Water Works Construction
Water Works Construction
Water Works Construction
HHC-Institute of Technology
Hydraulic structures
• Dams classification & selection
• concrete dams types and load acting
• Earth and rock fill dam parts and appurtenances
• Spillways-types and location
Irrigation: introduction to irrigation methods
Hydropower plants: construction of the different components of hydropower
plant
2. Hydraulic Structures
Storage Components
M.F.L (max Flood Level)
F.R.L (Full reservoir Level)
N.P.L (Normal pool Level)
M.P.L (Minimum pool level)
F.R.L
M.P.L
Reservoir parameters
1.A(H)=f(H)
2. V(H)=f(H)
*The reservoir surface area can be measured
using planimeter.
2.2 Classification of Dams
Factors to be considered
Topography
Foundation
Spillway site
Sediment rate
Cost
Health
Dam type selection
Factors to be considered
Topography and valley shape
Geology and foundation
Availability of construction materials
Overall costs
Spillway site and Location
Earth quake hazards
Hydrology
Environmental conditions
Length of the dam
Collection of Data
Physical and Topographical Data
Valley form
Slope
General Plan
Geotechnical and Geological Data
Dam and Spillway Site, Reservoir site and Earth quake
Water Resources Data
Project Development Data
Miscellaneous Data
General site exploration and investigation involves:
Field investigation
Laboratory tests
2. DESIGN PRINCIPLES OF CONCRETE DAMS
2.1. Forces Acting & Load combination on dams
Primary loads: major importance to all dams irrespective of type.
Example self weight, water & related seepage loads.
Zd = Z2+Kd(Z1-Z2)m
Kd = 0.33 (USBR)
Kd = 0.25 Tennase valley Authority
Kd = 0.25-0.5 U.S corps of Eng’s
b. Secondary loads
i. Sediment load:
A horizontal thrust, Ps generated by accumulated silt
s' .Z 2
Ps K a ; 3
acting @ Z3/3
2
1 Sins
Ka where, s is angle of shearing resistance
1 Sins
ii. Hydrodynamic wave Load
Transient load, Pwave, generated by wave action against the dam depends
on the fetch & wind velocity.
Pwave 2 w H w2
Hw 0.032 UF 0.76 0.2 7 4 F F ≤ 32 km
Where U = wind speed in km/hr
Hw 0.032 UF F > 32 km
F = Fetch length in km
iii. Wind load: when the dam is full, wind acts only on the d/s
side thus contribute to stability. When empty the wind can act
on the u/s face but insignificant compared to hydrostatic load.
Seismic load: Horizontal & vertical inertia loads are generated with respect to the dam & the retained water by
seismic disturbance.
Under reservoir full conditions the most adverse seismic loading will then occur when the ground shock is
associated with:
Vertical foundation acceleration operating downwards and vice-versa for reservoir empty condition
Horizontal Pemh = h Pm
H V 0&
M o
In relation to all probable conditions of loading, the profile
must have sufficient safety factor w.r.t:
Overturning
Over turning
Sliding and
Sliding
Overstress
Overturning stability
Factor of safety against overturning, Fo, in terms of moment
about the d/s toe of the dam.
Fo
M ve
M ve
FSS
H
V
If the foundation plane inclined @ small angle o
H tan
Fss
V
H
1 tan .
V
Fss should not permitted to exceed 0.75, but under ELC up to 0.9 is
acceptable
Shear friction factor, FSF
is the ratio of total resistance to shear & sliding to the total horizontal load.
s
Fsf ; where
H
CAh
s V tan( ) KN / m
cos (1 tan tan ) kN / m
s cAh V tan for horiontal plane( 0)
CAh V tan
Fsf
H.
Limit equilibrium factor, FLE.
the ratio of shear strength to mean applied stress across a
plane i.e
FLE = f
FLE
CAh V cos H sin tan
H cos V sin .
FLE = 2.0 normal operation & FLE =1.3 are recommended minima for limit equilibrium
factors of safety against sliding)
Stress analysis in gravity method
The primary stresses determined in a comprehensive analysis
are:
z V
M *
y1
Ah I
V Vey1 V 6e
z 12 and at y ’=T/2 z 1
T T3 T T
For reservoir full condition (sign convention is reversed for reservoir empty
condition)
V 6e
At the u/s face zu 1
T
T
V 6e
At the d/s face zd 1 T
T
M *
Where e = eccentricity =
V
2. Horizontal & vertical shear stresses
Numerically equal and complementary horizontal (zy) and
(yz) shear stresses are generated at any point as a result of
the variation in normal stress over a plane.
and
z y
2
Where max 2
2
The boundary values, 1 & 3 are determined by:
For upstream face
1u= zu (1+ tan2u)-Pw tan 2u
3u=Pw
a) Stress criteria
Which gives
……. (1)
NB: Dam thickness(T) should be the greater of equations (1) & (2)
For meeting the practical requirements certain changes have to
be made namely:
i) for communication, road has to be provided and therefore a top width;
ii) for wave action, free board above the high flood level must be provided
These changes will cause the resultant force to shift towards the
heel
Hence tension at toe
To prevent this concrete is needed at the u/s
Top Width:
Must resist shock of floating objects (ex. Ice)
Afford a road way
For sake of appearance
Most economical top width (a) = 14% of dam height(H)
Free Board(FB):
Is vertical distance b/n dam crest level & max. water level
Is a function of wave characteristics (wind set-up & wave run-up)
Wind Set-up (S)
Is piling up of water by wind stress
Is determined by Zuider Zee formula:
Therefore, FB = S + Rs
Design of Gravity Dam
Before starting, one must establish whether it is low or high
dam
In a high dam, the allowable stress are often exceeded as the
resultant of all the forces pass outside the middle third;
Upstream Flare:
Height of u/s flare is determined by intersection of line of action
of centroid (crest mass) with u/s middle 3rd line (see fig. next
slide)
Base thickness, T is fixed to satisfy Fo & Fss and checked for heel and toe
stresses.
Multistage Approach
Design commences from crest level, and descends through profile stages
Zone-I:
Fixed on the basis of FB + Crest thickness
Zone-II:
Fixed on the basis of middle 3rd rule; both faces vertical
limited at where R intersects the outer middle 3rd
Zone-III:
Fixed on the basis of middle 3rd rule; u/s face vertical & d/s face batter
limited at a level where R intersects the inner middle 3rd pt
Zone-IV:
Fixed on the basis of middle 3rd rule; both faces batter
limited by inclined compressive stress at d/s face
Zone-V:
D/s face is fixed on the basis of permissible stress & u/s on the basis of
middle 3rd rule
limited by inclined pressure at u/s face
Zone-VI:
Fixed on the basis of max. permissible stress
limited by the level at w/c conformity with permissible stress rule
is incompatible with the design assumption
Zone-VII:
Zone in which the limiting condition for zone-VI prevails and must
be eliminated by revision of entire design
Fig.: Division of gravity dam section in to zones
Stabilizing and heightening
where K0= pressure coefficient & Pds is considered to act at height zAB/3
above the base plane
2.3 Concrete Buttress Dams
Sloping membrane
Buttresses
Mat foundation or Footings
Lateral Braces (strut
Haunches or Corbels
Cutoff (Concrete)
Classification of Buttress Dam
Two ways of classification
The deck slab is cast monolithic with the buttresses and it acts as a
continuous slab.
Reinforcement is provided both on upstream & downstream faces of
the slab.
This type of deck can be used only
when the foundation is strong;
c. Cantilever Deck slab type
The deck slab is cast monolithically with the buttresses in such a manner
that it over hangs on either side of the buttress and acts as cantilever.
Multiple Arch Types Buttress Dam
30 to 45 9 to 12
Above 45 12 to 15
Upstream Slope
Varies from 350 to 450 and is governed by the requirements of sliding
factor, i.e., H/V resistance against sliding is achieved from the
vertical component of the water pressure since self weight of the
buttress dam is relatively small.
Thus for each value of u/s slope there would be an economical buttress
spacing which may be determined from a master curve. A master curve
is extremely useful for determining the most economical spacing for d/t
upstream slopes.
Preliminary design of Buttress and Check for Overall
Stability
For preliminary design of buttress only water pressure on the deck slab, weight of
deck slab and buttress are considered.
Preliminary design of buttress is carried out on the bases of Unit column theory, in
which the buttress is assumed to be made of a number of unit columns.
A unit column is a curved column of unit width.
Assumptions:
Each column transfers the load from the top of the column to the foundation
independently of the adjacent columns above or below it.
Each column is so proportioned that at every section of the column uniform
compressive stress is developed and it is curved to avoid eccentric loading.
The magnitude of the initial load Po depends on the type of joint b/n
deck slab and the buttress.
Loads on Buttress Dam
To determine the site suitability for an arch dam the canyon shape factor (CSF)
equation may be used:
B H (sec 1 sec 2 )
CSF
H
B H (sec 1 sec 2 )
CSF
H
different arches has the same central angle 2 from top to bottom. In practice
2 = 1000 to 1500 is used.
uses about 70% concrete as compared to constant radius arch dam.
Variable Radius Arch Dam
It is a compromise between constant radius and constant angle arch dams, i.e.,
neither the radius nor the angle is constant.
The radii of the extrados and intrados surfaces vary from the top to bottom,
usually maximum at the top and minimum at the base.
The central angle of the different arches is not constant; it usually ranges from
800 to 1500.
It is suitable for V and U-V shaped valleys.
Concrete volume consumed is about 80% of that for constant radius arch dam of
the same height.
Typical Arch-gravity dam plan and section
Multiple-Arch dam
P = F F = whre
F w hre
The transverse unit stress,
t *1 t
Hence, for given stress the required thickness is
w hre
t
Cont’d
re = rc + 0.5t = ri + t
w hrc w hri
t t
all 0.5 w h or
all w h
Differentiating V with respect to and setting to zero, = 133.5o which is the most
economical angle for arch with minimum volume. For = 133.50 r = 0.544B
Thick Cylinder Theory
The major advantage of RCC dam construction is the speed at which the
dam can be constructed, with associated resulting economies.
RCC construction techniques have made RCC gravity dams an
economically competitive alternative to conventional concrete and
embankment dams due to the following factors:
Rapid construction
Accordint to design
According to method of
Constructuion
Fig.: Homogeneous
5/11/2023 127
Hydraulic fill dam:
The materials are excavated, transported and placed by
Hydraulic fill method.
The material mixed with water at borrow pits, is pumped into
flumes laid at a suitable falling gradient along the outer edge
of the embankment
The slush is discharged through the outlets in the flume, at
suitable interval
The course material of the slush settles at the outer edge while
finer material settles at the center.
At present the method is not in general use.
5/11/2023 128
Causes of Failure of Earth Dams
The analysis of earth dam must ask a question:……
Generally, from the previous experiences, the failure of earth dam is grouped in to
Hydraulic failures
Seepage failure
Structural failure
5/11/2023 129
Causes of Failure of Earth Dams
Hydraulic Failures (40%):
Hydraulic failures include the following:
Overtopping
Erosion of u/s face
Erosion of d/s face
Erosion of d/s toe
5/11/2023 130
Seepage failures (30%):
Seepage failures may be due to
(a) Piping through the body of the dam
(b) Piping through the foundation of the dam
(c) Conduit leakage
(d) Sloughing of downstream toe.
5/11/2023 131
Structural Failures (30%):
Structural failures may be due to:
– U/s and D/s slope failures due to pore pressures
– U/s slope failure due to sudden draw down
– D/s slope failure during full reservoir condition.
– Foundation slide: Spontaneous liquefaction
– Failure due to Earth quake
– Slope protection failures
– Failure due to damage caused by burrowing
5/11/2023
animals 132
Fig.: Structural Failures
5/11/2023 133
Phreatic (seepage) line should
Criteria for Safe Design of Earth Dam
exit the dam body safely
Free from Overtopping without sloughing design
appropriate downstream
flood
face.
Adequate spillway
Seepage through
Sufficient the body
outlet worksof
thedam, foundation
Sufficient free and
board
Free from seepage failure abutments should be controlled
by adapting measures.
How can onesuitable
The dam and foundation
satisfy these
Free from structural should be safedesign
against piping
failure failure. criteria????......
There should be no opportunity
There must be proper slope for
free
Safepassage
U/S & D/Sof water
slopefrom
during
protection against wind & rain U/S to D/S both through the
construction
drop erosion. dam and foundation.
Safe U/S slope during sudden
There must be proper drainage draw down condition.
Safe D/S slope during steady
Economic section seepage condition
Foundation shear stress within
the safe limits.
Earth quake resistant dam
5/11/2023 134
Criteria for Safe Design of Earth Dam
1) No overtopping
– appropriate design flood
– Adequate spillway
– Sufficient outlet works
– Sufficient free board
2) No seepage failure
– Phreatic (seepage) line should exit the dam body safely
– Seepage through the body of the dam, foundation and abutments
should be controlled
– Dam and foundation should be safe against piping failure.
5/11/2023 135
3) No Structural failure
Safe u/s & d/s slope during construction
Safe u/s slope during sudden draw down condition.
Safe d/s slope during steady seepage condition
Foundation shear stress within the safe limits.
Earth quake resistant dam
5/11/2023 136
3.4 Seepage Analysis
Seepage analysis is aimed at:
Determination of phreatic line
finding the gradient & velocity of filtration
determination of the seepage flow
5/11/2023 137
Laplace equation for two dimensional flows
In earth dams, the flow is essentially two
dimensional
consider 2-D flows:
Vy+(∂Vy/∂y)∆y
y Vx+(∂Vx/∂x)∆
Vx x
x
Vy
5/11/2023 138
Consider an element of soil size x, y and of unit
thickness
Let Vx and Vy be the entry velocity components in x and
y direction
v x v y
Then, vx x and v y y
x y
will be the corresponding velocity components at the
exit of the element
5/11/2023 139
Assuming invariant soil saturation and and steady flow,
the quantity of water entering the element = the quantity of
water leaving it
Hence,
v x v y
v x y.1 v y x.1 v x x y.1 v y y x.1
x y
From which,
v x v y
0
x y ---------------------------(1)
5/11/2023 140
According to Darcy law,
h
vx K xix K x * ------------------------------(2)
x
h
VY kY IY
y
Ky
------------------------------(3)
5/11/2023 141
Substituting (2) and (3) in (1), we get
2 K x h ( K y .h)
2
0 -----------------------(4)
x 2
y 2
2h 2h
0 -----------------------(5)
x 2
y 2
5/11/2023 142
Substituting velocity potential = = K*h , we get
2 2
--------------------(6)
0
x 2
y 2
5/11/2023 143
The solution gives two sets of curves -
& (or flow lines), mutually
orthogonal to each other
field
b
l
5/11/2023 144
Seepage rate calculation from flow net
Let b & l be width and length of field
Then from Darcy’s law of flow considering unit
thickness
------------------------------(b)
--- -------------------------------(c)
------------------------------(d)
----- (e)
5/11/2023 147
Phreatic line for a homogeneous Earth dam with
horizontal Drainage blanket
Figure (next slide) shows a homogeneous earth dam with horizontal drainage
blanket FK
The phreatic line coincides with the base parabola ADC except at the entrance.
The basic property of the parabola is utilized for drawing the base parabola
That is the distance of any point p from the focus is equal to the distance of the
same point from the directrix.
5/11/2023 148
Fig.: Phreatic line for Homogeneous Dam
5/11/2023 149
Graphical method
Steps:
Starting point of base parabola is @ A AB = 0.3L
F is the focal point
Draw a curve passing through F center @ A
Draw a vertical line EG which is tangent to the curve
EG is the directrix of the base parabola
Plot the various points P on the parabola in such a way that PF = PR
5/11/2023 150
Analytical method
PF = PR
x 2 y 2 x yo
yo b 2 h 2 b
x y x b h b
2 2 2 2
5/11/2023 151
Discharge through the body of Earth dam
v k *i
q v * A k *i * A
dy
q k y *1
dx
d ( y 0 2 xyo )
2
qk ( y o 2 xyo )
2
dx
yo
q k( y o 2 xyo )
2
)(
y o 2 xyo
2
q kyo
5/11/2023 152
Characteristics of Phreatic line (Seepage line)
5/11/2023 153
4) When horizontal filter or drainage toe is provided, the
phreatic line would tend to emerge vertically
5) In the absence of any filter, the seepage line will cut the
downstream slope at some point above the base.
6) The presence of pervious foundation below the dam does
not influence the position of phreatic line.
7) In the case of a zoned dam with central impervious core,
the focus of the base parabola will be located at the
downstream toe of the core
5/11/2023 154
Fig.: Entry conditions of phreatic line
5/11/2023 155
Fig : Flow net for d/t d/s conditions
5/11/2023 156
Q)A homogeneous earthfill dam has a top width of 30m and a
height of 100m with a freeboard of 10m. The side slopes are
1V: 2.5H. It has a horizontal drainage blanket at the base
that extends from the downstream toe to a distance of
100m.
The embankment has a permeability of 1.5 x 10-5 m/s.
Determine the seepage through the dam.
5/11/2023 157
Fig.: Definition sketch
30m
M A B
1V:2.5H
H=100m
1V:2.5H Base Horizontal Blanket
h
parabola
F
b 100m
5/11/2023 158
Question
5/11/2023 159
1.Determine the phreatic surface and seepage rate per foot
length normal to the section that discharges into the blanket
drain.
Solution.
5/11/2023 160
Chapter 4
Dam Outlet Works
The spillway design depends primarily on the design flood, dam type and
location, and reservoir size and operation.
The hydraulics of outlet works usually involve either one or both of two
conditions of flow-open channel (or free) flow and full conduit (or
pressure) flow
Outlet conduit losses are losses due to trash rack, entrance, gate and
valve, transition, contraction and expansion, bends, friction, and exit
losses.
Spillway
A spillway is a structure constructed at or near the dam site to dispose of
surplus water from the reservoir to the channel downstream.
Spillways are provided for all dams as a safety measure against
Overtopping and the consequent damages and failure.
A spillway may be located either in the middle of the dam or at the end of
the dam near abutment.
Spillway Function
To release surplus water that cannot be contained in the allotted
storage space
Passes excess flow in a controlled manner
Many dam failures caused by spillways that were improperly designed
or designed with insufficient capacity
Control Structure
Discharge Channel
Terminal Structure
Outlet Channel
Classification of spillways
The spillway can be classified into different types based on
various criteria.
a. Classification based on purpose
2. Auxiliary spillway
3. Emergency spillway
2. Ogee spillway
4. Chute spillway
5. Shaft spillway
6. Siphon spillway
Free Overfall spillway
This is the simplest type of spillway.
In this type of spillway, the water freely drops down from the crest.
This is suitable for arch dams or dams with downstream vertical faces;
and this is suitable for small drops and for passing any occasional flood.
Free Over fall
Ogee spillway
This is the most widely used spillway.
The overflow type spillway has a crest shaped in the form of an ogee or S-
shape.
The upper curve of the ogee is made to conform closely to the profile of
the lower nappe of a ventilated sheet of water falling from a sharp crested
weir.
Ogee spillway
It is most commonly used with gravity dams. However, it is also used with
earth and rock fill dams with a separate gravity structure;
The ogee crest can be used as control in almost all types of spillways; and
it has got the advantage over other spillways for its high discharging
efficiency.
Ogee type Spillway
Overflow Spillway
Q CL H e
3/ 2
C f ( P, H e , , downstreamsubmergence)
H o
L effectivewidth of spillway
H e
total energyhead over crest
H o
designenergyhead overcrest
Effective width of spillway defined below, where
L L 2( N K
'
p K )H
a e
A shaft (or morning glory) spillway consists of a large vertical funnel, with
its top surface at the crest level of the spillway and its lower end connected
to a vertical (or nearly vertical) shaft.
When the inlet is funnel shaped, the structure is called a Morning Glory
Spillway.
Conduit (or Tunnel) Spillway
Where a closed channel is used to convey the discharge around a dam
through the adjoining hill sides, the spillway is often called a tunnel or
conduit spillway.
Tunnel spillways are advantageous for dam sites in narrow gorges with
steep abutments or at sites where there is danger to open channels from
rock slides from the hills adjoining the reservoir.
Energy Dissipaters
Froude number
Fr = V/(gy)1/2
V2 y2
y1 V1
Lj
Hydraulic Jump
Loss of energy
E = E1 – E2 = (y2 – y1)3 / (4y1y2)
Length of jump
Lj 6y2
Hydraulic Jump
Design guidelines
- Provide a basin to contain the jump
- Stabilize the jump in the basin: tail water control
- Minimize the length of the basin
When Fr > 4.5, but V < 60 ft/sec, use type III basin.
in ft2
(d1+hv1) = specific energy of flow entering the
basin in ft.
Type II Stilling Basin – Fr>4.5
When Fr > 4.5 and V > 60 ft/sec, use Type II stilling basin
Because baffle blocks are not used, maintain a tail water depth 5%
higher than required as safety factor to stabilize the jump.
Type II Stilling Basin – Fr>4.5
Type II Stilling Basin – Fr>4.5
5. Hydropower component
Introduction
Energy can be described as potential for work, which may be withdrawn if needed. The
source for any kind of energy on earth is the sun. This is also valid for nuclear and fossil fuel
when taking into account the genesis of the earth.
The Sun is the primary sources of energy , the energy radiated by the sun in the form of
213
Sources of Energy
214
215
Cont’d
Fuels: thermal power
Fuels such as coal. Oil, and natural gases the most commonly used sources
of energy coal is available in huge quantities in many steam so produced is
utilized in steam turbines coupled to generators.
• Therefore, for generation of electric power, oil, acing costly ,is used for
power production only where small power is required, for instance, as stand-
by power stations.
•Natural gases available in large quantities can be used to run gas engines or
turbines or can be burnt to produce steam and steam turbines can thereafter to
produce power.
Cont’d
Radio Active Substances:
Nuclear power Tremendous amount of heat energy can be by fission of nuclear
disintegration of uranium and other similar fissionable materials the heat energy so
librated in atomic reactors is extracted by pumping fluid or molten metal like liquid
sodium or gas through the pile .
oThe heated exchanger by circulation.
o On the heat exchanger the gas is heated or steam is generated which is utilized
to derive gas or steam turbines coupled with generators there by generating
electrical energy.
Cont’d
Wind speed
Winds have sufficient energy, which can be utilized in wind turbines to derive small
generators. Wind turbines make use of the aerodynamic force generated by aerofoil to
extract power from the wind the method is unreliable as the production of electrical
energy depends largely up on the availability of wind pressure.
Geothermal
The earth has a molten core ,During volcanic action, the material comes out from
the bowels of earth to form volcanic explosions also produces steam vents and hot
springs. This steam can be used for the generation of electric power and space heating.
Cont’d
Waterpower (hydropower)
•Water at high pressure or flowing with a high velocity can be used to run
turbines or water wheels coupled to generators, and therefore, for generation
of electric power.
• This method of generating electric power is well established as one of the
principal energy producing technologies around the world.
•It is widely acclaimed as the cleanest and cheapest of all energy forms.
• 90% of total energy is generated from water.
Advantages and Disadvantage of Hydropower
Advantage
Hydropower has a 'perpetual' source of energy, while thermal power has a depletable fossil
fuel source, besides hydropower does not consume the water.
Running cost of hydropower plant is very low compared to thermal and nuclear plant.
Hydropower plants can be brought in to operation in few minutes while thermal & nuclear
power plants lack this capability. Thus, hydropower plants are particularly useful in taking up
short period peak loads in a power grid system.
Efficiency of hydropower system is very high (90-95%), while thermal power plants have
low efficiency, as low as 40%.
Hydropower development also provides secondary benefit such as recreation, fishing, flood
control etc, where storage is contemplated.
Advantages and Disadvantage of Hydropower
Disadvantage
3. Unconventional Hydro-plants
a. Tidal power plant
Use the tidal energy of the seawater
Very few have been constructed due to structural complication.
b. Wave power plant
c. Depression power plant
Hydropower generated by diverting an ample source of water in the natural
depression
Water level in the depression is controlled by evaporation
Cont’d
3. Unconventional Hydro-plants
a. Tidal power plant
Use the tidal energy of the seawater
Very few have been constructed due to structural complication.
b. Wave power plant
c. Depression power plant
Hydropower generated by diverting an ample source of water in the natural
depression
Water level in the depression is controlled by evaporation
•Hydropower schemes have the ability to store water behind the dam in a reservoir in
order to de-couple generation from hydro inflows
a b c d e
Generally three basic elements are necessary in order to generate power from water:
• Creating head
• A conduit to convey water
• A power plant
Main components
Dam: to create the head necessary to move turbines and impound. Storage is used to
maintain the daily or seasonal flow variations.
Reservoir: Consists of the Water impoundment behind a dam.
Intake: Directs water from reservoir in to the penstock Gates or valves are used to shut off
the flow of water to permit emergency unit shut down or turbine and penstock
maintenance. Racks or screens prevent trash and debris from entering the turbine units.
Penstock: conveys water from the intake structure to the power house and can take many
configurations, depending up on the projects layout.
Surge tanks :are constructed on the conduit to reduce momentum changes due to water
hammer effects.
Main components
Dam: to create the head necessary to move turbines and impound. Storage is used to
maintain the daily or seasonal flow variations.
Reservoir: Consists of the Water impoundment behind a dam.
Intake: Directs water from reservoir in to the penstock Gates or valves are used to shut off
the flow of water to permit emergency unit shut down or turbine and penstock
maintenance. Racks or screens prevent trash and debris from entering the turbine units.
Penstock: conveys water from the intake structure to the power house and can take many
configurations, depending up on the projects layout.
Surge tanks :are constructed on the conduit to reduce momentum changes due to water
hammer effects.
cont’d
Power house
The power house shelters the turbines, generating Units, control and auxiliary equipments,
and sometimes erection and service areas.
Power house types
There are four types of power house configurations (structure)
Indoor: this type of structure encloses all of the power house components under one
roof.
Semi-out door: this powerhouse has a fully enclosed generator room. The main hoisting
and transfer equipment is located on the roof of the plant and equipment is handled
through hatches located in the roof.
cont’d
Outdoor: a generator room is not provided with this type of power house structure.
Generators are enclosed in a weather proof individual cubicles or enclosures and are
recessed in to the floor.
Underground: this type of powerhouse is often used in mountainous areas where there
is limited space available to locate a power plant.
Hydraulic Turbines
Are hydraulic motors or prime movers of a water power development
The shaft power runs electricity generators thus producing electrical power
Turbine Classification
Impulse turbine: All the available potential energy is converted in to kinetic energy
The water after impinging on the curved vanes or bucket is discharged freely to the
downstream channel
Then water moves into the runner through a series of guide vanes
The available energy partly converted to kinetic energy & substantial magnitude
remains in the form of pressure energy
If the external load on the machine suddenly drops to zero (sudden rejection) and the
governing mechanism fails at the same time, the turbine will tend to race up to the
maximum possible speed, known as runaway speed
This limiting speed under no-load, maximum-flow must be considered for safe design
Referring to the previous table and figure discuss which turbine type is more
appropriate in case of:
(i) high head & low discharge?
(ii) medium head & moderate discharge?
(iii) low head & large discharge?
(iv) Low head & high specific speed?
1) Mention the 3-basic components of hydropower plant?
2) Mention source of energy and their classification?
3) To achieve a given total hydropower plant capacity, one may adopt either a small number of large
units (turbines & generators) or a large number of small units. Considering the total costs and
efficiency of the units, elaborate whether you recommend large/small units in case:
(i) The power demand is reasonably uniform;
(ii) Of widely variable operating conditions i.e. wide load variation.
Thank you!