Professional Documents
Culture Documents
Teaching Manuscript 3 BUILDING
Teaching Manuscript 3 BUILDING
TRAINING WORKSHOPS
WORKSHOP TECHNOLOGY
BUILDING WORKSHOP
March 2017
This manuscript is intended for internal use only as teaching compendium at Building
Workshop-Department of Training Workshops, College of Engineering and Technology-
University of Dar es Salaam.
PREFACE
Prepared by:
March 2017
i
ii
CONTENTS
PREFACE..............................................................................................I
2 BUILDING DRAWINGS......................................................................5
4 SITE WORKS..................................................................................21
5 FOUNDATIONS..............................................................................31
5.1 Introduction............................................................................31
6.1 Walls.......................................................................................41
6.2 Bonding..................................................................................49
7 BRIDGING OF OPENINGS...............................................................56
7.1 Bricks/Blocks..........................................................................56
7.2 Timber....................................................................................58
iii
7.3 Steel.......................................................................................58
7.4 Concrete.................................................................................60
8 FORMWORKS.................................................................................82
8.1 Materials................................................................................83
9 ROOFS...........................................................................................93
10 REFERENCES.............................................................................105
iv
1 READING AND INTERPRETING DRAWINGS
1
planning, and building regulations; however, of primary importance, is the
building use and the associated schedule of basic accommodation
including the number and nature of the intended occupants. Thus, we
classify buildings based on their use or purposes as outlined in the
following examples:
For simple building, the design of the total building, including its
internal and external environment, has traditionally been the
responsibility of an architect. However, for a complex building, a
multidisciplinary involvement is necessary whereby engineering,
surveying, services and other specialist skills are integrated with those of
the architect, forming the ‘building team’ to achieve consistent quality
throughout the project.
The building team is a team efort in which each member has a role
to play (Table 1 -1). The building team comprises of diferent people of
diferent professional qualifcations and background. The number of
members in the building team is determined by the type and size of
2
project. The building team in a philosophy of building design views
employees as members of mutually dependent teams of professionals
instead of as individual workers. The philosophy gives ability to identify
and motivate a team that works together and achieves together. A typical
building team is shown in Figure 1 -2.
3
Table 1-1. Professional names and qualifiations as used in the
building team
4
2 BUILDING DRAWINGS
5
Table 2-2. Description and purpose of components of working
drawings*
6
often infuenced by the need to communicate information accurately and
adequately to secure maximum output, the nature of the subject and the
desirability of producing all drawings for a particular project of uniform
size is shown in Table 2 -3. A scale of 1:100 is very popular for plans,
sections and elevations of new buildings. For instance, 1:100 means that
one unit on the drawing represents one hundred units on the site.
7
3 TOOLS AND INSTRUMENTS
The building basic site tools and instruments maybe divided into
three groups, namely:
Figure 3-3. Example of Metal (Left) and Wooden (Right) folding ruler
Spirit level
9
Spirit level, is an instrument designed to indicate whether a surface
is horizontal (level) or vertically upright (plumb). Spirit level are available
in various lengths ranging between 225mm to 1.2m. The shorter lengths
spirit levels are used for adjusting small works or individual bricks. The
longer levels are used for plumbing the work vertically and leveling the
courses horizontally.
Figure 3-4. Example of Linen (Left) and Metal (Right) tape measure
10
Checking for the accuracy of spirit level:
Don’t use the spirit level if the spirit level response is negative to
the checks above.
11
• The liquid at both ends will be at the same level irrespective of
their distances apart.
Plumb bob
12
Figure 3-7. Vertiial alignment using Plumb bob
13
level turns only in a horizontal circles while the transit level can turn in a
vertical as well as horizontal circles.
Procedures:
14
3.1.2 Parts of Dumpy level
15
c) Instruments and methods for setting out right angle: these
include
Optical square
3:4:5 method
Builders’ square
16
The instrument is usually installed on a tripod stand and three
ranging poles are needed when setting out a right angle.
• First, place the instrument vertically above peg C on the base line
AB from which a right angle has to be set out.
• Rotate the instrument slowly until pole A is seen through the
bottom slot.
• An assistant should hold pole B in such a way that it can be seen
when looking through the top right slot of the prism.
• At the indication of the operator, pole B is slightly moved so that it
forms one line with the image of pole A. The base line AB is a
straight line.
• The assistant holding pole D will search the right position under
the guidance of the operator at C.
• The line connecting pole C and D is a line perpendicular to the
base line AB.
Figure 3-11. Use of optiial square to set right (90 degree) angle
17
3.1.4 3:4:5 method principals
18
Figure 3-13. Setting right Angle by using builder square
19
4 SITE WORKS
21
On the other hand, the site for industrial purposes will consider
availability of raw materials, labor, power and fuel, transportation and
communications, markets, the government politics and policy, among
others.
22
spaces to be left in front and sides, heights of the buildings, etc.
should be preferred than squatter.
Size of the site: Keeping in view of local authority restrictions and
meeting the client requirement the shape and size of selected plot
should allow for future extensions. In other words, the plot should be
big enough to accommodate today and future demand.
Terrain Condition: Aspect of site in order to determine orientation
of elevation. Being drier and easier to drain, elevated sites are
generally preferable to low-laying ones. Elevated site ensure also
natural light and air.
23
achieve a safe and economical design of a foundation and
temporary works.
foresee and provide against difculties that may arise during
construction due to ground and other local conditions.
investigate the occurrence of all natural and manmade changes in
conditions and the result arising from those changes.
ensure the safety of surrounding existing struitures.
design for the failed struitures or remedial measures for the
struitures deemed to be unsafe.
locate the ground water table and possible corrosive efect of soil
and water on foundation material.
4.2.1 How to do it
24
4.3.1 Establishing levels on site
Levels are transferred from the OBM to the building site using
Dumpy
Tilting
Automatic level and levelling staf.
25
This is done by checking the dimensions between the new
building and the side boundary. The front line of the building encloses
the building footprint.
26
Step 6: Transfer measurement to the profiles
27
Step 7: Re - check measurement and diagonal
28
EXERCISE I: SETTING OUT
29
5 FOUNDATIONS
5.1 Introduction
Thus, the primary purpose for the foundations design is to safely receive
and transfer the design load of a structure to a suitable subsoil, evenly
and without excessive settlement among other functions. To achieve the
primary goals, the foundations must thus, be able to:
31
5.2 Choice of the foundations
The choice and design of the foundations for domestic and small
types of building depends mainly on the total load of the building and the
bearing capacity of the soil.
The type and magnitude of loads depend on the form and type of
the building to be constructed.
5.2.3 Terminologies
32
o Ultimate or Gross Bearing Capacity: It is the lowest total
pressure which will cause shear failure of the supporting soil
immediately below the footing.
o Net Bearing capacity:
- Bearing pressure: The pressure produced on the ground by
building weight or loads from the building.
- Settlement: Ground movement which may be caused by:
o Deformation of the soil due to imposed loads.
o Volume changes of the soil as a result of seasonal conditions.
o Mass movement of the ground in unstable areas.
- Backfill: Materials excavated from site and if suitable used to fll in
around the walls and foundations.
- Made ground: Refuse, excavated soil deposited to fll in a
depression or to raise the site above the natural level.
33
5.3.1 Shallow foundations
34
5.3.1.1 Strip foundations
35
Figure 5-20. Seitions of some iommon strip foundations
36
Figure 5-22. Some typiial seitions of Isolated Pad Foundations
Raft foundations cover the whole area of the building footprint and
usually extends beyond it. They consist primary of thick reinforced
concrete (R.C) slab up to 450 mm thick, which is thickened under load
bearing walls. Raft foundations are:
• Useful where column loads are heavy thus requiring large bases.
• Best suited on light weight building on soils of low bearing
capacity and structures having basement storey.
• Used when uplift is larger than spread footing can accommodate.
• Used when the use of isolated pads cease to be economical (i.e.
total area of isolated pads exceed 30% of the building footprint).
37
Figure 5-23. Example of Reinforied Raft foundations showing iolumns
38
many cases, piles are linked with pile cap or beams to carry load bearing
walls. Piles may be classifed in several ways depending on the
mechanisms of load transfer.
The pile shaft passes through the soft soil deposit of unsatisfactory
bearing capacity and the base or point rests on the bedrock, dense sand
or gravel where the load is transmitted. The end bearing capacity piles
may include pre-drilled piles or driven piles of concrete, timber or steel.
The friction piles are used where the bedrock, dense sand or gravel
do not exist or are located at the far depth beyond an uneconomical end
bearing piles design. The pile are normally embedded in cohesive soils
and obtains its support or bearing resistance mainly by adhesion or skin
friction of the soil on the surface shaft. Friction piles are commonly of
driven piles of concrete, timber or steel.
39
Figure 5-24. Types of Pile Foundations (a) End bearing pile (b) Friition pile
40
6 WALLS AND BONDING
6.1 Walls
Walls are designed and build to serve some or all of the following:
41
vi. Provide privaiy and seiurity to users and property: External walls
should provide sufcient privacy and security against burglar
vii. Divide and enilose the spaie: The wall defnes areas and encloses
the spaces within the building.
42
Figure 6-25. Typiial example of exterior load bearing walls
43
Figure 6-26. Creating a pass-through load bearing wall
Walls can be made of burnt clay bricks, concrete blocks, either mass
or reinforced concrete, timber, wood, steel, etc. The construction material
44
should be durable, appealing and provide comfort to the dwellers or users.
In Tanzania, bricks and blocks are commonly used as building materials.
The Bricks are mostly used in small towns and villages, whereas Blocks
are commonly used in cities and big towns.
Bricks and blocks basically are of the same species and are
manufactured from the same material. In general, the size makes the
diference between bricks and blocks. In construction industry, the
maximum thickness (in imperial unit) of brick or block bears the size of it.
For instance, a 4” block and 6” block has the thickness of 100mm and
150mm, respectively with the length of the other sides remaining
constant.
The usual brick size is 215 x 102.5 x 65 mm. Allowing for mortar
joint of 10mm gives an overall walling unit size of 225 x 112.5 x 75
mm
Blocks are made to various sizes, a common size being 450 x 230 x
150 mm.
Due to their sizes and easy manufacturing, bricks are cheaper than
blocks.
45
Types of bricks/blocks
6.1.4.2 Mortar
spreads easily and remains plastic while bricks/blocks are being laid
to provide good bond between bricks/blocks and mortar and
acquires early strength.
46
should not be stronger than necessary as excessive strong mortar
concentrates the efects of settlements in fewer and wider cracks.
Types of Mortar
Mortar are named after the binding agent (s) and used for binding
building blocks of stones, bricks or blocks in walls constructions. The ratios
between the binding agent and sand various depending on usage. The
common ones are 1:3, 1:4, 1:6, etc.
i. Lime mortar
Composed of 1 unit of lime in ‘X’ units of sand
Develops strength slowly.
Generally weak mortar.
Their use is limited to temporary jobs.
ii. Cement mortar
Composed of 1 unit of cement in ‘X’ units of sand
Stronger than lime mortar.
Suitable for heavy loaded brickwork or in extremely wet
situation.
47
Also described as gauged or compo mortar.
Composed of 1 unit of cement and 1 unit of lime in ‘X’ units of
sand.
Deliver the best properties of both cement and lime.
Suitable for the general purpose mortar.
48
6.2 Bonding
49
6.2.1 Types of bonding
Header bond consists of all bricks lain as headers in all courses. The
bond is formed by three quarter bat at the quoin in the second course and
repeats after every course. The bond is satisfactory for walls of one brick
thick. Generally used in footing courses or walls curved in plan.
50
Figure 6-36. Walling in a header bond
51
Figure 6-38. Walling in Flemish bond
52
53
EXERCISE II: A QUOIN IN STRETCHER BOND
TASKS:
Assessment Criteria
Correct dimensions
30%
Plumbing and levelling 20%
Accuracy in setting right angle
30%
Neatness and self-organization during work and after work.
20%
54
55
7 BRIDGING OF OPENINGS
lighting,
access, and
ventilation.
Bricks/stones,
wood,
steel,
concrete.
7.1 Bricks/Blocks
56
supports members such as columns. Brick lintel/soldier arches are popular
and superior to wood lintels.
- attractive appearance.
- no corrosion or decay.
- similar appearance as walls.
- weak tensile strength thus, requires steel bars to take tensile
loads.
- require a wooden center to temporary or permanent support
them.
- suitable for small span.
57
7.2 Timber
7.3 Steel
58
Figure 7-41. Example of steel seitions
59
Figure 7-42. Example of steel lintel
7.4 Concrete
60
7.4.1 Quality of Ingredients/components
Types of iement
61
Should be stored in a dry ventilated place. Cement bags should not
be stacked on the foor.
62
depend on the materials, and their proportions, that make up the mixture.
This will determine the workability, strength, durability, economy, volume
stability, and appearance of the fnished hardened concrete. Enough
water is added to make the mix plastic, so that it will fow into the forms.
Too much water, however, will reduce the strength and durability of the
concrete. On other hand, too much little water may not sufce to dissolve
cement. This may cause cement to remain in a dry solid state and hence
failure to undergo hydration reaction. A typical mix would consist of 10%
cement, 15% water, 25% fne aggregates, 45% coarse aggregates, and
1% to 5% entrained or entrapped air. Depending on the desired strength,
the water-cement ratio ranges between 0.4 and 0.6.
7.4.3 Admixtures
Any material added to the concrete mix other than cement, sand,
aggregate, and water is known as an admixture. Admixtures are used to
make the mix more workable, retard or speed up hardening, or increase
chemical resistance. Other admixtures are have no chemical efect but
are used for aesthetic of fnished concrete work. The common admixtures
to concrete include:
63
7.4.4 Placing
7.4.5 Curing
64
The hardening is not dependent on the concrete drying out
but on the moisture available. Thus, it is more important that the concrete
is properly cured to maintain the moisture in the concrete while the
hydration reaction is still active.
7.4.6 Batching
65
7.4.7 Compaction
66
Figure 7-44. Compaition of ionirete using Porker vibrator
Initial setting time, which refers to the time between end of mixing
and casting prior to loss of consistency. The time for initial set
various among types of cement and presence of admixtures. It
takes approximately 30 minutes for concrete made of OPC cement
to lose its consistency and stifen to fow during placement. This is
refers to as initial setting time. Prior to 30 minutes, the consistency
67
of cement is fresh and concrete can fow to take the shape of the
mould.
Final setting time, which refers to the time of no disturbance and
hardening of concrete. It is the period of strength development and
re-working of concrete will cause irrecoverable damage of concrete.
As the concrete undergo fnal setting, although it is still weak and
can be easily damaged, the workability reduces and the concrete
steadily become more difcult to compact or mould.
SLUMP TEST
68
construction. The slump test is performed on fresh concrete. To perform
slump test one needs:
i. Clean internal surface of the mould and apply grease oil to reduce
friction.
ii. Place the mould on a smooth horizontal non-porous base plate.
iii. Take representative sample of fresh concrete, and within 2 minutes
fll the mould with prepared concrete mix in four approximately
equal layers.
iv. Tamp each layer with 25 strokes of the rounded end of tamping rod
in a uniform manner over the cross section of the mould.
v. Strike of top level, remove excess concrete and clean of any
leakage around base of mould and without delay.
69
vi. Clean the out surface of the mould and water leaked out between
the mould and the base plate.
vii. Raise the mould from the concrete immediately and slowly in
vertical direction.
viii. Measure the slump as the diference between the height of the
mould and that of height point of the specimen being tested. If
shear or collapse slumps occur repeat the test with another sample.
ix. Record results.
x. Clean and dry the mould. Do not oil.
There are three type of slump, namely; (i) collapse (ii) shear slump
(iii) true slump as shown in Figure 7 -47.
70
Interpretation of slump test results:
The following are factors that can afect the concrete slump value
71
Size - Larger sizes gives better workability while smaller sizes have
greater specifc surface and greater inter-particle friction, hence less
workability.
HAND MIXING
72
During hand mixing, sand (fne aggregates) are thoroughly mixed to
attain uniform mixture. Coarse aggregates are then placed on top of the
mix and water is poured. The mixture is turned from one side to another
until uniform mixture is achieved. The number of revolutions in hand
mixing is undetermined. However, it is important to maintain speed,
turning number and uniform color of consistency. The uniformity of hand
mixed concrete tend to vary between diferent gangs and time of day.
Nonetheless, compressive strength of hand mixed concrete increases with
in degree of mixing which is measured by number of turning.
MACHINE MIXING
Concrete mixer
Mobile Concrete Mixer Truck
Plant Mixer
For 1cubic meter drum mixer, mixing time between 1 and 1.5
minutes is sufcient. Mixing less than 1 minute may result in non-
uniformity. On the other hand, prolonging mixing time has no signifcant
improvement on uniformity and the resulting strength.
73
Figure 7-48. Conirete Hand Mixing
74
Figure 7-50. Conirete Drum Mix Truik
75
Retaining walls,
Over-site concrete,
Road or parking lots.
76
Figure 7-52. Longitudinal Seition through RC beam showing steel bars
positions
77
Distribution bars: To hold main bars in positions and to take care
of tensile forces in the direction of longest span.
Stirrups/Links bars: To defne the shape and size of the concrete
member and hold bars in position.
Bent up bars/Shear bars: To prevent diagonal shear forces at
supports.
Top/compression bars: To give shape and keep the stirrups up
right or in position. They serve also as compression bar to increase
compressive strength of concrete.
Spacer blocks: Provide the thickness of concrete cover.
Concrete cover: To provide space for concrete to fow and cover
the bottom steel bars. Concrete cover also provide protection
against exposure of main bars to air, which may cause moist attack
and corrosion and rust. Concrete cover also acts as fre resistance to
rebar, which are vulnerable to fre attack.
78
Figure 7-54. Sequenies of operations during manufaiture of pre-stressed
ionirete
79
Figure 7-55. Sequenie of operations during post tensioning of ionirete
TASKS:
80
ASSESSMENT:
81
8 FORMWORKS
82
8.1 Materials
8.1.1 Plywood
83
They are used for facing panel where good quality surface
fnishes are required.
8.1.2 Timber
8.1.3 Steel
84
Steel forms can be installed and dismantled with greater ease and
speed.
The quality of exposed concrete surface by using steel forms is good
and such surfaces need no further treatment
Steel formwork does not absorb moisture from concrete.
8.1.4 Plastics
85
Bracing is by squared and round timbers as well as boards
diagonally arranged.
Tie wires as well as metal screws are used as formwork ties.
86
Figure 8-56. Strip footing Foundations
87
8.2.3 Slab Formwork
88
Figure 8-57. Slab formwork
89
Figure 8-58. Cross-seition view of beam formwork
90
8.2.5 Column formwork
91
EXERCISE IV: COLUMN FORMWORK
92
9 ROOFS
Weather resistance
Regional roof design and construction is an important to the
engineer. A good roof should provide resistance to all kind of nature
weather conditions such as rainfall, sun, wind, earthquake, acidic
conditions etc. It is important that the roof structures is kept on the
house when such extreme condition attack the building.
Strength
Roof structures and covering should be strong to carry
designed load with allowance for unexpected load. Permanent dead
load such as self-weight of roof structures and periodic dead load
from snow and wind should be considered. Roof structure should
also be strong to support live load such as humans and equipment
during construction and maintenance over life time.
Durability
Although the term durability is very relative. Roof structures
and covering should last long without frequent maintenance. It is
therefore, important to use material that has high degree of
resistance to change in weather or climatic conditions. Thus, roof
covering should be able to withstand atmospheric pollution, heat
and other harmful weather conditions.
Fire resistance
93
A good roof will act as resistance to spread of fre in case the
building catches fre. The roof should be able to resist the spread of
fre over the roof and from one building to another. While timber
and grasses can accelerate spread of fre from one room to another
and from one building to next building, natural slates, clay and
concrete tile can confned fre within the area of break out. The
aforementioned covering are designated as roof covering with good
fre resistance.
Thermal design
Thermal design in the roof refers to the fow of both heat and
vapor/water in the roof. A good roof structures and covering design
will consider the amount and type of insulation that will be required
to control both heat loss and condensation. Thermal insulation of
roof is necessary during cold weather to reduce heat losses to an
acceptable level, and to prevent excessive heat gains during hot
weather, thus ensuring a reasonable standard of comfort within the
building.
o Condensation
Appearance
94
The roof is a primary landmark of the building, it should
therefore, be attractive. It should be designed to refect the shape
and elevation views of the building.
Economy
It might be difcult to obtain roof structure and covering that
will have all the above mentioned characteristics of good roof.
However, the choice of good roof structure and covering will remain
the choice of client with the help of architect. In all cases, good roof
should not very expensive.
Roof can be categorized based on the ratio between the raise and
run (Figure 9 -61). This ratio is also known as Pitch. If the angle of pitch is
less or equal to 10°, the roof is termed as Flat roof. If the angle of the
pitch is more than 10°, the roof is referred to as Pitched roof. Figure 9
-61 indicates the pitch, run and rise.
95
Figure 9-61. Rise, Run and Span in Roof Design and Construition
Rise Rise
NOTE:
Pitch=
Run
→∠ Pitch=tan−1 ( Run )
9.2.1 Flat roof
96
Figure 9-62. Warm Flat Roof Design and Construition (Bauder Magazine-
Flat Roof Design Consideration)
Figure 9-63. Cold Flat Roof Design and Construition (Bauder Magazine-
Flat Roof Design Consideration)
97
In an inverted fat roof construction, thermal insulation is located
both on the roof structure and above the waterproofng. In this case, both
the waterproofng, structural deck and support structure are at
temperature close to that of the interior of the building. Ventilation is not
needed in this type of fat roof. This type of fat roof is generally used for
fat roof applications to concrete support structures due to the weight
loading of the ballast that restrain the insulation against wind uplift and
foatation.
98
2. Double Pitched Roofs
Double pitched roofs are also known as Purlin roofs. These are used
in large spans where single roofs are no longer suitable. Purlin are
introduced at design interval (e.g. 3m center to center) to give an
intermediate support to rafters. The purlin may in turn be supported by
struts which bear on the loadbearing partitions or ceiling beams or by
stepped internal partitions.
99
Figure 9-67. Double or Purlin Pitihed Roof
Trussed or framed roof are used over large spans. Further support
to Purlin is provided in the form of trusses, which consists of three sets of
members, i.e. rafters (Figure 9 -68) that are partially supported by purlins
(Figure 9 -69), which are in turn carried by trusses. There are several
types of pitched roof timber trusses (Figure 9 -70):
100
Figure 9-68. Trussed rafter
101
Figure 9-70. Types of pitihed roof
102
9.3.2 Roof covering
The range of roof covering various from that of grasses to tiles and
aluminum of diferent quality and materials. Flat roofs are usually
provided with covering to prevent them from deterioration and also to
prevent roof leakages when raining. Several of the roof covering are
available in the market. Some of most utilized tropical fat roof covering
includes
Bitumat
Mastic asphalt, which is highly suitable for covering concrete roofs.
Built-up bitumen felt
Lead sheeting, Zinc sheeting and copper sheeting.
103
10 REFERENCES
2) S.G Brighty., D.M Stirling. (1989), “Setting out, a guide for site
engineers” BSP Professional books, Oxford.
105