode. The MicroTech III
Chiller Unit Controller uses the RTU mode only. Refer to Ref.#1 for more detailed information.
D-EOMOC002(04)09-15EN - 5/35
Minimum Integration
This section describes the information that assure compliance of Microtech III to the integration criteria for a
Modbus network integration. The data/alarm points that represent the minimum integration data points are
listed in Table 1 below and in boldface in Table 2 to Table 5.
Table 1. MicroTech III Chiller Unit Controller Registers for minimum integration
Data/Alarm points
Actual Capacity
Chiller Enable Setpoint
Chiller Mode Setpoint - Network
Chiller Status
Clear Alarms - Network
Evaporator Entering Fluid Temperature
Evaporator Leaving Fluid Temperature
Capacity Limit Setpoint – Network
Cool Setpoint – Network
Problem Alarm Code
Fault Alarm Code
Warning Alarm Code
D-EOMOC002(04)09-15EN - 6/35
Data Points
Table 2. MicroTech III Unit Controller Data Points List for Chiller Model
STREAM
WATER
ATLAS
EWWD
GIZMO
ACZC
ACZH
AWS
MNG
ADZ
PFS
Data Point
Active Energy X X X
Active Setpoint X X X X X X X X X X
Actual Capacity X X X X X X X X X X
Chiller Current X X X X X X X X X
Chiller Local/Remote X X X X X X X X X X
Chiller Location X X X X X X X X X X
Chiller Model X X X X X X X X X X
Chiller On/Off X X X X X X X X X X
Chiller Tons X X X X X X X X X X
Chiller Voltage X X X
Compressor Current X X
Compressor Power X X
D-EOMOC002(04)09-15EN - 7/35
STREAM
WATER
ATLAS
EWWD
GIZMO
ACZC
ACZH
AWS
MNG
ADZ
PFS
Data Point
Compressor Starts X X X X X X X X X
Compressor Status X X X X X X X X
Compressor Voltage X X
Date X X X X X X X X X X
Day of Week X X X X X X X X X X
EXV Position X X X X X X X X X
Hour X X X X X X X X X X
Liquid Temperature X
Minute X X X X X X X X X X
Month X X X X X X X X X X
D-EOMOC002(04)09-15EN - 8/35
STREAM
WATER
ATLAS
EWWD
GIZMO
ACZC
ACZH
AWS
MNG
ADZ
PFS
Data Point
Number of Circuits X X X X X X X X X X
Number of Compressors X X X X X X X X X X
Power Factor X X X
Power Input X X X
Refrigerant Type X X X X X X X X X X
Run Enabled X X X X X X X X X X
Second X X X X X X X X X X
Units X X X X X X X X X X
Year X X X X X X X X X X
Table 3. MicroTech III Unit Controller Modbus Comprehensive Data Point List
H.R.1
R/W2
1
Holding Register (4xxxx)
2
Read/Write
D-EOMOC002(04)09-15EN - 9/35
H.R.1
R/W2
Data Point Range/Description
Chiller Current 25 R
Chiller Model 317 R 0=Centrifugal, 1=Water Cooled, 2=Air Cooled, 3=Heat Pump, 9=Other
Chiller Status (Chiller Run Mode) 15 R 1=Off, 2=Start, 3=Run, 4=Pre Shutdown, 5=Service
D-EOMOC002(04)09-15EN - 10/35
H.R.1
R/W2
Data Point Range/Description
Circuit #2 Comp #1 - Discharge Refrigerant Temp 107 R -40 to 121°C (-40 to 250°F)
Circuit #3 Comp #1 - Discharge Refrigerant Temp 146 R -40 to 121°C (-40 to 250°F)
Circuit #1 Comp #1 - Oil Feed Pressure 1849 R -40 to 121 kPa (-5.801473 to 17.54946 psi)
Circuit #2 Comp #1 - Oil Feed Pressure 1809 R -40 to 121 kPa (-5.801473 to 17.54946 psi)
Circuit #1 Comp #1 - Oil Feed Pressure 1846 R -40 to 121 kPa (-5.801473 to 17.54946 psi)
Circuit #1 Comp #2 - Oil Feed Pressure 1832 R -40 to 121 kPa (-5.801473 to 17.54946 psi)
Circuit #3 Comp #1 - Oil Feed Pressure 1770 R -40 to 121 kPa (-5.801473 to 17.54946 psi)
D-EOMOC002(04)09-15EN - 11/35
H.R.1
R/W2
Data Point Range/Description
Circuit #2 Comp #1 - Suction Refrigerant Temp 104 R -40 to 110° C (-40 to 230° F)
Circuit #3 Comp #1 - Suction Refrigerant Temp 143 R -40 to 110° C (-40 to 230° F)
Circuit #1 - Condenser Refrigerant Pressure 39 R 0 to 2827 kPa (4826 kPa for R410A) - 0 to 410 psi (700 psi for R410A)
Circuit #2 - Condenser Refrigerant Pressure 43 R 0 to 2827 kPa (4826 kPa for R410A) - 0 to 410 psi (700 psi for R410A)
Circuit #3 - Condenser Refrigerant Pressure 47 R 0 to 2827 kPa (4826 kPa for R410A) - 0 to 410 psi (700 psi for R410A)
D-EOMOC002(04)09-15EN - 12/35
H.R.1
R/W2
Data Point Range/Description
Date 311 RW -
Circuit #1 - Evaporator Refrigerant Pressure 41 R -2413 to 2413 kPa (-349.97 to 349.97 psi)
Circuit #2 - Evaporator Refrigerant Pressure 45 R -2413 to 2413 kPa (-349.97 to 349.97 psi)
Circuit #3 - Evaporator Refrigerant Pressure 49 RW -2413 to 2413 kPa (-349.97 to 349.97 psi)
D-EOMOC002(04)09-15EN - 13/35
H.R.1
R/W2
Data Point Range/Description
D-EOMOC002(04)09-15EN - 14/35
H.R.1
R/W2
Data Point Range/Description
D-EOMOC002(04)09-15EN - 15/35
H.R.1
R/W2
Data Point Range/Description
Heat Recovery Entering Water Temp 22 R Enabled whit Heat Recovery option
Heat Recovery Leaving Water Temp 23 R Enabled whit Heat Recovery option
D-EOMOC002(04)09-15EN - 16/35
H.R.1
R/W2
Data Point Range/Description
D-EOMOC002(04)09-15EN - 17/35
Alarm Points
Table 4. MicroTech III Unit Controller Alarm Points List for Chiller Model
STREAM
WATER
ATLAS
EWWD
GIZMO
ACZC
ACZH
AWS
MNG
ADZ
PFS
Alarm Point
D-EOMOC002(04)09-15EN - 18/35
STREAM
WATER
ATLAS
EWWD
GIZMO
ACZC
ACZH
AWS
MNG
ADZ
PFS
Alarm Point
D-EOMOC002(04)09-15EN - 19/35
STREAM
WATER
ATLAS
EWWD
GIZMO
ACZC
ACZH
AWS
MNG
ADZ
PFS
Alarm Point
Table 5. MicroTech III Unit Controller Modbus Comprehensive Alarm Point List
Alarm Point H.R.3 R/W Range
3
Holding Register (4xxxx)
D-EOMOC002(04)09-15EN - 20/35
3
Alarm Point H.R. R/W Range
Circuit #1 - SHUTDOWN – Phase Voltage Protection Fault (ATLAS, AWS, EWWD, MNG) 751 R 0=Normal, 1=Alarm
Circuit #1 - SHUTDOWN – Phase Voltage Protection Fault (ACZC, ACZH, ADZ) 817 R 0=Normal, 1=Alarm
Circuit #2 - SHUTDOWN – Phase Voltage Protection Fault (ATLAS, AWS, EWWD, MNG) 752 R 0=Normal, 1=Alarm
Circuit #2 - SHUTDOWN – Phase Voltage Protection Fault (ACZC, ACZH, ADZ) 818 R 0=Normal, 1=Alarm
Circuit #3 - SHUTDOWN – Phase Voltage Protection Fault (AWS) 753 R 0=Normal, 1=Alarm
Circuit #1 Comp #1 - LOCKOUT - Number of Allowed Re-Starts Exceeded Fault 583 R 0=Normal, 1=Alarm
Circuit #2 Comp #1 - LOCKOUT - Number of Allowed Re-Starts Exceeded Fault 585 R 0=Normal, 1=Alarm
Circuit #3 Comp #1 - LOCKOUT - Number of Allowed Re-Starts Exceeded Fault 587 R 0=Normal, 1=Alarm
Circuit #1 Comp #1 - SHUTDOWN - COM ERROR With VFD Fault 774 R 0=Normal, 1=Alarm
Circuit #2 Comp #1 - SHUTDOWN - COM ERROR With VFD Fault 776 R 0=Normal, 1=Alarm
Circuit #3 Comp #1 - SHUTDOWN - COM ERROR With VFD Fault 778 R 0=Normal, 1=Alarm
Circuit #1 Comp #1 - SHUTDOWN - Discharge Temp High Fault 535 R 0=Normal, 1=Alarm
Circuit #1 Comp #2 - SHUTDOWN - Discharge Temp High Fault (PFS) 536 R 0=Normal, 1=Alarm
Circuit #2 Comp #1 - SHUTDOWN - Discharge Temp High Fault 537 R 0=Normal, 1=Alarm
Circuit #3 Comp #1 - SHUTDOWN - Discharge Temp High Fault 539 R 0=Normal, 1=Alarm
Circuit #1 Comp #1 - SHUTDOWN - Discharge Temp Sensor Fault 529 R 0=Normal, 1=Alarm
Circuit #1 Comp #2 - SHUTDOWN - Discharge Temp Sensor Fault (PFS) 530 R 0=Normal, 1=Alarm
Circuit #2 Comp #1 - SHUTDOWN - Discharge Temp Sensor Fault 531 R 0=Normal, 1=Alarm
Circuit #3 Comp #1 - SHUTDOWN - Discharge Temp Sensor Fault 533 R 0=Normal, 1=Alarm
Circuit #1 Comp #1 - SHUTDOWN - Low pressure ratio Fault 440 R 0=Normal, 1=Alarm
Circuit #2 Comp #1 - SHUTDOWN - Low pressure ratio Fault 442 R 0=Normal, 1=Alarm
Circuit #3 Comp #1 - SHUTDOWN - Low pressure ratio Fault 444 R 0=Normal, 1=Alarm
Circuit #1 Comp #1 - SHUTDOWN - Mechanical High Pressure Fault 601 R 0=Normal, 1=Alarm
Circuit #1 Comp #2 - SHUTDOWN - Mechanical High Pressure Fault (PFS) 602 R 0=Normal, 1=Alarm
Circuit #2 Comp #1 - SHUTDOWN - Mechanical High Pressure Fault 603 R 0=Normal, 1=Alarm
D-EOMOC002(04)09-15EN - 21/35
3
Alarm Point H.R. R/W Range
Circuit #3 Comp #1 - SHUTDOWN - Mechanical High Pressure Fault 605 R 0=Normal, 1=Alarm
Circuit #1 Comp #1 - SHUTDOWN - Mechanical Low Pressure Fault 717 R 0=Normal, 1=Alarm
Circuit #1 Comp #2 - SHUTDOWN - Mechanical Low Pressure Fault (PFS) 718 R 0=Normal, 1=Alarm
Circuit #2 Comp #1 - SHUTDOWN - Mechanical Low Pressure Fault 719 R 0=Normal, 1=Alarm
Circuit #3 Comp #1 - SHUTDOWN - Mechanical Low Pressure Fault 721 R 0=Normal, 1=Alarm
Circuit #1 Comp #1 - SHUTDOWN - Motor Temp High Fault 478 R 0=Normal, 1=Alarm
Circuit #1 Comp #2 - SHUTDOWN - Motor Temp High Fault (PFS) 479 R 0=Normal, 1=Alarm
Circuit #2 Comp #1 - SHUTDOWN - Motor Temp High Fault 480 R 0=Normal, 1=Alarm
Circuit #3 Comp #1 - SHUTDOWN - Motor Temp High Fault 482 R 0=Normal, 1=Alarm
Circuit #1 Comp #1 - SHUTDOWN - Motor Temp Sensor Fault 734 R 0=Normal, 1=Alarm
Circuit #1 Comp #2 - SHUTDOWN - Motor Temp Sensor Fault (PFS) 735 R 0=Normal, 1=Alarm
Circuit #2 Comp #1 - SHUTDOWN - Motor Temp Sensor Fault 736 R 0=Normal, 1=Alarm
Circuit #3 Comp #1 - SHUTDOWN - Motor Temp Sensor Fault 738 R 0=Normal, 1=Alarm
Circuit #1 Comp #1 - SHUTDOWN - Oil Delta Pressure High Fault 637 R 0=Normal, 1=Alarm
Circuit #1 Comp #2 - SHUTDOWN - Oil Delta Pressure High Fault (PFS) 638 R 0=Normal, 1=Alarm
Circuit #2 Comp #1 - SHUTDOWN - Oil Delta Pressure High Fault 639 R 0=Normal, 1=Alarm
Circuit #3 Comp #1 - SHUTDOWN - Oil Delta Pressure High Fault 641 R 0=Normal, 1=Alarm
Circuit #1 Comp #1 - SHUTDOWN - Oil Feed Pressure Sensor Fault 643 R 0=Normal, 1=Alarm
Circuit #1 Comp #1 - SHUTDOWN - Oil Feed Pressure Sensor Fault (PFS) 649 R 0=Normal, 1=Alarm
Circuit #1 Comp #2 - SHUTDOWN - Oil Feed Pressure Sensor Fault (PFS) 650 R 0=Normal, 1=Alarm
Circuit #2 Comp #1 - SHUTDOWN - Oil Feed Pressure Sensor Fault 645 R 0=Normal, 1=Alarm
Circuit #3 Comp #1 - SHUTDOWN - Oil Feed Pressure Sensor Fault 647 R 0=Normal, 1=Alarm
Circuit #1 Comp #1 - SHUTDOWN -Slide position Sensor Fault 756 R 0=Normal, 1=Alarm
Circuit #1 Comp #2 - SHUTDOWN - Slide position Sensor Fault (PFS) 757 R 0=Normal, 1=Alarm
Circuit #2 Comp #1 - SHUTDOWN - Slide position Sensor Fault 758 R 0=Normal, 1=Alarm
Circuit #3 Comp #1 - SHUTDOWN - Slide position Sensor Fault 760 R 0=Normal, 1=Alarm
Circuit #1 Comp #1 - SHUTDOWN - Suction Temp Sensor Fault 698 R 0=Normal, 1=Alarm
Circuit #1 Comp #2 - SHUTDOWN - Suction Temp Sensor Fault (PFS) 699 R 0=Normal, 1=Alarm
Circuit #2 Comp #1 - SHUTDOWN - Suction Temp Sensor Fault 700 R 0=Normal, 1=Alarm
Circuit #3 Comp #1 - SHUTDOWN - Suction Temp Sensor Fault 702 R 0=Normal, 1=Alarm
D-EOMOC002(04)09-15EN - 22/35
3
Alarm Point H.R. R/W Range
Circuit #1 Comp #1 - SHUTDOWN - VFD Over Heat Fault 768 R 0=Normal, 1=Alarm
Circuit #2 Comp #1 - SHUTDOWN - VFD Over Heat Fault 770 R 0=Normal, 1=Alarm
Circuit #3 Comp #1 - SHUTDOWN - VFD Over Heat Fault 772 R 0=Normal, 1=Alarm
Circuit #1 Comp #1 - SHUTDOWN - Low Discharge Superheat Fault 808 R 0=Normal, 1=Alarm
Circuit #1 Comp #2 - SHUTDOWN - Low Discharge SuperHeat Fault (PFS) 809 R 0=Normal, 1=Alarm
Circuit #2 Comp #1 - SHUTDOWN - Low Discharge SuperHeat Fault 810 R 0=Normal, 1=Alarm
Circuit #3 Comp #1 - SHUTDOWN - Low Discharge Superheat Fault 812 R 0=Normal, 1=Alarm
Condenser Entering Water Temp Sensor Fault (EWWD) 365 R 0=Normal, 1=Alarm
Condenser Entering Water Temp Sensor Fault (PFS) 541 R 0=Normal, 1=Alarm
Evaporator Pump #1 Failure - Pump #2 Start Attempted Problem 430 R 0=Normal, 1=Alarm
Evaporator Pump #2 Failure - Pump #1 Start Attempted Problem 431 R 0=Normal, 1=Alarm
Option Fan Alarm Controller Communication Failed Warning 900 R 0=Normal, 1=Alarm
Circuit #1 - RESTART DELAYED - Power Loss While Running Problem 384 R 0=Normal, 1=Alarm
Circuit #2 - RESTART DELAYED - Power Loss While Running Problem 385 R 0=Normal, 1=Alarm
Circuit #3 - RESTART DELAYED - Power Loss While Running Problem 386 R 0=Normal, 1=Alarm
Circuit #1 Comp #1 - SHUTDOWN – Condenser Pressure Sensor Fault 509 R 0=Normal, 1=Alarm
Circuit #2 Comp #1 - SHUTDOWN - Condenser Pressure Sensor Fault 511 R 0=Normal, 1=Alarm
Circuit #3 Comp #1 - SHUTDOWN - Condenser Pressure Sensor Fault 513 R 0=Normal, 1=Alarm
UNIT RESTART DELAYED - Power Loss While Running Problem 379 R 0=Normal, 1=Alarm
UNIT SHUTDOWN - Evaporator Entering Water Temp Sensor Fault 755 R 0=Normal, 1=Alarm
UNIT SHUTDOWN - Evaporator Leaving Water Temp Low (Freeze) 543 R 0=Normal, 1=Alarm
UNIT SHUTDOWN - Evaporator Leaving Water Temp Sensor Fault 589 R 0=Normal, 1=Alarm
UNIT SHUTDOWN - Evaporator Pressure Sensor Fault (PFS) 551 R 0=Normal, 1=Alarm
D-EOMOC002(04)09-15EN - 23/35
3
Alarm Point H.R. R/W Range
UNIT SHUTDOWN - Outside Air Temp Sensor Fault 446 R 0=Normal, 1=Alarm
UNIT SHUTDOWN – Phase Voltage Protection (ATLAS, AWS, EWWD, MNG, PFS) 661 R 0=Normal, 1=Alarm
UNIT SHUTDOWN – Phase Voltage Protection (ACZC, ACHZ, ADZ) 816 R 0=Normal, 1=Alarm
UNIT SHUTDOWN – Condenser Pressure Sensor Fault (PFS) 508 R 0=Normal, 1=Alarm
D-EOMOC002(04)09-15EN - 24/35
Appendix A – ASCII Characters Conversion Table
This table lists the ASCII characters and their decimal and hexadecimal numbers. The MicroTech III
Chiller Unit Controller does not support the characters in boldface type. Also, non-printing characters,
with the exception of the (Space) character, are not listed in this table and are not supported. Characters not
supported are translated to a space.
D-EOMOC002(04)09-15EN - 25/35
Appendix B – Overall Registers Table
This section summarizes all Data/Alarm Points Registers discussed above in the document and listed by
Holding Register address.
D-EOMOC002(04)09-15EN - 26/35
Holding Register
Data Point / Alarm Point
(4xxxx)
Heat Setpoint – Network 37
Capacity Limit Setpoint - Network 38
Circuit #1 - Condenser Refrigerant Pressure 39
Circuit #1 - Condenser Saturated Refrigerant Temp 40
Circuit #1 - Evaporator Refrigerant Pressure 41
Circuit #1 - Evaporator Saturated Refrigerant Temp 42
Circuit #2 - Condenser Refrigerant Pressure 43
Circuit #2 - Condenser Saturated Refrigerant Temp 44
Circuit #2 - Evaporator Refrigerant Pressure 45
Circuit #2 - Evaporator Saturated Refrigerant Temp 46
Circuit #3 - Condenser Refrigerant Pressure 47
Circuit #3 - Condenser Saturated Refrigerant Temp 48
Circuit #3 - Evaporator Refrigerant Pressure 49
Circuit #3 - Evaporator Saturated Refrigerant Temp 50
Circuit #1 - Suction Refrigerant Temp 65
Circuit #1 Comp #1 - Discharge Refrigerant Temp 68
Circuit #1 Comp #1 - Percent RLA 69
Circuit #1 Comp #1 - Current 70
Circuit #1 Comp #1 – Voltage 71
Circuit #1 Comp #1 – Power 72
Circuit #1 Comp #1 – Starts (ACZC, ACZH, ADZ, ATLAS, AWS, GIZMO, WATER STREAM) 73
Circuit #1 Comp #1 – Starts (EWWD, MNG, PFS) 73
Circuit #1 Comp #1 - Run Hours (ACZC, ACZH, ADZ, ATLAS, AWS, GIZMO, WATER STREAM) 74
Circuit #1 Comp #1 - Run Hours (EWWD, MNG, PFS) 74
Circuit #1 Comp #2 - Suction Refrigerant Temp 78
Circuit #1 Comp #2 - Discharge Refrigerant Temp 81
Circuit #1 Comp #2 – Starts (ACZC, ACZH, ADZ, GIZMO, WATER STREAM) 86
Circuit #1 Comp #2 – Starts (PFS) 86
Circuit #1 Comp #2 - Run Hours (ACZC, ACZH, ADZ, GIZMO, WATER STREAM) 87
Circuit #1 Comp #2 - Run Hours (PFS) 87
Circuit #1 Comp #3 – Starts (ACZC, ACZH, ADZ, WATER STREAM) 99
Circuit #1 Comp #3 - Run Hours (ACZC, ACZH, ADZ, WATER STREAM) 100
Circuit #2 Comp #1 - Suction Refrigerant Temp 104
Circuit #2 Comp #1 - Discharge Refrigerant Temp 107
Circuit #2 Comp #1 - Percent RLA 108
Circuit #2 Comp #1 - Current 109
Circuit #2 Comp #1 - Voltage 110
Circuit #2 Comp #1 - Power 111
Circuit #2 Comp #1 – Starts (ACZC, ACZH, ADZ, ATLAS, AWS, WATER STREAM) 112
Circuit #2 Comp #1 – Starts (EWWD, MNG) 112
Circuit #2 Comp #1 - Run Hours (ACZC, ACZH, ADZ, ATLAS, AWS, WATER STREAM) 113
Circuit #2 Comp #1 - Run Hours (EWWD,MNG) 113
D-EOMOC002(04)09-15EN - 27/35
Holding Register
Data Point / Alarm Point
(4xxxx)
Circuit #2 Comp #2 - Starts (ACZC, ACZH, ADZ, WATER STREAM) 125
Circuit #2 Comp #2 - Run Hours (ACZC, ACZH, ADZ, WATER STREAM) 126
Circuit #2 Comp #3 - Starts (ACZC, ACZH, ADZ, WATER STREAM) 138
Circuit #2 Comp #3 - Run Hours (ACZC, ACZH, ADZ, WATER STREAM) 139
Circuit #3 Comp #1 - Suction Refrigerant Temp 143
Circuit #3 Comp #1 - Discharge Refrigerant Temp 146
Circuit #3 Comp #1 - Percent RLA 147
Circuit #3 Comp #1 - Current 148
Circuit #3 Comp #1 - Voltage 149
Circuit #3 Comp #1 - Power 150
Circuit #3 Comp #1 – Starts (AWS) 151
Circuit #3 Comp #1 – Starts (EWWD) 151
Circuit #3 Comp #1 - Run Hours (AWS) 152
Circuit #3 Comp #1 - Run Hours (EWWD) 152
Condenser Pump Run Hours 297
Condenser Pump Status 299
Evaporator Pump #1 Run Hours (ACZC, ACZH, ADZ, ATLAS, AWS, GIZMO, WATER STREAM) 303
Evaporator Pump #1 Run Hours (EWWD, MNG, PFS) 303
Evaporator Pump #1 Status 305
Evaporator Pump #2 Run Hours (ACZC, ACZH, ADZ, ATLAS, AWS, GIZMO, WATER STREAM) 306
Evaporator Pump #2 Run Hours (EWWD, MNG, PFS) 306
Evaporator Pump #2 Status 308
Year 309
Month 310
Date 311
Day of Week 312
Hour 313
Minute 314
Second 315
Units 316
Chiller Model 317
Chiller Location [1] 318
Chiller Location [10] 327
Application Software Version [1] 334
Application Software Version [5] 338
Condenser Entering Water Temp Sensor Fault (EWWD) 365
Evap Ent Water Temp Sensor Fault 366
Condenser Leav Water Temp Sensor Fault 368
Bad setpoint override input Warning 377
Bad demand limit input Warning 378
UNIT RESTART DELAYED - Power Loss While Running Problem 379
Circuit #1 - RESTART DELAYED - Power Loss While Running Problem 384
D-EOMOC002(04)09-15EN - 28/35
Holding Register
Data Point / Alarm Point
(4xxxx)
Circuit #2 - RESTART DELAYED - Power Loss While Running Problem 385
Circuit #3 - RESTART DELAYED - Power Loss While Running Problem 386
START INHIBITED - Ambient Temp Low Problem 388
UNIT INHIBIT LOAD - High Pressure Problem 389
Circuit #1 - INHIBIT LOAD - High Pressure Problem 390
Circuit #2 - INHIBIT LOAD - High Pressure Problem 391
Circuit #3 - INHIBIT LOAD - High Pressure Problem 392
UNIT UNLOAD - High Pressure Problem 394
Circuit #1 - UNLOAD - High Pressure Problem 395
Circuit #2 - UNLOAD - High Pressure Problem 396
Circuit #3 - UNLOAD - High Pressure Problem 397
UNIT INHIBIT LOAD - Low Pressure Problem 410
Circuit #1 - INHIBIT LOAD - Low Pressure Problem 411
Circuit #2 - INHIBIT LOAD - Low Pressure Problem 412
Circuit #3 - INHIBIT LOAD - Low Pressure Problem 413
UNIT UNLOAD - Low Pressure Problem 415
Circuit #1 - UNLOAD - Low Pressure Problem 416
Circuit #2 - UNLOAD - Low Pressure Problem 417
Circuit #3 - UNLOAD - Low Pressure Problem 418
Circuit #1 Comp #1 - UNLOAD - Hi Current Problem 420
Circuit #2 Comp #1 - UNLOAD - Hi Current Problem 422
Circuit #3 Comp #1 - UNLOAD - Hi Current Problem 424
Evap Pump #1 Failure - Pump #2 Start Attempted Problem 430
Evap Pump #2 Failure - Pump #1 Start Attempted Problem 431
Circuit #1 Comp #1 - SHUTDOWN - Low pressure ratio Fault 440
UNIT SHUTDOWN - Low Pressure Ratio 441
Circuit #2 Comp #1 - SHUTDOWN - Low pressure ratio Fault 442
Circuit #3 Comp #1 - SHUTDOWN - Low pressure ratio Fault 444
UNIT SHUTDOWN - Outside Air Temp Sensor Fault 446
Circuit #1 Comp #1 - SHUTDOWN - Current Overload Fault 447
Circuit #2 Comp #1 - SHUTDOWN - Current Overload Fault 449
Circuit #3 Comp #1 - SHUTDOWN - Current Overload Fault 451
Circuit #1 - SHUTDOWN – Low Evaporator Pressure Fault 461
Circuit #2 - SHUTDOWN – Low Evaporator Pressure Fault 462
Circuit #1 Comp #1 - SHUTDOWN – Motor Protector Fault 466
Circuit #1 Comp #2 - SHUTDOWN – Motor Protector Fault 467
Circuit #2 Comp #1 - SHUTDOWN – Motor Protector Fault 468
Circuit #2 Comp #2 - SHUTDOWN – Motor Protector Fault 469
Circuit #1 Comp #3 - SHUTDOWN – Motor Protector Fault 470
Circuit #2 Comp #3 - SHUTDOWN – Motor Protector Fault 471
Circuit #1 Comp #1 - SHUTDOWN - Motor Temp High Fault 478
Circuit #1 Comp #2 - SHUTDOWN - Motor Temp High Fault (PFS) 479
D-EOMOC002(04)09-15EN - 29/35
Holding Register
Data Point / Alarm Point
(4xxxx)
Circuit #2 Comp #1 - SHUTDOWN - Motor Temp High Fault 480
Circuit #3 Comp #1 - SHUTDOWN - Motor Temp High Fault 482
UNIT SHUTDOWN – Condenser Pressure Sensor Fault 508
Circuit #1 Comp #1 - SHUTDOWN – Condenser Pressure Sensor Fault 509
Circuit #2 Comp #1 - SHUTDOWN - Condenser Pressure Sensor Fault 511
Circuit #3 Comp #1 - SHUTDOWN - Condenser Pressure Sensor Fault 513
UNIT SHUTDOWN - Condenser Flow Loss 515
UNIT SHUTDOWN - Condenser High Pressure 516
Circuit #1 - SHUTDOWN – Condenser Pressure High Fault 517
Circuit #2 - SHUTDOWN – Condenser Pressure HighFault 519
Circuit #3 - SHUTDOWN - Condenser Pressure High Fault 521
Circuit #1 Comp #1 - SHUTDOWN - Discharge Temp Sensor Fault 529
Circuit #1 Comp #2 - SHUTDOWN - Discharge Temp Sensor Fault (PFS) 530
Circuit #2 Comp #1 - SHUTDOWN - Discharge Temp Sensor Fault 531
Circuit #3 Comp #1 - SHUTDOWN - Discharge Temp Sensor Fault 533
Circuit #1 Comp #1 - SHUTDOWN - Discharge Temp High Fault 535
Circuit #1 Comp #2 - SHUTDOWN - Discharge Temp High Fault (PFS) 536
Circuit #2 Comp #1 - SHUTDOWN - Discharge Temp High Fault 537
Circuit #3 Comp #1 - SHUTDOWN - Discharge Temp High Fault 539
Condenser Entering Water Temp Sensor Fault (PFS) 541
UNIT SHUTDOWN - Evap Water Flow Loss 542
UNIT SHUTDOWN - Evap Leav Water Temp Low 543
UNIT SHUTDOWN - Evap Low Pressure 544
Circuit #1 - SHUTDOWN – Low Evaporator Pressure Fault 545
Circuit #2 - SHUTDOWN – Low Evaporator Pressure Fault 547
Circuit #3 - SHUTDOWN - Low Evaporator Pressure Fault 549
UNIT SHUTDOWN – Evap Pressure Sensor Fault 551
Circuit #1 - SHUTDOWN – Evaporator Pressure Sensor Fault 552
Circuit #2 - SHUTDOWN – Evaporator Pressure Sensor Fault 554
Circuit #3 - SHUTDOWN - Evaporator Pressure Sensor Fault 556
Circuit #1 Comp #1 - LOCKOUT - Number of Allowed Re-Starts Exceeded Fault 583
Circuit #2 Comp #1 - LOCKOUT - Number of Allowed Re-Starts Exceeded Fault 585
Circuit #3 Comp #1 - LOCKOUT - Number of Allowed Re-Starts Exceeded Fault 587
UNIT SHUTDOWN - Evap Leav Water Temp Sensor Fault 589
Evap Leav Water Temp Sensor Fault 590
UNIT SHUTDOWN - Evap Freeze Protection Fault 592
Circuit #1 Comp #1 - SHUTDOWN - Mechanical High Pressure Fault 601
Circuit #1 Comp #2 - SHUTDOWN - Mechanical High Pressure Fault (PFS) 602
Circuit #2 Comp #1 - SHUTDOWN - Mechanical High Pressure Fault 603
Circuit #3 Comp #1 - SHUTDOWN - Mechanical High Pressure Fault 605
Circuit #1 Comp #1 - SHUTDOWN - Oil Delta Pressure High Fault 637
Circuit #1 Comp #2 - SHUTDOWN - Oil Delta Pressure High Fault (PFS) 638
D-EOMOC002(04)09-15EN - 30/35
Holding Register
Data Point / Alarm Point
(4xxxx)
Circuit #2 Comp #1 - SHUTDOWN - Oil Delta Pressure High Fault 639
Circuit #3 Comp #1 - SHUTDOWN - Oil Delta Pressure High Fault 641
Circuit #1 Comp #1 - SHUTDOWN - Oil Feed Pressure Sensor Fault 643
Circuit #2 Comp #1 - SHUTDOWN - Oil Feed Pressure Sensor Fault 645
Circuit #3 Comp #1 - SHUTDOWN - Oil Feed Pressure Sensor Fault 647
Circuit #1 Comp #1 - SHUTDOWN - Oil Feed Pressure Sensor Fault (PFS) 649
Circuit #1 Comp #2 - SHUTDOWN - Oil Feed Pressure Sensor Fault (PFS) 650
UNIT SHUTDOWN – Phase Voltage Protection Fault 661
Circuit #1 Comp #1 - SHUTDOWN - Starter Fault 662
Circuit #1 Comp #2 - SHUTDOWN - Starter Fault (PFS) 663
Circuit #2 Comp #1 - SHUTDOWN - Starter Fault 664
Circuit #3 Comp #1 - SHUTDOWN - Starter Fault 666
Circuit #1 Comp #1 - SHUTDOWN - Suction Temp Sensor Fault 698
Circuit #1 Comp #2 - SHUTDOWN - Suction Temp Sensor Fault (PFS) 699
Circuit #2 Comp #1 - SHUTDOWN - Suction Temp Sensor Fault 700
Circuit #3 Comp #1 - SHUTDOWN - Suction Temp Sensor Fault 702
Circuit #1 - SHUTDOWN – No Pressure at Startup Fault 711
Circuit #2 - SHUTDOWN – No Pressure at Startup Fault 712
Circuit #3 - SHUTDOWN – No Pressure at Startup Fault 713
Circuit #1 Comp #1 - SHUTDOWN - Mechanical Low Pressure Fault 717
Circuit #1 Comp #2 - SHUTDOWN - Mechanical Low Pressure Fault (PFS) 718
Circuit #2 Comp #1 - SHUTDOWN - Mechanical Low Pressure Fault 719
Circuit #3 Comp #1 - SHUTDOWN - Mechanical Low Pressure Fault 721
Circuit #1 - Controller board offline Fault 723
Circuit #2 - Controller board offline Fault 724
Circuit #3 - Controller board offline Fault 725
Circuit #1 Comp #1 - SHUTDOWN - Motor Temp Sensor Fault 734
Circuit #1 Comp #2 - SHUTDOWN - Motor Temp Sensor Fault (PFS) 735
Circuit #2 Comp #1 - SHUTDOWN - Motor Temp Sensor Fault 736
Circuit #3 Comp #1 - SHUTDOWN - Motor Temp Sensor Fault 738
Unit Power Restore Warning 740
Circuit #1 - Failed pumpdown Warning 741
Circuit #2 - Failed pumpdown Warning 742
Circuit #3 - Failed pumpdown Warning 743
External event Warning 745
Unit Controller board offline Fault 746
Circuit #1 - SHUTDOWN – No Pressure Change After Start 747
Circuit #2 - SHUTDOWN – No Pressure Change After Start 748
Circuit #3 - SHUTDOWN – No Pressure Change After Start 749
Circuit #1 - SHUTDOWN – Phase Voltage Protection Fault (ATLAS, AWS, EWWD, MNG) 751
Circuit #2 - SHUTDOWN – Phase Voltage Protection Fault (ATLAS, AWS, EWWD, MNG) 752
Circuit #3 - SHUTDOWN – Phase Voltage Protection Fault (AWS) 753
D-EOMOC002(04)09-15EN - 31/35
Holding Register
Data Point / Alarm Point
(4xxxx)
UNIT SHUTDOWN - Evap Ent Water Temp Sensor Fault 755
Circuit #1 Comp #1 - SHUTDOWN -Slide position Sensor Fault 756
Circuit #1 Comp #2 - SHUTDOWN - Slide position Sensor Fault (PFS) 757
Circuit #2 Comp #1 - SHUTDOWN - Slide position Sensor Fault 758
Circuit #3 Comp #1 - SHUTDOWN - Slide position Sensor Fault 760
Circuit #1 Comp #1 - SHUTDOWN - VFD Fault 762
Circuit #2 Comp #1 - SHUTDOWN - VFD Fault 764
Circuit #3 Comp #1 - SHUTDOWN - VFD Fault 766
Circuit #1 Comp #1 - SHUTDOWN - VFD Over Heat Fault 768
Circuit #2 Comp #1 - SHUTDOWN - VFD Over Heat Fault 770
Circuit #3 Comp #1 - SHUTDOWN - VFD Over Heat Fault 772
Circuit #1 Comp #1 - SHUTDOWN - COM ERROR With VFD Fault 774
Circuit #2 Comp #1 - SHUTDOWN - COM ERROR With VFD Fault 776
Circuit #3 Comp #1 - SHUTDOWN - COM ERROR With VFD Fault 778
Circuit #1 - INHIBIT LOAD - High Current Problem 780
Circuit #2 - INHIBIT LOAD - High Current Problem 782
Circuit #3 - INHIBIT LOAD - High Current Problem 784
UNIT STOP - Emergency Stop Alarm 798
UNIT STOP - Evap Water Temps Inverted 799
UNIT STOP - External Alarm 800
Circuit #1 Comp #1 - SHUTDOWN - Low Discharge Superheat Fault 808
Circuit #1 Comp #2 - SHUTDOWN - Low Discharge SuperHeat Fault (PFS) 809
Circuit #2 Comp #1 - SHUTDOWN - Low Discharge SuperHeat Fault 810
Circuit #3 Comp #1 - SHUTDOWN - Low Discharge Superheat Fault 812
Bad Current Limit Input Warning 814
Option Controller Communication Failed Warning 815
UNIT SHUTDOWN – Phase Voltage Protection Fault 816
Circuit #1 - SHUTDOWN – Phase Voltage Protection Fault (ACZC, ACZH, ADZ) 817
Circuit #2 - SHUTDOWN – Phase Voltage Protection Fault (ACZC, ACZH, ADZ) 818
Circuit #1 - Failed pumpdown - High Pressure 841
Circuit #2 - Failed pumpdown - High Pressure 842
Option Fan Controller Communication Failed Warning 900
Circuit #1 - Option Fan Alarm Warning 901
Circuit #2 - Option Fan Alarm Warning 902
Circuit #1 - SHUTDOWN - Global Alarm 911
Circuit #2 - SHUTDOWN - Global Alarm 912
Refrigerant Type 1606
Number of Circuits 1607
Number of Compressors 1608
Chiller Tons 1609
Circuit #3 Comp #1 - Actual Capacity 1761
Circuit #3 Comp #1 - Off Auto 1762
D-EOMOC002(04)09-15EN - 32/35
Holding Register
Data Point / Alarm Point
(4xxxx)
Circuit #3 Comp #1 - Full Load 1763
Circuit #3 Comp #1 - VFD Output 1766
Circuit #3 Comp #1 - Oil Feed Pressure 1770
Circuit #3 Comp #1 - Oil Level Status 1772
Circuit #3 Comp #1 - Status 1773
Circuit #2 Comp #3 - Off Auto 1775
Circuit #2 Comp #3 - Status 1786
Circuit #2 Comp #2 - Off Auto 1788
Circuit #2 Comp #2 - Status 1799
Circuit #2 Comp #1 - Actual Capacity 1800
Circuit #2 Comp #1 - Off Auto 1801
Circuit #2 Comp #1 - Full Load 1802
Circuit #2 Comp #1 - VFD Output 1805
Circuit #2 Comp #1 - Oil Feed Pressure 1809
Circuit #2 Comp #1 - Oil Level Status 1811
Circuit #2 Comp #1 - Status 1812
Circuit #1 Comp #3 - Off Auto 1814
Circuit #1 Comp #3 – Status 1825
Circuit #1 Comp #2 - Actual Capacity (PFS) 1826
Circuit #1 Comp #2 - Off Auto 1827
Circuit #1 Comp #2 - Full Load 1828
Circuit #1 Comp #2 - Oil Feed Pressure 1832
Circuit #1 Comp #2 – Status 1838
Circuit #1 Comp #1 - Actual Capacity 1840
Circuit #1 Comp #1 - Off Auto 1841
Circuit #1 Comp #1 - Full Load 1842
Circuit #1 Comp #1 - VFD Output 1845
Circuit #1 Comp #1 - Oil Feed Pressure 1846
Circuit #1 Comp #1 - Oil Feed Pressure 1849
Circuit #1 Comp #1 - Oil Level Status 1851
Circuit #1 Comp #1 – Status 1852
Evaporator SuperHeat Setpoint 1897
Evaporator SuperHeat Temperature 1899
Active Energy 1900
Power Factor 1902
Circuit #3 - EXV Position 1950
Circuit #3 - Outdoor Fan Speed 1954
Circuit #3 - Condenser Approach Temp 1955
Circuit #3 - Evaporator Approach Temp 1956
Circuit #3 - Outdoor Fan Status 1965
Circuit #2 - EXV Position 1966
Circuit #2 - Outdoor Fan Speed 1970
D-EOMOC002(04)09-15EN - 33/35
Holding Register
Data Point / Alarm Point
(4xxxx)
Circuit #2 - Condenser Approach Temp 1971
Circuit #2 - Evaporator Approach Temp 1972
Circuit #2 - Outdoor Fan Status 1981
Circuit #1 - EXV Position 1982
Liquid Temperature 1984
Circuit #1 - Outdoor Fan Speed 1986
Circuit #1 - Condenser Approach Temp 1987
Circuit #1 - Evaporator Approach Temp 1988
Circuit #1 - Outdoor Fan Status 1997
Noise Reduction Auto On 1998
Noise Reduction Status 2000
D-EOMOC002(04)09-15EN - 34/35
The present publication is drawn up by of information only and does not constitute an offer binding upon Daikin Applied Europe S.p.A..
Daikin Applied Europe S.p.A. has compiled the content of this publication to the best of its knowledge. No express or implied warranty is
given for the completeness, accuracy, reliability or fitness for particular purpose of its content, and the products and services presented
therein. Specification are subject to change without prior notice. Refer to the data communicated at the time of the order. Daikin Applied
Europe S.p.A. explicitly rejects any liability for any direct or indirect damage, in the broadest sense, arising from or related to the use
and/or interpretation of this publication. All content is copyrighted by Daikin Applied Europe S.p.A.
D-EOMOC002(04)09-15EN - 35/35
APPENDIX-N
(Instruments Calibration to be attached)
APPENDIX-O
A100- APOLLO DATA CENTRE
ITPC SCOPE START-UP COMMISSIONING OF AIR COOLED CHILLERS ITP NO. HWI-APO-CN-MSS-0009-01 DATE 26/11/2020 DISCIPLINE MECHANICAL
REFERENC SPECIFICATION
Controlling Documents
Acceptance Criteria (Tolerance Inspection & Test Verifying Records (Forms, Checklist, Test 3rd
S/N Activity Description (Drawings,specs, SC MC CNS PM Remarks
Parameters) Method/Equipment Reports) Party
Contract)
1 Genral
Contract Specification, MEP Contractor
All the documents to have minimum status of – No
1.1 Commissioning Method Statement. Mechanical Schematics, Method As per Check List Review of Documents H H S/H S/R R
objection with comments (B)
statement
All the documents to have minimum status of – No
1.2 Commissioning Test Sheets MS attachments As per Check List Review of Documents H H S/H S/R R
objection with comments (B)
All the documents to have minimum status of – No
1.3 Commissioning Risk Assessment RA attachments As per Check List Review of Documents H H S/H S/R R
objection with comments (B)
Testing & Commissioning forAIR COOLED Approved Material, Installation, Shop Chiller Start Up Form
2.2 Commissioning check Refer to method statement and Test report sheet H H S/H S/R W
CHILLERS Drawing
ACTION CODE:
H (Hold Point)- the responsible party has to perform this check/inspection/test and it needs to be successful in order to proceed to the next stage of the construction.
W (Witness Point)- the responsible party has to be informed that check/inspection/test is going to be performed but its presence and signature is not obligatory to move on the next stage
R (Review)-the responsible party has to only review the record/document that check/inspection/test has been done and it passed.
S(Surveillance)- the responsible party has to conduct random visual check/inspection of the activity without formal request for inspection
DISEGNATO AL CAD - VIETATO APPORTARE MODIFICHE A MANO. / DRAWING BY CAD - DO NOT MANUALLY MODIFY THIS DRAWING.
La proprietà del presente disegno e' di
Denominazione / Identification Dis./Dwg. Codice /Part. No.
DAIKIN APPLIED EUROPE S.p.A. Tolleranza generale
La riproduzione, anche se parziale, e la diffusione
senza autorizzazione sono vietate a termini di legge. Ver./Check General Tolerance
This document is reserved property of Data/Date Foglio-Sheet Scala-Scale
DAIKIN APPLIED EUROPE S.p.A.
Appr./Passed
Reproduction or use for any purpose
without authorization is strictly forbidden by law.
DISEGNATO AL CAD - VIETATO APPORTARE MODIFICHE A MANO. / DRAWING BY CAD - DO NOT MANUALLY MODIFY THIS DRAWING.
APPENDIX-Q
QTA.MOD.0055_AWS
ITEM CONTROLLO OK
Homogeneous paint and color , Scratches , Damages , Item burnt , Rust , Cleaning
SHEET METALS 3
Sheet metals , Fan section , Compressor , Evaporator , Fixed screws and bolts , Fixed screw cabin , Application
ASSEMBLYNG rivets , Blunt tip screws channel fan section , Electrical wiring-capillaries no contact hot parts , Connections In /
Out free of obstacles
3
Vertical assembly , Verification model, Bar and S/N , Guarantee seal , Year and month validity start
SECURITY VALVES 3
Homogeneous paint and color , Cover conduit , Presence of all the fixing screws , Tightening cable gland
FANS 3
Homogeneous paint , Oil level , Verification code and S/N , Check oil label and correct data , Removing label
COMPRESSORS nitrogen presence , Delivery pipe tap closed , Suction tap open , Caps blind tightening , Verification heater Volt
and Watt
3
OPTIONAL
XN version spacers neoprene anchor bolts compress. , XN version insulation sandwich on piping liquid , LN
version insulation sandwich suction pipes , Verification requested special treatment battery , Mod Bus Card ,
3
Verification required special insulation , Victaulic for each connection , Gaskets for each connection , Boxes
vibration kit and verification code
PED - standard
TEST TYPE AND
CERTIFICATIONS 3
Microprocessor manual in languge , Multilingual Installation Manual , Certificates CE , Electric scheme ,
DOCUMENTS
ACCOMPANYING
Dimension drawing , Evaporator manual 3
Keys P.E. and evaporator caps on handle switch , Photo chiller four sides, inside P.E., optional , Seals on locks
FINAL AUDIT electrical panel , Label OK/QC 3
ITEM CONTROLLO OK
Homogeneous paint and color , Scratches , Damages , Item burnt , Rust , Cleaning
SHEET METALS 3
Sheet metals , Fan section , Compressor , Evaporator , Fixed screws and bolts , Fixed screw cabin , Application
ASSEMBLYNG rivets , Blunt tip screws channel fan section , Electrical wiring-capillaries no contact hot parts , Connections In /
Out free of obstacles
3
Vertical assembly , Verification model, Bar and S/N , Guarantee seal , Year and month validity start
SECURITY VALVES 3
Homogeneous paint and color , Cover conduit , Presence of all the fixing screws , Tightening cable gland
FANS 3
Homogeneous paint , Oil level , Verification code and S/N , Check oil label and correct data , Removing label
COMPRESSORS nitrogen presence , Delivery pipe tap closed , Suction tap open , Caps blind tightening , Verification heater Volt
and Watt
3
No contact with metal parts , No contact between pipes , Braze welding cleaning and quality , Absence of deep
ASSEMBLED PIPES cuts and creases , Taps closed and cap presence , Blind caps on attacks Schraeder 3
PROTECTION TECTIL To be updated by Daikin for Phase 3 3
Braze welding , Rotalock , Oil sight compressor , Antivibration compressor , Taps , Expansion valves , Deitratore
filter
Color
SIGHTGLASS 3
Fixing , Labels tightening torque
LIFTING BRACKETS 3
Verify code and S/N , Dents , Deformation excessive diaphragms
COILS 3
Verify code and S/N , Precence label In/Out and position , Removing drain plugs
EVAPORATOR 3
Integrity , Cleaning , Bonding , Present on suction pipes , Present on piping liquid line
INSULATION 3
Temperature sensors entered with thermal paste , Gaskets transducers in the seat , Flow switch incoming if not
SENSORS present pump , Flow switch exit if present pump , Verification Bar pressure switches 3
Electrical cables not in contact with sharp metal , Cable fixing with cable ties , Wires under stress , No wires
ELETTRIC CABLES contact with hot pipes 3
Internal plate code / model / Volt / Hz , Removing jumpers used for testing , Voltage cables with stranded copper
ELECTRIC PANEL
by the sheath , Cable wiring tidy , Mechanical operation emergency button , Paint of fuses , Paint on pins fixing
power cables , Caps on the holes present on panel roof , Rubber caps on unused holes , Closing doors
3
alignment
Label identifying Daikin , Warning label , Type Gas label , Multilinguage Gas label , Label quantity Gas for circuit
INNER LABEL ELECTRIC
PANEL
, Check identifying chiller label data , Check weight on label identifying 3
Label identifying Daikin , Logo , Label lifting points , Check identifying SN/CH label data , Check weight on label
CHILLER EXTERNAL LABEL identifying 3
Compilation of RM with annotations and signatures , Dimension drawing and verification code with RM da ,
CHILLER DOCUMENTS
Electric scheme and verification code and revision , Compiling HATA with S/N and signatures , Certificates of
safety valves and check S/N , Certificates evaporators and check S/N , Dielectric tests performed , Dimension
3
drawing and verification code with RM da , Language manual
Check the back of the RM , Check notes for ancillaries not in the catalog , Cabin soundproofing for XN version ,
OPTIONAL
XN version spacers neoprene anchor bolts compress. , XN version insulation sandwich on piping liquid , LN
version insulation sandwich suction pipes , Verification requested special treatment battery , Mod Bus Card ,
3
Verification required special insulation , Victaulic for each connection , Gaskets for each connection , Boxes
vibration kit and verification code
PED - standard
TEST TYPE AND
CERTIFICATIONS 3
Microprocessor manual in languge , Multilingual Installation Manual , Certificates CE , Electric scheme ,
DOCUMENTS
ACCOMPANYING
Dimension drawing , Evaporator manual 3
Keys P.E. and evaporator caps on handle switch , Photo chiller four sides, inside P.E., optional , Seals on locks
FINAL AUDIT electrical panel , Label OK/QC 3
ITEM CONTROLLO OK
Homogeneous paint and color , Scratches , Damages , Item burnt , Rust , Cleaning
SHEET METALS 3
Sheet metals , Fan section , Compressor , Evaporator , Fixed screws and bolts , Fixed screw cabin , Application
ASSEMBLYNG rivets , Blunt tip screws channel fan section , Electrical wiring-capillaries no contact hot parts , Connections In /
Out free of obstacles
3
Vertical assembly , Verification model, Bar and S/N , Guarantee seal , Year and month validity start
SECURITY VALVES 3
Homogeneous paint and color , Cover conduit , Presence of all the fixing screws , Tightening cable gland
FANS 3
Homogeneous paint , Oil level , Verification code and S/N , Check oil label and correct data , Removing label
COMPRESSORS nitrogen presence , Delivery pipe tap closed , Suction tap open , Caps blind tightening , Verification heater Volt
and Watt
3
No contact with metal parts , No contact between pipes , Braze welding cleaning and quality , Absence of deep
ASSEMBLED PIPES cuts and creases , Taps closed and cap presence , Blind caps on attacks Schraeder 3
PROTECTION TECTIL
To be updated by Daikin for Phase 3
Braze welding , Rotalock , Oil sight compressor , Antivibration compressor , Taps , Expansion valves , Deitratore
filter 3
Color
SIGHTGLASS 3
Fixing , Labels tightening torque
LIFTING BRACKETS 3
Verify code and S/N , Dents , Deformation excessive diaphragms
COILS 3
Verify code and S/N , Precence label In/Out and position , Removing drain plugs
EVAPORATOR 3
Integrity , Cleaning , Bonding , Present on suction pipes , Present on piping liquid line
INSULATION 3
Temperature sensors entered with thermal paste , Gaskets transducers in the seat , Flow switch incoming if not
SENSORS present pump , Flow switch exit if present pump , Verification Bar pressure switches 3
Electrical cables not in contact with sharp metal , Cable fixing with cable ties , Wires under stress , No wires
ELETTRIC CABLES contact with hot pipes 3
Internal plate code / model / Volt / Hz , Removing jumpers used for testing , Voltage cables with stranded copper
ELECTRIC PANEL
by the sheath , Cable wiring tidy , Mechanical operation emergency button , Paint of fuses , Paint on pins fixing
power cables , Caps on the holes present on panel roof , Rubber caps on unused holes , Closing doors
3
alignment
Label identifying Daikin , Warning label , Type Gas label , Multilinguage Gas label , Label quantity Gas for circuit
INNER LABEL ELECTRIC
PANEL
, Check identifying chiller label data , Check weight on label identifying 3
Label identifying Daikin , Logo , Label lifting points , Check identifying SN/CH label data , Check weight on label
CHILLER EXTERNAL LABEL identifying 3
Compilation of RM with annotations and signatures , Dimension drawing and verification code with RM da ,
CHILLER DOCUMENTS
Electric scheme and verification code and revision , Compiling HATA with S/N and signatures , Certificates of
safety valves and check S/N , Certificates evaporators and check S/N , Dielectric tests performed , Dimension
3
drawing and verification code with RM da , Language manual
Check the back of the RM , Check notes for ancillaries not in the catalog , Cabin soundproofing for XN version ,
OPTIONAL
XN version spacers neoprene anchor bolts compress. , XN version insulation sandwich on piping liquid , LN
version insulation sandwich suction pipes , Verification requested special treatment battery , Mod Bus Card ,
3
Verification required special insulation , Victaulic for each connection , Gaskets for each connection , Boxes
vibration kit and verification code
PED - standard
TEST TYPE AND
CERTIFICATIONS 3
Microprocessor manual in languge , Multilingual Installation Manual , Certificates CE , Electric scheme ,
DOCUMENTS
ACCOMPANYING
Dimension drawing , Evaporator manual 3
Keys P.E. and evaporator caps on handle switch , Photo chiller four sides, inside P.E., optional , Seals on locks
FINAL AUDIT electrical panel , Label OK/QC 3
ITEM CONTROLLO OK
Homogeneous paint and color , Scratches , Damages , Item burnt , Rust , Cleaning
SHEET METALS 3
Sheet metals , Fan section , Compressor , Evaporator , Fixed screws and bolts , Fixed screw cabin , Application
ASSEMBLYNG rivets , Blunt tip screws channel fan section , Electrical wiring-capillaries no contact hot parts , Connections In /
Out free of obstacles
3
Vertical assembly , Verification model, Bar and S/N , Guarantee seal , Year and month validity start
SECURITY VALVES 3
Homogeneous paint and color , Cover conduit , Presence of all the fixing screws , Tightening cable gland
FANS 3
Homogeneous paint , Oil level , Verification code and S/N , Check oil label and correct data , Removing label
COMPRESSORS nitrogen presence , Delivery pipe tap closed , Suction tap open , Caps blind tightening , Verification heater Volt
and Watt
3
No contact with metal parts , No contact between pipes , Braze welding cleaning and quality , Absence of deep
ASSEMBLED PIPES cuts and creases , Taps closed and cap presence , Blind caps on attacks Schraeder 3
Braze welding , Rotalock , Oil sight compressor , Antivibration compressor , Taps , Expansion valves , Deitratore
PROTECTION TECTIL filter 3
OPTIONAL
XN version spacers neoprene anchor bolts compress. , XN version insulation sandwich on piping liquid , LN
version insulation sandwich suction pipes , Verification requested special treatment battery , Mod Bus Card ,
3
Verification required special insulation , Victaulic for each connection , Gaskets for each connection , Boxes
vibration kit and verification code
PED - standard
TEST TYPE AND
CERTIFICATIONS 3
Microprocessor manual in languge , Multilingual Installation Manual , Certificates CE , Electric scheme ,
DOCUMENTS
ACCOMPANYING
Dimension drawing , Evaporator manual 3
Keys P.E. and evaporator caps on handle switch , Photo chiller four sides, inside P.E., optional , Seals on locks
FINAL AUDIT electrical panel , Label OK/QC 3
ITEM CONTROLLO OK
Homogeneous paint and color , Scratches , Damages , Item burnt , Rust , Cleaning
SHEET METALS 3
Sheet metals , Fan section , Compressor , Evaporator , Fixed screws and bolts , Fixed screw cabin , Application
ASSEMBLYNG rivets , Blunt tip screws channel fan section , Electrical wiring-capillaries no contact hot parts , Connections In /
Out free of obstacles
3
Vertical assembly , Verification model, Bar and S/N , Guarantee seal , Year and month validity start
SECURITY VALVES 3
Homogeneous paint and color , Cover conduit , Presence of all the fixing screws , Tightening cable gland
FANS 3
Homogeneous paint , Oil level , Verification code and S/N , Check oil label and correct data , Removing label
COMPRESSORS nitrogen presence , Delivery pipe tap closed , Suction tap open , Caps blind tightening , Verification heater Volt
and Watt
3
No contact with metal parts , No contact between pipes , Braze welding cleaning and quality , Absence of deep
ASSEMBLED PIPES cuts and creases , Taps closed and cap presence , Blind caps on attacks Schraeder 3
Braze welding , Rotalock , Oil sight compressor , Antivibration compressor , Taps , Expansion valves , Deitratore
3
To be updated by Daikin for Phase 3 3
PROTECTION TECTIL filter
Color
SIGHTGLASS
OPTIONAL
XN version spacers neoprene anchor bolts compress. , XN version insulation sandwich on piping liquid , LN
version insulation sandwich suction pipes , Verification requested special treatment battery , Mod Bus Card ,
3
Verification required special insulation , Victaulic for each connection , Gaskets for each connection , Boxes
vibration kit and verification code
PED - standard
TEST TYPE AND
CERTIFICATIONS 3
Microprocessor manual in languge , Multilingual Installation Manual , Certificates CE , Electric scheme ,
DOCUMENTS
ACCOMPANYING
Dimension drawing , Evaporator manual 3
Keys P.E. and evaporator caps on handle switch , Photo chiller four sides, inside P.E., optional , Seals on locks
FINAL AUDIT electrical panel , Label OK/QC 3
ITEM CONTROLLO OK
Homogeneous paint and color , Scratches , Damages , Item burnt , Rust , Cleaning
SHEET METALS 3
Sheet metals , Fan section , Compressor , Evaporator , Fixed screws and bolts , Fixed screw cabin , Application
ASSEMBLYNG rivets , Blunt tip screws channel fan section , Electrical wiring-capillaries no contact hot parts , Connections In /
Out free of obstacles
3
Vertical assembly , Verification model, Bar and S/N , Guarantee seal , Year and month validity start
SECURITY VALVES 3
Homogeneous paint and color , Cover conduit , Presence of all the fixing screws , Tightening cable gland
FANS 3
Homogeneous paint , Oil level , Verification code and S/N , Check oil label and correct data , Removing label
COMPRESSORS nitrogen presence , Delivery pipe tap closed , Suction tap open , Caps blind tightening , Verification heater Volt
and Watt
3
No contact with metal parts , No contact between pipes , Braze welding cleaning and quality , Absence of deep
ASSEMBLED PIPES cuts and creases , Taps closed and cap presence , Blind caps on attacks Schraeder 3
Braze welding , Rotalock , Oil sight compressor , Antivibration compressor , Taps , Expansion valves , Deitratore
PROTECTION TECTIL filter 3
SIGHTGLASS To be updated by Daikin for Phase 3
Color
3
Fixing , Labels tightening torque
LIFTING BRACKETS 3
Verify code and S/N , Dents , Deformation excessive diaphragms
COILS 3
Verify code and S/N , Precence label In/Out and position , Removing drain plugs
EVAPORATOR 3
Integrity , Cleaning , Bonding , Present on suction pipes , Present on piping liquid line
INSULATION 3
Temperature sensors entered with thermal paste , Gaskets transducers in the seat , Flow switch incoming if not
SENSORS present pump , Flow switch exit if present pump , Verification Bar pressure switches 3
Electrical cables not in contact with sharp metal , Cable fixing with cable ties , Wires under stress , No wires
ELETTRIC CABLES contact with hot pipes 3
Internal plate code / model / Volt / Hz , Removing jumpers used for testing , Voltage cables with stranded copper
ELECTRIC PANEL
by the sheath , Cable wiring tidy , Mechanical operation emergency button , Paint of fuses , Paint on pins fixing
power cables , Caps on the holes present on panel roof , Rubber caps on unused holes , Closing doors
3
alignment
Label identifying Daikin , Warning label , Type Gas label , Multilinguage Gas label , Label quantity Gas for circuit
INNER LABEL ELECTRIC
PANEL
, Check identifying chiller label data , Check weight on label identifying 3
Label identifying Daikin , Logo , Label lifting points , Check identifying SN/CH label data , Check weight on label
CHILLER EXTERNAL LABEL identifying 3
Compilation of RM with annotations and signatures , Dimension drawing and verification code with RM da ,
CHILLER DOCUMENTS
Electric scheme and verification code and revision , Compiling HATA with S/N and signatures , Certificates of
safety valves and check S/N , Certificates evaporators and check S/N , Dielectric tests performed , Dimension
3
drawing and verification code with RM da , Language manual
Check the back of the RM , Check notes for ancillaries not in the catalog , Cabin soundproofing for XN version ,
OPTIONAL
XN version spacers neoprene anchor bolts compress. , XN version insulation sandwich on piping liquid , LN
version insulation sandwich suction pipes , Verification requested special treatment battery , Mod Bus Card ,
3
Verification required special insulation , Victaulic for each connection , Gaskets for each connection , Boxes
vibration kit and verification code
PED - standard
TEST TYPE AND
CERTIFICATIONS 3
Microprocessor manual in languge , Multilingual Installation Manual , Certificates CE , Electric scheme ,
DOCUMENTS
ACCOMPANYING
Dimension drawing , Evaporator manual 3
Keys P.E. and evaporator caps on handle switch , Photo chiller four sides, inside P.E., optional , Seals on locks
FINAL AUDIT electrical panel , Label OK/QC 3
ITEM CONTROLLO OK
Homogeneous paint and color , Scratches , Damages , Item burnt , Rust , Cleaning
SHEET METALS 3
Sheet metals , Fan section , Compressor , Evaporator , Fixed screws and bolts , Fixed screw cabin , Application
ASSEMBLYNG rivets , Blunt tip screws channel fan section , Electrical wiring-capillaries no contact hot parts , Connections In /
Out free of obstacles
3
Vertical assembly , Verification model, Bar and S/N , Guarantee seal , Year and month validity start
SECURITY VALVES 3
Homogeneous paint and color , Cover conduit , Presence of all the fixing screws , Tightening cable gland
FANS 3
Homogeneous paint , Oil level , Verification code and S/N , Check oil label and correct data , Removing label
COMPRESSORS nitrogen presence , Delivery pipe tap closed , Suction tap open , Caps blind tightening , Verification heater Volt
and Watt
3
No contact with metal parts , No contact between pipes , Braze welding cleaning and quality , Absence of deep
ASSEMBLED PIPES cuts and creases , Taps closed and cap presence , Blind caps on attacks Schraeder 3
OPTIONAL
XN version spacers neoprene anchor bolts compress. , XN version insulation sandwich on piping liquid , LN
version insulation sandwich suction pipes , Verification requested special treatment battery , Mod Bus Card ,
3
Verification required special insulation , Victaulic for each connection , Gaskets for each connection , Boxes
vibration kit and verification code
PED - standard
TEST TYPE AND
CERTIFICATIONS 3
Microprocessor manual in languge , Multilingual Installation Manual , Certificates CE , Electric scheme ,
DOCUMENTS
ACCOMPANYING
Dimension drawing , Evaporator manual 3
Keys P.E. and evaporator caps on handle switch , Photo chiller four sides, inside P.E., optional , Seals on locks
FINAL AUDIT electrical panel , Label OK/QC 3
ITEM CONTROLLO OK
Homogeneous paint and color , Scratches , Damages , Item burnt , Rust , Cleaning
SHEET METALS 3
Sheet metals , Fan section , Compressor , Evaporator , Fixed screws and bolts , Fixed screw cabin , Application
ASSEMBLYNG rivets , Blunt tip screws channel fan section , Electrical wiring-capillaries no contact hot parts , Connections In /
Out free of obstacles
3
Vertical assembly , Verification model, Bar and S/N , Guarantee seal , Year and month validity start
SECURITY VALVES 3
Homogeneous paint and color , Cover conduit , Presence of all the fixing screws , Tightening cable gland
FANS 3
Homogeneous paint , Oil level , Verification code and S/N , Check oil label and correct data , Removing label
COMPRESSORS nitrogen presence , Delivery pipe tap closed , Suction tap open , Caps blind tightening , Verification heater Volt
and Watt
3
No contact with metal parts , No contact between pipes , Braze welding cleaning and quality , Absence of deep
ASSEMBLED PIPES cuts and creases , Taps closed and cap presence , Blind caps on attacks Schraeder 3
Braze welding , Rotalock , Oil sight compressor , Antivibration compressor , Taps , Expansion valves , Deitratore
OPTIONAL
XN version spacers neoprene anchor bolts compress. , XN version insulation sandwich on piping liquid , LN
version insulation sandwich suction pipes , Verification requested special treatment battery , Mod Bus Card ,
3
Verification required special insulation , Victaulic for each connection , Gaskets for each connection , Boxes
vibration kit and verification code
PED - standard
TEST TYPE AND
CERTIFICATIONS 3
Microprocessor manual in languge , Multilingual Installation Manual , Certificates CE , Electric scheme ,
DOCUMENTS
ACCOMPANYING
Dimension drawing , Evaporator manual 3
Keys P.E. and evaporator caps on handle switch , Photo chiller four sides, inside P.E., optional , Seals on locks
FINAL AUDIT electrical panel , Label OK/QC 3