Indian Standard: Code of Practice For Design and Construction OF Pile Foundations
Indian Standard: Code of Practice For Design and Construction OF Pile Foundations
( Reaffirmed 1997 )
Indian Standard
CODE OF PRACTICE FOR
DESIGN AND CONSTRUCTION OF
PILE FOUNDATIONS
PART 1 CONCRETE PILES
( First Revision )
Fifth
Reprint SEPTEMBER 1998
UDC 624.154.33.04
0 Cowrighr 1980
Gr 9 June 1980
IS : a911 ( Part I/Set 3 ) - 1979
Indian Standard
CODE OF PRACTICE FOR
DESIGN AND CONSTRUCTION OF
PILE FOUNDATIONS
PART I CONCRETE PILES
(First Revision)
Foundation Engineering SectionabCommittee, BDC 43
Chainnnn Rcprcsenting
Paop DINESHMOHAN Central Building Research Institute ( CSIR ),
Roorkee
Members
DB R. K. BRANDARK Central B&ding Research Institute ( CSIR ),
Roorkee
SHRI I. G. CHACXO Calcutta Port Trust, Calcutta
SHIU S. GUHA ( Alternate)
SHRI K. N. DADINA In personal capacity ( P-820, Block P, sv’ew Alipore,
Calcutta )
SHRI M. G. DANDAVATE Concrete Association of India, Bombay
SHRI N. C. ~UGGAL ( Alternate )
SHRI R. K. DAS GUPTA Simplex Concr& Piles (*I ) Pvt Ltd, Calcutta
&RI H. GUHA BISIVAS(Ahmate )
SHRI A. G. DA~TIDAR In
personal capacity ( 5 Ifungerford Court, 122
Hungnford Street, Calcutta )
SHRI V. C. DESHP~NDE Pressure Piling Co ( India ) Pvt Ltd, Bombay
DIRECTOR( CS &IRS ) Central Water Commission, New Delhi
DEPUTY DIRECTOR( CSMRS ) ( Alternate )
SHRI A. H. DIVANJI Asia Foundation and Construction Pvt Ltd, Bombay
SHRI A. N. JANGLE ( Altematc )
SHRI A. GHOSHAL Braithwaite Burn & Jessop Construction Co Ltd,
Calcutta
SHRI N. E. A. RAGHAVAN( Alternate)
SHR1 M.IYENGAR Engineers India Ltd, New Delhi
DR R. K. M. BHANDARI( Alfcmate )
DR SHASHI K.GULHATI Indian Institute of Technology, New Delhi
SHRI A. VARADARAJAN (Alternate)
( Continued on page 2 )
@ Copyrighf 1980
BUREAU OF INDIAN STANDARDS
This publication is protected under the Indian Copyright Acf (XIV of 1957 ) and
reproduction in whole or in part by any means except with written permission of the
publisher shall be deemed to be an infringement of copyright under the said Act.
IS : 2911 ( Part I/Set 3 ) - 1979
Mcm6ers Rtpresenfing
SHRI G. S. JAIN G. S. Jain & Associates, Roorkee
JOINT DIRECTOR RESEARCH ( SM) Ministiy of Railways
(RDSO)
JOINT DIRECTORRESEARCH
( B & S ), RDSO ( Al&mute )
DR R. K. KATTI Indiari Instittite of Technology, Bombay
SHRI K. K. KHANNA National Buildings Organization, New Delhi
SHRI SUNILBERRY ( Altqmte )
SHRI 0. P. MALHOTRA B & R Branch, Public Works Department, Govt of
Punjab
SHRI A. P. MATI~UR Central Warehousing Corporation, New Delhi
SHRI V. B. MATHUR Mckenzies Limited, Bombay
SIIRI Y. V. NARASIMRA RAO Bokaro Steel Plant (Steel .4uthority of India ),
Bokaro Steel City
BRIU OMRIR SINCH Engineer-in-Chief’5 Branch, Army Headquarters
MA J H. K.BXITANI ( A&rnntc )
SI*RIB. K. PANTHAKY Hindustan Construction Co Ltd, Bombay
SHRI V. M. MADGE ( Alternate )
SHRI S. R. KULKARNI M. N. Dastur and Company Pvt Ltd, Calcutta
SHRI S. ROY ( Alternate )
SHRI M. R. PUNTA Cementation Co Ltd, Bombay
PRESIDENT * Indian Geotechnical Society, New Delhi
SECRETARY( Alternate )
PROFESSOR ( CIV ENGG) College of Engineering, Guindy, Madras
ASSISTANT PROFESSOR ( CIV ENOO
(Alternate )
SIIRI A. A. RAJU Steel Authority of India, New Delhi
DR GOPAL RANJAN University of Roorkee, Roorkee
DR V. V. S. RAO Nagadi Consultants 1% Ltd, New Delhi
SHRI ARJUNRIJHSINGHANZ Cement Corporation of India, New D&i
SHRI 0. S. SRIVASTAVA( Alltrnatc)
SHRI K. R. SAXENA Engineering Research Laboratorics, Govt of Andhra
Pradesh
DR S. P. SHRIVASTAVA United Technical Consultants Pvt Ltd, New Delhi
DR R. KAPUR ( Affcrnafc )
SIZRIN. SIVAGURU Roads r%Xng, Ministry of Shipping and Tmnsllort
SIIRI S. SEETHARAMAN( Alternate )
SIIRI T. N. SUBBA RAO Gammon India Ltd, Bombay
SHRI S. A. REDDI ( Al~srnate )
SUPERINTENDING E N c I N E E R Central Public \\‘orks lX~p:~rtn3cnt,New D&i
( DeSIoN )
EXIFXJTI~.E ENGINIXER
( DESIGN\J)
( n1ternntt)
SIlRI h1. D. TA~IIXXAR Bombay Port Trust, l%:nnbny
SnRr 1). AJITHASIMIIA, Director Gcncrnl.+B[S ( &-q/i;& Afmbtr )
Director ( Civ Engg )
SIIRI G. RAMAN
Deprlty Director ( Civ Engg )-BE
SIIRI K. Ad. MATHUR
Deputy Director ( Civ Engg ),B’IS
( Cmtimted onfqe 42 )
IS : 890 ( Part IlSec 3 ) -1979
Indian Standard
CODE OF PRACTICE FOR
DESIGN AND CONSTRUCTION OF
PILE FOUNDATIONS
PART I CONCRETE PILES
Section 3 Driven Precast Concrete Piles
( First Revision)
0. FOREWORD
0.1 This Indian Standard (Part I/Set 3 ) ( First Revision ) was adopted
by the Indian Standards Institution on 10 August 1979, after the draft
finalized by the Foundation Engineering Sectional Committee had been
approved by the Civil Engineering Division Council.
0.2 Piles find Application in foundation to transfer loads from a structure
to competent sub-surface strata having adequate load-bearing capacity. The
load transfer mechanism from a pile to the surrounding ground is compli-
cated and could not yet be fully determined, although application of piled
foundations is in practice over many decades. Broadly, piles transfer axial
loads either substantially by friction along its shaft and/or substantially by
the end bearing. Piles are used where either of the above load transfer
mechanism is possible, depending upon the subsoil stratification at a parti-
cular site. Construction of pile foundations requires a careful choice of
piling system, depending upon the subsoil conditions, the load characteristics
of a structure and the limitations of total settlement, differential settlement
and any other special requirement of a project. The installation of piles
demands careful control on position, alignment and depth and involve
specialized skill and experience.
0.3 This standard ( Part I ) was originally published in 1964 and included
provisions regarding driven cast in situ piles, precast concrete piles, bored and
under-reamed piles including load testing. Subsequently, portions pertaining
to under-reamed pile foundations were deleted and which are now covered
in IS : 2911 ( Part III )-1980*. At that time it was decided that the provi-
sions regarding other types of piles should also be published separately for
the ease of reference and to take into account the recent developments in
‘Code of practice for design and construction of pile foundations: Part III Under-
reamed pile foundations ( jsst revision).
3
fS : 2911 ( Part l/Set 3 ) - 1979
this field. This revision has been brought out to incorporate these decisions.
Consequently IS : 2911 ( Part I ) - 1964* has been revised in the follow-
ing sections:
Section 1 Driven cast-in-situ concrete piles
Section 2 Bored cast-in-situ piles
Section 3 Driven precast concrete piles
.
0.3.1 The portion relating to load test on piles has been covered by a
separate part, namely IS : 2911 (Part IV)-1979t. This section covers the
driven precast concrete piles. In this revision, an appendix on the deter-
mination of load-carrying capacity of piles by static formula has been added.
Provisions regarding minimum quantity of cement and reinforcement and
curtailment of reinforcement have been modified.
0.4 Driven Precast Concrete Pile is a pile constructed in a casting yard
and subsequently driven in the ground with or without jetting, or other
technics like preboring ( depending on the conditions of soil ) when the pile
has attained sufficient strength. By driving, the subsoil is displaced and
remain in direct contact with the pile. These piles find w?de application
particularly for structures such as wharves, jett,ies, etc, to act as a free stand-
ing piles above the soil/water level or where conditions are unfavourable
for use of cast-in-situ piles.
0.5 The technical committee, responsible for this standard, while formulating
this standard has given due consideration to the available experience in
this country in pile construction and also to the limitations regarding the
availability of piling plant and equipment.
0.5.1 The information furnished by the various construction agencies and
specialist firms doing piling work in this country and the technical discussions
thereon considerably assisted the committee in formulation of this code.
0.5.2 The committee has also consulted several standards and publications
from different countries of the world, of which special mention can be made
of the following:
BSCP : 2031-1972 Code of practice for foundations,
Recommendation of British Piling Specialist Committee, and
New York City Building Code.
0.6 For the pu,rpose of deciding whether a particular requirement of this
standard is complied with, the fnal value, observed or calculated, express-
ing the result of a test, shall be rounded off in accordance with IS : 2-19601,
The number of significant places retained in the rounded off value should
be the same as that of the specified value in this standard.
___..._-__
*Code of practice for design and construction of pile foundations: Part I Load-hearing
concrete piles.
tCode ofpractice for design and construction of pile foundatins: Part 1V Load test on
piles.
IRules for rounding off numerical values ( reoised ).
4
IS : 2911( Part I/Set 3 ) - 1979
1. SCOPE
1.1 This standard ( Part I/Set 3 ) covers the design and construction of
load-bearing driven precast concrete piles which transmit the load of the
structure to the soil by resistance developed either at the tip by end-bearing
or along the surface of the shaft by friction or by both.
1.2 This standard does not cover the use of driven precast concrete piles for
any other purpose, for example, temporary or permanent retaining structure.
2. TERMINOLOGY
2.0 For the purpose of this standard, the following definitions shall apply.
2.1 Allowable Load - The load which may be applied to a pile after taking
into account its ultimate load capacity, pile spacing, overall bearing capa-
city of the ground below the pile, the allowable settlement, negative skin
friction and the loading conditions including reversal of loads, etc.
2.2 Batter Pile (Raker Pile ). -The pile which is installed at an angle to
the vertical.
2.3 Bearing Pile - A pile formed in the ground for transmitting the load of
a structure to the soil by the resistance developed at its tip and/or along
its surface. It may be formed either vertically or at an inclination ( Batter
Pile) and may be required to take uplift.
If the pile supports the load primarily by resistance developed at the
pile point or base it is referred to as ‘ End Bearing Pile ‘; if primarily by fric-
tion along its surface then as ’ Friction Pile ‘.
2.4 Driven Precast Pile - A pile constructed in concrete ( Reinforced or
Prestressed ) in a casting yard and subsequently driven in the ground when
it has attained sufficient strength.
2.5 Cut-Off Level - It is the level where the installed pile is cut-off to sup-
port the pile caps or beams or any other structural components at that level.
2.6 Drop or Stroke--The distance through which the driving weight is
allowed to fall for driving the pile.
2.7 Factor of Safety - It is the ratio of the ultimate load capacity of a pile,
to the safe load of a pile.
2.8 Nett Displacement - The nett movement of the pile top after the pile
has been subjected to a test load and subsequently released.
2.9 Safe Load - It is the load derived by applying a factor of safety on the
ultimate load capacity of the pile or as determined in the load test.
5
IS : 2911 ( Part I/Set 3 ) - 1979
2.10 Set-The net distance by which the pile penetrates in the ground due
to a stated number of blows of the hammer.
2.11 Test Pile -A pile which is selected for load testing and which is sub-
sequently loaded for that purpose. The test pile may form a working pile
itself,*‘if subjected to routine load test with up to one and one-half times the
safe load.
2.12 Total Displacement ( Gross) - The total movement of the pile top
under a given load.
2.13 Total Elastic Displacement-This is the magnitude of the displacc-
ment of the pile due to rebound caused by the top after removal of a given
test load. This comprises two components:
a) Elastic displacement of the soil participating in the load transfer, and
b) Elastic displacement of the pile shaft.
2.14 Trial Pile - Initially one or more piles, which are not working piles,
may be installed if required to assess the load-carrying capacity of a pile.
These piles are tested either to their ultimate load capacity or to twice the
estimated safe load.
2.15 Ultimate Load Capacity - ‘The maximum load which a pile can carry
before failure of ground ( when the soil fails by shear ).
2.16 Working Load -- The load assigned to a pile as per design.
2.17 Working Pile - A pile forming part of the foundation of a structural
system.
3. NECESSARY INFORMATION
3.1 For the satisfactory design and construction of driven precast piles and
pile foundation, the following information is necessary:
a) Site investigation data as laid down under IS : 1892-1979*, or
any other relevant IS Code. Sections of trial boring, supplemented,
wherever appropriate, by penetration tests, should incorporate data/
information sufficiently below the anticipated level of the pile tip; the
boring below the pile tip should generally be not less than 10 metres
unless bed rock or firm sirata has been encountered earlier. The
nature of the soil both around and beneath the proposed pile should
be indicated on the basis of appropriate tests of strength, compres-
sibility, etc. Ground water levels and conditions ( such as artesian
conditions ) should be indicated. Results of chemical tests to
ascertain the sulphate and chloride content and/or any other dele-
terious chemical content of soil and/or ground water should be
indicated, particularly in areas where large piling is envisaged or
where such information is not generally available.
*Code of practice for subsurface investigations for foundations (jirst reuisiun).
6
IS :2911(PartI/Sec
3)-Pm
4.1 The equipment and accessories will have to be selected depending upon
the hardness of driving, the capacity suitable for the size and weight of the
pile to be handled and the location of work.
4.2 Generally, the equipment for installation of piles consists of a movable
steel or timber structure designed for handling, pitching and driving the
piles in the correct position and alignment. Additional equipment, tackles,
etc, may be necessary to handle the piles from the casting/stacking yard.
*Code of practice fox planning and design of ports and harbours: Part I Site investiga-
tion (Jirst revision) .
7
IS : 2911 ( Part I/Set 3 ) - 1979
5. DESIGN CONSIDERATIONS
5.1 General - Pile foundations shall be designed in such a way that the load
from the structure it supports can be transmitted to the soil without causing
any soil failure and without causing such settlement, differential or total,
under permanent/transient loading as may result in structural damage
and/or functional distress. The pile shaft should have adequate structural
capacity to withstand all loads ( vertical, axial or otherwise ) and moments
which are to be transmitted to the subsoil.
5.2 Adjacent Structures
5.2.1 When working near existing structures care shall be taken to avoid
damage to such structures. Fig. 1 of IS : 2974 ( Part I )-1969’k may bc used
as a guide for studying qualitatively the effect of vibration of persons and
structures.
5.2.2 In case of deep excavations adjacent to piles, proper shoring or
other suitable arrangement shall be done to guard against the lateral move-
ment of soil stratum or releasing the confining soil stress.
5.3 Soil Resistance-The bearing capacity of a pile is dependent on the
properties of the soil in which it is embedded. Axial load from a pile is
normally transmitted to the soil through skin friction along the shaft and
end bearing at its tip. A horizontal load on a vertical pile is transmitted
to the subsoil primarily by horizontal subgrade reaction generated in the
upper part of the shaft. A single pile is normally designed to carry load
along its axis. Transverse load-bearing capacity of a single pile depends
*Code of practice for design and construction of machine foundations: Part I Founda-
tiods for reciprocating type machines (Jirst revision ).
8
IS : 2911 ( Part I/Set 3 >- 1979
on the soil reaction developed and the structural capacity of the shaft under
bending. In case the horizontal loads are of higher magnitude, it is essen-
ti;?l to investigate the phenomena using principles of horizontal subsoil
i-caction adopting appropriate values for horizontal modulus of the soil.
Alternatively, piles may be installed in rake.
53.1 The ultimate bearing capacity of a pile may be estimated approxi-
mately by means of a static formula on the basis of soil-test results, or by
using a dynamic pile formula using data obtained during driving the pile
or by test loading.
The settlement of pile obtained at safe load/working load from load-test
results on a single pile shall not be directly used for casting the settle-
l:lent of a structure unless experience from similar foundations on its settlc-
mcni behaviour is available. The average settlement may be assessed on the
!?t?sir of subsoil data and loading details of the structure as a whole using the
~)rinciples of soil mechanics.
5.3.1.1 Static formula - By using static formula, the estimated value of
i;llimnte load capacity of a typical pile is obtained, the accuracy being de-
tlendent on the reliability of the formula and the reliability of the soil pro-
* ;>ertics for various strata available. The soil properties to be adopted in
such formula may be assigned from the results of laboratory tests and field
test, like standard penetration tests ( IS : 2131-1963* ). Results of cone
penetration tests [see IS : 4968 ( Part I)-19687, IS : 4968 ( Part )X)-1968$,
and IS : 4968 ( Part III ) - 19719 ] may also be utilized where necessary cor-
relation with soil data her been established. The two separate static formulae,
commonly applicable For cohesive and non-cohesive soil respectively, are
iildicated in Appendix A, to serve only as a guide. Other alternative for-
mulae may also be applic,-,ble depending on the subsoil characteristics and
method of installation of piles.
5.3.1.2 Dynanzic formzrla - In non-cohesive soils such as gravels, coarse 1
sand and similar deposits an approximate value of the bearing capacity may
be determined by a dynamic pile formula. The Hiley formula ‘is one of the
more reliable and is most commonly used ( see Appendix B ). The ultimate
bearing capacity of a pile may be estimated approximat.ely by means of a
static formula on the basis of soil-test results, or by using a dynamic pile
formula using data obtained during driving the pile or by test loading,
Dynamic formulae are not directly applicable to cohesive soil deposits
such as saturated silts and clays as the resistance to impact of the toe
4
IS : a911 ( Part I/Set 3 ) - 1979
of the casing will be exaggerated by their low permeability while the fric-
tional resistance on the sides is reduced by lubrication. If as a result of test
loadings on a given area a suitable coefficient can be applied to a dynamic
formula, the results may then be considered of reasonable reliability for that
particular area.
5.3.1.3 Load test results-The ultimate bearing capacity of a single
pile is, with reasonable accuracy, determined from test loading [see
IS : 2911 ( Part IV ) - 1979” 1. The load test on a pile shall not be carried
out earlier than four weeks from the time of installation of the pile.
5.4 Negative Skin Friction or Dragdpwn Force-When a soil stratum,
through which a pile shaft has penetrated into a underlying hard stratum,
compresses as a result of either it being unconsolidated or it being under a
newly placed fill or as a result of remoulding during driving of the pile, a
dragdown force is generated along the pile shaft up to a point in depth where
the surrounding soil does not move downward relative to the pile shaft.
Recognition of the existence of such a phenomenon shall be made and
suitable reduction shall be made to the allowable load where appropriate.
NATE - Estimation of this dragdown force is still under research studies and consi-
derations, ,although a few empirical approaches are in use for the same. The concept is
constantly under revision and therefore no definite proposal is embodied in this standard.
5.5 Structural Capacity - The piles shall have necessary structural strength
to transmit the loads imposed on it, ultimately to the soil
5.5.1 Axial Capacity - Where a pile is wholely embedded in the soil
( having an undrained shear strength not less than 0.1 kgf/cm* ), its axial carry-
ing capacity is not limited by its strength as a long column. Where piles are
installed through very weak soils ( having an undrained shear strength less
than O-1 kgf/cms ), special considerations shall be made to determine whether
the shaft would behave as a long column or not; if necessary, suitable
reductions shall be made for its structural strength following the normal
structural principles covering the buckling phenomenon.
When the finished pile projects above ground level and is not secured
against buckling by adequate bracing, the effective length will be governed
by the fixity conditions imposed on It by the structure it supports atid by
the nature of the soil into which it is installed. The depth below the ground
surface to the lower point of contraflexure varies with the type of the soil
In good soil the lower point of contraflexure may be taken at a depth of 1
metre below ground surface subject to a minimum of 3 times the diameter
of the shaft. In weak soil undrained shear strength ( less than 0.1 kgf/cme )
such as soft clay or soft silt, this point may be taken at about half the depth
of penetration into such stratum but not more than 3 metres or 10 times
the diameter of the. shaft whichever is less. A stratum of liquid mud
___-
*Code of practice for design and construction of pile foundations: Part IV Load test on
piles.
10
-_
IS:291l(PartI/!ke3)-1979
11
IS : 2911 ( Part I/See 3 ) - 1979
12
IS : 2911( Part .I/Sec 3 ) - 1979
the adequacy of the pile group in resisting the applied moment should be
checked. In case of a single pile subjected to moments due to lateral forces
or eccentric loading ground beams may be provided to restrain the pile cap
effectively from lateral or rotational movement.
5.7.4 In case of a structure supported on single piles/group of piles result-
ing into large variation in the number of piles from column to column, it is
likely, depending on the type of subsoil supporting the piles, to result in a
high order of differential settlement. Such high order of differential settle-
ment may be either catered for in the structural design or it may be suitably
reduced by judicious choice of variations in the actual pile loading. For
example, a single pile cap may be loaded to a level higher than that of the
pile in a group in order to achieve reduced differential settlement between two
adjacent pile caps supported on different number of piles.
13
IS : 2911( Part I/Set 3 ) - 1979
5.9 Transier& Loading -- The maximum permissible increase over the safe
load of a pile, as arising out of wind loading, is 25 percent. In case of loads
and moments arising out of earthquake effects, the increase of safe load on
a single pile may be limited to the provisions contained in IS : lS93-1975*.
For transient loading arising out of superimposed loads, no increase may be
generally allowed.
5.10 Overloading - When a pile in a group, designed for a certain safe load,
is found, during or after execution, to fall just short of the load required
to be carried by it, an overload up to 10 percent of the pile capacity may be
allowed on each pile. The total oveiloading on the group should not be
more than 10 percent of the capacity of the group and not more than
40 percent of the allowable load on a single pile. This is subject to the
increase of the load on any pile not exceeding 10 percent of its capacity.
14
IS:2911(PartI/Sec3)-1979
5.113 Reinforcement
5.11.7.1 The longitudinal reinforcement shah be provided in precast
reinforced concrete piles for the entire length. All the main longitudinal
bars shall be of the same length and should fit tightly into the pile shoe if
there is one. Shorter rods to resist local bending moments may be added
but the same should be carefully detailed to avoid any sudden discontinuity
of the steel which may lead to cracks during heavy driving. The area of
main longitudinal reinforcement shall not be less than the following percen-
tages of the cross-sectional area of the piles:
a) For piles with a length less than 30 times the least width - 1.25
percent,
*Code of practice for plain and reinforced concrete ( third revSon ).
15
IS : 2911 ( Part I/Set 3 ) - 1979
b) For piles with a length 30 to 40 times the least width - -- I.5 percent.
and
c) For piles with a length greater than 40 times the least width - 2
percent.
5.11.7.2 The lateral reinforcement is of particular importance in resist-
ing the driving stresses induced in the piles and should be in the form of hoops
or links and of a diameternot less than 6 mm. The volume of lateral reinfor-
cement shall not be less than the following:
a) At each end of the pile for a distance of about 3 times the least
width-not less than 0.6 percent of the gross volume of piles,
and
b) In the. body of the pile-not less than 0.2 percent of the gross
volume of piles.
The spacing shall be such as to permit free flow of concrete around it.
The transition between the close spacing of lateral reinforcement near the
ends and the maximum spacing shall be gradually over a length of 3 times the
least width of the pile.
5.11.7.3 While adopting deformed medium tensile steel as per IS :
1139-1966” or IS : 1786-1966t as reinforcement in the piles, suitable grade
of concrete shall be used keeping in view the stresses which will be induced
during driving of the piles.
5.11.7.4 The cover of concrete over all the reinforcement including bind-
ing wire should not be less than 40 mm, but where the piles are exposed to
sea-water or water having other corrosive content, the cover should be nowhere
less than 50 mm. Cover should be measured clear from the main or longitu-
dinal reinforcement.
NOTE - Where concrete of the pile is liable to be exposed to tie attack of @hates and
chlorides present in the ground wzter, the piles may be coated with a suitable material.
5.11.8 Piles should be provided with flat or pointed co-axial shoes if the)
are driven into or through ground such as rock, coarse gravel, clay with cob-
bles and other soils liable to damage the concrete at the tip of the pile. The
shoe can be of steel or cast iron. In uniform clay or sand the shoe may be
omitted and in these circumstances there may be no advantage in tapering
the tip of the pile.
Where jetting is necessary for concrete piles a jet tube may be cast into
the pile, the tube being connected to the pile shoe which is provided with jet
holes. Generally, a central jet is inadvisable, as it is liable to become chok-
ed. At least two jet holes will be necessary on opposite sides of the shoe,
*Specification for hot rolled mild steel, medium tensile steel and high yield strength ster:l
drformed bars for concrete reinforcements ( revised).
@pecification for cold-twisted steel bars for concrete reinforcement ( w&d )_
16
IS : 2911( Part I/set 3 ) - 1979
four holes giving the best result. Alternatively two or more jet pipes may be
attaclied to the sides of the pile. A balanced arrangement of jets is essential
or the pile is liable to load off.
5.12 Design of Pile Cap
5.U.l The pile caps may be designed by assuming that the load from
column is dispersed at 45Q from the top of the cap up to the mid-depth of
the pile cap from the base of the column or pedestal. The reaction from
piles may also be taken to be distributed at 45” from the edge of the pile,
up to the mid-depth of the pile cap. On this basis the maximum bending
moment and shear forces should be worked out at critical sections. The
method of analysis and allowable stresses should be in accordance with
IS : 4561978*. Other suitable rational methods as agreed between the
concerned parties may also be used.
5.12.2 Pile cap shall be deep enough to allow for necessary anchorage of
the cohunn and pile reinforcement.
5.123 The pile cap should be rigid enough so that -the imposed load could
be distributed on the piles in a group equitably.
5.12.4 In case of a large cap, where differential settlement may be imposed
between piles under the same cap, due consideration for the consequential
moment should be given.
5.12.5 The clear overhang of the pile cap beyond the outermost pile in the
group shall normally be 100 to 150 mm, depending upon the pile size.
5.12.6 The cap is generally cast over a 75 mm thick levelling course of
concrete. The clear cover for main reinforcement in the cap slab shall
not be less than 60 mm.
5.12.7 The pile should project 50 mm into the cap concrete.
5.13 The design of grade beams if used shall be as given in
IS : 2911 (Part HI)-1980t.
6. MATERIALS
Cl Cement - The cement used shall conform to the requirements of IS :
269-1976x, IS : 455-19760, IS : 8041-197811and IS : 6909-19737 as the case
may be.
*Code of practice for plain and reinforcedconcrete ( third revision
1.
t&de of-practice fo; design and construction of pile found&u: Part 111 Under-
reamed D&Z foundations (first revision1.
~Sp&cation for ox&&y and 104 heat Portland cement ( third rat&n ) .
&ecikation for Portland slag cement ( third rmision).
[~S@fia~tion for rapid hardening Portland cement.
~Specification for aupenulphatcd cement.
17
IS : 2911( Part I/Set 3 ) - 1979
63 Concrete
63.1 Materials and method of manufacture for cement concrete of prc-
cast piles shall in general be in accordance with the relevant requirements
given in IS : 456-197811. The stresses in concrete due to working load and
during handling, pitching and driving of the pile should not exceed those
stipulated in IS : 456-197811according to the grade of concrete used and
having due regard to the age of piles at the time of handling.
63.2 The grade of concrete shall be as follows:
Situation Grade of Concrete
For hard driving ( where driving stress Not less than M 20
exceeds 100 kgf/cm* )
For easy driving ( where the driving Not less than M 15
stress is less than 100 kgf/cm2 )
633 Clean water, free from acids and other impurities, shall be used in
the manufacture of concrete.
7. woRKMANsIIIP
7.1 The casting yard for all concrete piles shall preferably be so arranged
that t&y can be lifted directly from their beds and transported to the piling
frame with a minimum of handling. The casting yard should have a well-
drained surface to prevent excessive or uneven settlement due to softening
during manufacture and curing.
7.2 As far as practicable each longitudinal reinforcement shall be in one
length. In cases where joints in reinforcing bars cannot be avoided, the
joints in bars shall be staggered and preferably be made by butt welding.
The hoops and links for reinforcement or by tying with mild steel wire, ‘the
free ends of which should be turned into the interior of the pile. The longi-
tudinal bars may be held apart by temporary or permanent spreader forks
not more than 1.5 metres apart. The reinforcement shall be checked for
tightness and position immediately before concreting.
*Specification for mild steel and medium tensile steel bars and hard-drawn steel wire for
concrete reinforcement: Part I Mild steel and medium tensile steel bars ( second revision).
tSpecification for hot rolled mild steel, medium tensile steel and high yield strength
steel deformed bars for concrete reinforcements (revised).
SSpecification for cold-twisted steel bars for concrete reinforcement (m&d)).
&Specification for structural steel standard quality (Jiflh revision).
\lCode of practice for plain and reinforced concrete ( third reoirion ).
18
IS : 2911( Part I/Set 3 ) - 1979
without difficulty. The order of stacking shall be such that the older pile&
~811be withdrawn for driving without disturbing the newer pilea. Separate
stacks shall be provided for different lengths of piles. Wherever euring
is needed during storage, arrangements shall be made to enable the pilea
to be watered if weather conditions so require. For &tailed precautions
with regard to curing operations reference may be made to IS : 4561978%
7.4.3 Care shall be taken at all stages of transporting, lifting and handling
of the piles that they are not damaged or cracked. During transportation
the piles shall be supported at the appropriate lifting holes provided for thq
purpose. If the piles are put down temporarily after being lifted they shall
be placed on trestles or blocks located at the lifting points.
20
IS :2911(PartI/Skc3)-1979
damaged. The hammer, helmet, dolly and pile should be coaxial and
should sit squ’arely one upon the other.’ It is always preferable to employ
the heaviest hammer practicable and to limit the stroke so as not to damage
the pile. When choosing the size of the hammer, regard should be given to
whether the pile is to be driven to a given,resistance or to a given depth.
The stroke of a single acting or drop hammer should be limited to 1-Z m,
preferably 1 m. A shorter stroke with particular care should be used when
there is a danger. of damaging the pile. The following are examples of such
conditions:
a) Where in the early stages of driving a long pile, a hard layer near
the ground surface has to be penetrated.
b) Where there is a very soft grotmd up to a considerable depth, so that
a large penetration is achieved at each hammer blow.
c) Where the pile is expected suddenly to reach refusal on rock or
other- virtually impenetrable soil.
When a satisfactory set with an appropriate.hammer and drop for the
last 10 blows has been achieved, repeat sets should only be carried out with
caution and long-continued driving, after the pile has almost ceased to pene-
trate, should be avoided, especially when a hammer of moderate weight is
used. It is desirable that a full driving record be taken on one pile in every
hundred driven, and on the first few piles in a new area.
7.5.4.1 Any sudden change in the rate of penetration which cannot be
ascribed to normal changes in the nature of the ground should be noted
and the cause ascertained, if possible, before driving is continued.
7.5.4.2 When the acceptance of piling is determined by driving to a
set, the driving conditions when taking the set should be the same as those
used when the sets of test piles were obtained.
7.5.5 The head of precast concrete pile should be protected with packing
of resilient material, care being taken to ensure that it is evenly spread and
held securely in place. A helmet should be placed over the packing and
provided with a dolly of hardwood or other material not thicker than the
width of the pile.
7.5.6 Jetting may be used as a means of minimizing or eliminating the
resistance at the toe: frictional resistance along the surface of the pile shaft
may also be reduced. By reducing the toe resistance very hard driving and
vibration can be avoided and greater rates and depths of penetration can be
achieved than by percussive methods. Jetting is effective in cohesionless
soils such as sand, gravel and fine-grained soils provided the percentage of
clay is small; it is not effective in clay soils.
7.5.6.1 Jetting of piles should be carried out only when it is des$ed and
in such a manner as not to impair the bearing capacity of the piles already
in place, the stability of the ground or the safety of any adjoining buildings.
21
7.5.6.2 The quantity of water required for effective jetting is directly
related to the cross-sectional area of the piles (including external jet piles );
up to 2 litres per minute per square centimetre of pile cross-section may be
required at the pile in dense cohesionless soils; loosely compacted soils may
require less water. The pressure should be from 5.6 kgf/cm’ to 106 kgf/cm*
or more. If large quantities of water are used, it may be necessary to
make provision for leading away the water that emerges at the ground
surface so that the stability of the piling equipment is not endangered by the
softening of the ground.
7.5.6.3 The arrangement of the jets should be balanced to ensure that
the pile penetrates vertically. Independent piles surged down or two pipes
attached to the opposite sides of the pile may be used. To minimize the
risk of blockages the nozzles should not be positioned at the point of the toe.
Acceptable verticality may be achieved by the use of rigid Ieaders and allow-
ing the pile to enter the ground gradually, after operating the water under
weight of the pile and hammer, the rate of penetration being controlled by
the pile winch. Once maximum apparent penetration is achieved by this
method, further penetration may generally be obtained in cohesionless soils
by light driving whilst the water jets are running. When jetting is completed
the piles should be driven to the final penetration or set.
7.5.6.4 Jetting should be stopped before completing the driving, which
should always be finished by ordinary methods. Jetting should be stopped
if there is any tendency for the pile tips to be drawn towards the piles already
driven owing to disturbance to the ground.
7.5.6.5 Jets shall be tested before driving commences. If it becomes
necessary to jet a pile which is not provided with built-in-jet, satisfactory
results can be obtained by working on independent jet pipes down the out-
side of the pile, the jet being worked alternatively down the several faces of
the pile to assist verticality.
7.5.7 ControI of Alignment - Piles shall be installed as accurately as
possible as per the designs and drawings either vertically or to the specified
better. Greater care should be exercised il; respect of installation of single
pile or piles in two pile groups. As a guide, for vertical piles a deviation of
1.5 percent and for raker piles a deviation of 4 percent should not normally
be exceeded although in special cases a closer tolerance may be necessary.
Piles should not deviate more than 75 mm from their designed positions at
the working level of the piling.rig. In the case of a single pile m a column
positional tolerance should not be more than 50 mm. Greater tolerance
may be prescribed for piles driven over water and for raking piles. For
piles to be cut-off at a substantial depth, the design should provide for the
worst combination of the above tolerances in position and inclination. In
case of piles deviating beyond these limits and to such an extent that the re_
sulting eccentricity cannot be taken care of by a re-design of the pile cap or
22
Is:a91l(P8rtIpec3)-1979
pile ties! the piles should be replaced or supplemented by one or more addi-
tional piles.
Nm -In case of raker pila up to a rake of 1 in 6, there nuy be no reduction in the
capacity of the pile.
be joined by full penetration butt welding. The concrete at the top of the
original pile should be cut down to expose not less than 200 mm of the bars.
The bars should be held accurately and rigidly in position during welding.
Where facilities to site are insufficient to make good butt welding practicable,
the joint may be made by lapping. The reinforcement at the head of the
pile will need to be exposed for a distance of 40 times the bar diameter and
the new bars overlapped for this distance. If the bonds are lapped, spot
welding shall be done As an alternative special bottle nut joints may be
provided.
7.9 Risen Piles - In ground where there is a possibility of piles rising due
to ground heave, levels of the tops of the piles should be measured at interval
while nearby piles are being installed. Piles which have risen as a result of
drivirig adjacent piles should be redriven to the original depth or resistance,
unless redriving tests on neighbouring piles have shown this to be
unnecessary.
7.10 Defective piles shall be removed or left in place whichever is convenient
without affecting performance of the adjacent piles or the cap as a whole.
Additional piles shall be provided to replace them.
8.1 General - The stresses set up when handling prestressed piles of given
length can be resisted by smaller cross-section and thus economy in materials
may be achieved. The small cross-section may permit or necessitate greater
penetration. The bearing capacity may govern the cross-section of a pile
and could preclude the use of the smaller sizes that would be possible from
strength considerations alone. The tensile stresses caused by the action
of stress waves when driving can be reduced by the prestress. The reduc-
tion of tensile cracks may give greater durability to the pile, particularly if
the pile is submerged. The piles are better able to resist, without cracking,
any tensile forces set up by the working loads, whether direct or due to bend-
ing, or by accidental loads.
8.2 Concrete
8.2.1 The maximum axial stress that may be applied to a pile acting as a
short strut should be 25 percent of the specified works cube strength at 28
days !ess the prestress after losses.
8.2.2 The static stresses produced during lifting and pitching should not
exceed the values given in IS : 1343-1960’#,the values relating to loads of
short duration. To allow for impact, the tensile stresses during transport,
calculated as static stresses, should not exceed one-third of the values
calculated as .above.
*Code of practice for prcstresscd concrete.
24
IS : 2911 ( Part I/Set 3 ) - 1979
8.3 Prestresses
8.3.1 The prestress after allowing for losses of prestress should satisfy
the following conditions:
a) Prestress to cover handling, transporting and lifting conditions.
For this purpose it may be assumed that only 75 percent of the
full loss of prestrcss will have occnred witl:in LYJOmonths of
casting.
b) Prestress in N/mma of not less than 0.07 times the ratio of the
length of the pile to its least lateral dimensions.
c) Minimum prestress related to the ratio of effective weight of hammer
to weight of pile to be as follows:
Ratio of hammer to pile weight not 0.9 0.8 0.7 0.6
less t’han
Minimum prestress for narxal driv- 20 35 50 60
ing, kgf/cm7
Minimum prestress for easy driving, 35 40 50 60
kgf/cmz
8.3.1.1 For diesel hammers the minimum prestress should be 5 N/mmg
( 50 kgf/cmz ).
8.3.2 A considerably greater prestress may be required for raking piles,
particularly if these are driven in ground which may tend to deflect the piles
from their true alignments.
8.3.3 Loss of prestress should be calculated in accordance with IS : 1343-
1960’%.
25
IS:a9ll(PartI/Sec3)-1979
8.6 Workmanship
8.6.1 Manufacture Curing and Transfer of IVestress - Prestressed piles
require high strength concrete and careful control during manufacture,
usually this means casting in a factory where the curing conditions can be
strictly regulated. Where piles have to be lengthened the procedure is more
elaborate. ( see 8.7 ).
8.6.2 Manufacture - Prestrcssed concrete piles are normally cast by
the ‘ long-line ’ method in a factory under conditions of close control. Where
piles are cast other than in factory, casting should take place in an enclosed
space at an air temperature of not less than 10°C ( 50?F). Piles should
not be removed from the place of casting until after the transfer of prestress.
The piles should be cast in one operation using internal and external
vibrators to assist compaction of the concrete.
Care should be taken to ensure that vibration from adjoining work
does not affect the placed concrete during the setting period. Care should
be taken that the head of the piles is finished plane and normal to the axis
of the pile. Each pile should be marked with a reference number and rate uf
casting. Curing should be carried out as described in 7.3.3 or the piles may
be steam cured.
8.6.3 Transfer of Prcstress - Whenever a batch of piles is cast, four test
cubes should be cast and stored in close proximity to and under the SLLIIK
conditions of temperature and humidity as the piles.
The minimum cube strength of the concrete at transfer of prestrcsb
should be 2.5 times the stress in the concrete at transfer, or 28 N/mm’ ( ZSIJ
kgf/cm’l ) for strand or crimped wire or 35 N/mm2 ( 350 kgf/cm’ ) for plain
or indented wire, whichever is the greater. The attainment of this strength
may be checked either by testing the relevant test cubes or by allowing suffi-.
cient times to elapse after casting. provided this period can be shown to bc
*Specification for hot-rolled mild s~erl, medium trnsile steel and high yield strcrlgth
steel deformed bars for concrete reinl’orcrnlcnts ( reuired).
TSpecification for cold-twisted steel bars for concrete reinforcement ( reuircdj.
ZSpecification for high tensile steel bars used in prestressed concrete.
&ode of practice for prestresscd k’ncretv.
Is:2911 (PartI/sec3)-1979
adequate on the basis of previous test cube results and strictly controlled
curing conditions. After transfer of prestress, the prestressing wires should
be cut off flush with the face of the concrete or pile shoe.
86.4 Stacking and Storing -- For stacking and storing, 7.4.1 may
be referred to.
8.7 Driving -There is some evidence to suggest that a larger ratio of ham-
mer weight to pile weight is required to avoid damaging the pile. Driving
of prestressed concrete piles should follow the recommendations for reinforc-
ed concrete piles as in 7.5. Although the effect of prestressing is to reduce
tension cracks induced by stress waves, such cracking may still occur, par-
ticularly when driving is ‘ light ‘, or if too light a hammer is used. A careful
check.for tension cracks should be made during the driving of the first pile
and, if these occur, the hammer drop should be reduced. If the cracks
persist or recur when the full drop has to be used, then a heavier hammer
should be substituted.
8.8 Bonding of Head of Pile into Pile Cap - The concrete of the pile may be
stripped to expose the prestressing wires. The concrete should be stripped
to such a level that the remaining concrete projects 50 mm to 7.5 mm into the
pile cap. Where tension has to be developed between the cap and pile, the
exposed prestressing wires should extend at least 600 mm into the cap. An
alternative method is to incorporate mild steel reinforcement in the upper
part of the pile. After stripping the concrete this reinforcement should be
bonded into the cap.
8.9 Lengthening of Piles - Where piles have to be lengthened during driving,
this may be done by one of the following methods:
a) Where mild steel reinforcement is incorporated in the head of the
pile,, lengthening may be as described in 7.8.
b) By using a mild steel splicing sleeve together with a precast exten-
sion piece. The sleeve should be bedded on to the top of the pile
with an earth-dry sand/cement mortar or other compound, and
the extension piece similarly bedded on to the sleeve.
It should be noted that piles lengthened in this way have a limited
resistance to bending at the splice.
c) By means of dowel bars inserted into drilled holes the connection
being made with grout or epoxy resin.
21
IS : 2911 ( Part I&x 3 ) - 1979
APPENDIX A
( cIm.lJe 5.3.1.1 )
LOAD-CARRYING CAPACITY - STATIC FORMULA
where
A, = cross-sectional area of pile toe in cm‘J,
D = stem diameter in cm,
*( = effective unit weight of soil at pile tot in !<gf/cm*,
PD = effective overburden pressure at pile toe in kgfjcjn:,
A’-{and N, = bearing capacity factors depending ugon the angle of
internal friction +!Jat toe,
NOTE1 -.- .?;( factor can he taken for general shear failure according to IS : 6403-
1971”. *
NOTE 2 - JVq factor will depend, apart from nature of soil, on the type of pile and
its method of construction, and the value are given in Fig. 1.
NOTE 3 -The earth pressure coeficient 2~’ depends on the nature of soil strata,
type of pile and its method of construction. For driven piles in loose to medium sands,
K values of 1 to 3 should be used.
NOTE 4 - The angle of wall friction may be taken equal to angle of shear resistance
of soil.
28
IS : 2911 ( Part I/Set 3 >- 1979
100
50 I_-^
20 25 30 35 40 45
ANGLE OF INTERNAL FRICTION 8
NOTE 5 - In working out pile capacities using static formula, for piles longer than 15
to 20 pile diameters, maximum &ective overburden at the pile tip should correspond to
pile length equal to 15 to 20 diameters.
A-2.2 When full static penetration data are available for the entire depth,
the following correlations may be used as a guide for the determination of
shaft resistance of a pile:
Type of Soil Local Side Friction
f
.B
Clays and peats where q. .c 10
30
IS:2911(PartI/Sec3)-1979
Sands
where
qc = static point resistance, and
h = local side friction.
qil Z -~
qco
2”
qcl+qca
2
where
qU = ultimate point bearing capacity,
qco = average static cone resistance over a depth of 2~i below
the base level of the pile,
gel = minimum static cone resistance over the same 2d below
the pile tip,
qez = average of the minimum cone resistance values in the
diagram over a height of 88 above the base level of the
pile, and
n = diameter of the pile base or the equivalent diameter for
a non-circular cross-section.
A-2.3 The correlation between standard penetration test value N and static
point resistance qc given below may be used for working the shaft resistance
and sink friction of piles.
31
IS:2911’(FartI/Sec3)-11979
APPENDIX B
( Clause 5.3.1.2 >
DYNAMIC FILE FQRMULAE
R-l. GENERAL
B-l.1 These are based on the laws governing the dynamic impact of elastic
bodies. They equate the energy of the hammer blow to the work done in
overcoming the resistance of the ground to the penetration of the pile. hl-
iowance is made for losses of energy due to the elastic contractions of the
pile, cap, and subsoil, as well as the losses caused by the inertia of the pile.
One of the most used of these formulae is the Hiley formula.
B-1.2 The modified Hiley formula is:
Whn
R= St-C/2
where
R r; ultimate driving resistance in tonnes. The safe load
shall be worked out by dividing it with a factor of safety
of 2.5;
w’ = mass of the ram in tonnes;
II = height of the free. fall of the ram or hammer in cm
taken at its full value for trigger-operated drop hammers,
80 percent of the fall of normally proportioned winch-
operated drop hammers, and 90 percent of the stroke for
single-acting hammers. When using the McKiernan-
Terry type of double-acting hammers, 90 percent of the
maker’s rated energy in tonne-centimetre per blow should
be substituted for the product ( Wh) in the formula.
The hammer shouid be operated at its maximum speed
whilst the set is being taken;
II = efficiency of the blow, representing the ratio of energy after
impact to striking energy of ram;
s- final set or penetration per blow in cm; and
C = sum of the temporary elastic compressions in cm
of the pile, dolly, packings, and ground, calculated or
measured as prescribed in B-1.4.
Where W is greater than P, and the pile is driven into penetrable
ground,
w + PZ,Z
‘I= w+P
32
IS : 2911( Part I/Set 3 ) - 1979
Where W is less than Pe and the pile is driven into penetrable ground,
Where the pile finds refusal in rock, 0.5P should be substituted for P
in the above expressions for 11.
33
IS : 2911( Part I/Stc 3 ) - 1979
table should be deducted from the calculated bearing value in the axial
direction of the pile.
Rake Pcrccn~ Dcrhrctior~
1 in 12 1.0
1 in 10 I.5
lin 8 2.0
lin 6 3.0
Iin 5 4.0
lin 4 5.5
Iin 3 8.5
lin 2 14.0
B-l.4 Value of Temporary Compression - The temporary compression of
the pile and ground occurring during driving shall bc determined from site
measurements whenever possible ,espedially when the set is small. A typical
arrangement for setting up of the set-recorder is shown in Fig. 2. To the
measured compression, the value of the compression of the dolly and pack-
ing ( Cl ) shall be added.
The value C may be obtained by calculations ( see B-1.4.2 ).
B-1.4.1 Where measurement cannot be taken, the temporary compression
of the pile C, and of the ground Cs may also be obtained by calculatioils
( see B-1.4.2 ).
B-1.4.2 Calculation for Temporary Compressiorl - The value of C (see
formula in B-l.2 ) is equal to C, + C, + C,,
where
Cl = temporary compression of dolly and packing,
C, = temporary compression of pile, and
C, = temporary compression of ground.
The values of C, C, and CJ may be computed using the following
formulae:
C, = 1.77 R/A, where the driving is without dolly or helmet, and
cushion about 2.5 cm thick; or
= 9.05 R/A, where the driving is with short dolly up to 60 cm
long, helmet, and cushion up to 75 cm thick.
C 2 = 0.657 g
A
c, = 3.55 J+
where
R = ultimate driving resistance calculated as in El.2 in tonnes,
L = length of the pile in metres, and
A = area of the pile in cm2.
34
DIRECTION OF
HAMMER BLOW
ELASTIC COklPRESSlON IN
PILE AND GROUND CC2 + C$
----p--- T
PILE
BOARD CLAMPED
TO PiLE DIRECTION OF PENCIL
MOVEMENT -
I
, _-
E
I,
>
1
PENCIL
s_$
u
,,A\V%\Y,~
I I
I
APPENDIX C
( Clause 5.52 )
DETERMINATION OF DEPTH OF FIXITY OF PILES
C-l. For determining the depth of fixity for calculating the bending moment
induced by horizontal load, the following procedure may be followed.
1 to 2 32 to 65 48.79
2 to 4 65 to’130 97.73
4 - 195.46
36
IS : 2911( Part I/Set 3 ) - 1979
L = Equivalent length of cantilever giving the same deflection at ground level ar the
actual pile.
d = Diameter of the pile.
L = Equivalent length of cantilever giving the same deflection at ground level ar the
actual pile.
d = Diameter of the pile.
37
IS : 2911( Part I/See 3 ) - 1979
APPENDIX D
( Clause 7.6.3 )
DATA SHEETS
Site .............................................................................................
Title .............................................................................................
Dnte for enquiry .............................................................................
Drltc piliag commenced. ...................................................................
Actual or anticipated date for completion of piling work ..........................
Number of pile ...............................................................................
Pi!c spcci!icitli~in:
[ . . . . . . . . . . . . . . . .. . .. . . . . . . . . . . . . . . . . . . .. . . . . . . ... .
From ccntrc towards the pcriphcry or from pcri-
pllCiy towuds the ccntrc
38
IS : 2911 ( Part I/% 3 ) -t 1979
Test Landing:
................................................ . ..........................................
Cmx-nl Rcnm-ks:
. . . . . . . . . . .. . .. . . . . .. . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. .. . . . . . . . . .. . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . .. . . . . . . . . . . . . . . . . . . . . . ..
. . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . .. . . . . . . . . . . . . . . . .. .
39
Special Difficulties Encountered:
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..*..........
. . . . . . . . . . . . . . . . . . . . . . . . . . . . ..*...........................................................
Results:
Working load specified for the test pile.. ..................................
Settlement specified for the test pile. ......................................
Settlement specified for the structure .........................................
Working laxi accepted for a single pile as a result of the test .............
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . *. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ,.
..............................................................
Working load in a group of piles accepted as a result of the test .........
........ ..... ..I..............................................
. . . . . . . . . . . . . . . . ..*...........................................
___~~_ .~~ ___~_ ~~~~ ~_.
General description of the structure to be founded on piles.. . . . . . . . . . . . .
. . . . . . . . . ..*.......... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...*.
. . . . . . . . ..-....................................................
. . . . .. ... . .. . . .. . . .. . . . . . . . ....... . . . . . . .. .. .. . . . . .. .. . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . .
...... .. ... . .. .... ... .... . .... ...... .. .. .. .... .. .. ....... .. ..
.........................................................................
40
IS : 2911 ( Part I@ec 3 >- 1979
BORE-HOLE LOG
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..
. . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Position of the
toe of pile to be
indicated thus +
Standing ground
water level indi-
cated thus _O
... ... ... ... .. . . .. ... .. . .. . .. . .. . .. . ... . .. ... ... ... ... ... ... ... . .. ... ... ... ... ... ... ... .. .
NOTE- Graph, showing the following relations, shall be prepared and added to the
report:
1) Load ve Time, and
2) Settlement vs Load.
41
IS : a911( Part I/Set 3) - 1979
( Continuedfrom page 2 )
CO~lJtViLV Representing
SHRI M. D. TAMBEKAR Bombay Port Trust, Bombay
Members
SHRI K. N. DAWNA In personal capacity ( P-820, Block P, Jlrcw .&pore,
Calcutta)
Dapun DIRECTOR RESEARCH Ministry of Railways
( SM II ), RDSO
DEPUTY DIRECTORSTANDARDS
( B & S/CB II ), RDSO ( Ah-mate)
SHRI A. GHOSHAL Braith~ch;taBum & Jessops Construction Co,
42
BUREAU OF INDIAN STANDARDS
Headquarters:
Manak Bhavan, 9 Bahadur Shah Zafar Marg, NEW DELHI 110002
Telephones: 323 0131, 323 3375,323 9402
Fax : 91 11 3234062,91 11 3239399, 91 11 3239382
Telegrams : Manaksanstha
(Common to all Offices)
Central Laboratory: Telephone
Plot No. 20/9, Site IV, Sahibabad Industrial Area, Sahibabad 201010 8-77 00 32
Regional Offices:
Central : Manak Bhavan, 9 Bahadur Shah Zafar Marg, NEW DELHI 110002 323 76 17
*Eastern : 1114 CIT Scheme VII M, V.I.P. Road, Maniktola, CALCUTTA 700054 337 86 62
Northern : SC0 335-336, Sector 34-A, CHANDIGARH 160022 60 38 43
Southern : C.I.T. Campus, IV Cross Road, CHENNAI 600113 235 23 15
TWestern : Manakalaya, E9, Behind Marol Telephone Exchange, Andheri (East), 832 92 95
MUMBAI 400093
Branch Offices:
‘Pushpak’, Nurmohamed Shaikh Marg, Khanpur, AHMEDABAD 380001 550 13 48
t Peenya Industrial Area, 1st Stage, Bangalore-Tumkur Road, 839 49 55
BANGALORE 560058
Gangotri Complex, 5th Floor, Bhadbhada Road, T.T. Nagar, BHOPAL 462003 554021
Plot No. 62-63, Unit VI, Ganga Nagar, BHUBANESHWAR 751001 40 36 27
Kalaikathir Buildings, 670 Avinashi Road, COIMBATORE 641037 21 01 41
Plot No. 43, Sector 16 A, Mathura Road, FARIDABAD 121001 8-28 88 01
Savitri Complex, 116 G.T. Road, GHAZIABAD 201001 8-71 1996
53/5 Ward No. 29, R.G. Barua Road, 5th By-lane, GUWAHATI 781003 54 11 37
5-8-56C, L.N. Gupta Marg, Nampally Station Road, HYDERABAD 500001 201083
E-52, Chitaranjan Marg, C-Scheme, JAIPUR 302001 37 29 25
117/418 8, Sarvodaya Nagar, KANPUR 208005 21 68 76
Seth Bhawan, 2nd Floor, Behind Leela Cinema, Naval Kishore Road, 23 89 23
LUCKNOW 226001
NIT Building, Second Floor, Gokulpat Market, NAGPUR 440010 52 51 71
Patliputra Industrial Estate, PATNA 800013 26 23 05
Institution of Engineers (India) Building 1332 Shivaji Nagar, PUNE 411005 32 36 35
T.C. No. 14/1421, University PO. Palayam, THIRUVANANTHAPURAM 695034 621 17
( First Revision )
Alterations
(Page 18, foot-note with ‘ $ ’ mark ) - Substitute the following for the
existing foot-note:
‘@pecification for cold worked steel high strength deformed ban for concrete
reinforcement ( rtcond retirion ).’
(Page 28, foot-note with c * ’ mark ) - Substitute the following for the
existing foot-note:
‘ *Code of practice for determination of bearing capacity of shallow foundation8
(jrst revision
). ’
(Pug8 29, Fig. 1 ) - Substitute the following-for the existing figure:
20 25 30 35 40 45
ANGLE OF INTERNAL FRICTION @
Clays
( Page 8, clause 5.1, line 6 ) - Add the words ‘ handling and driving
stresses and ’ after the word ‘ withstand ‘.
( Page 15, clause 5.11.6.1, line 6 ) - Add the words ( (see Appendix
B for probable value of n ) ’ after the word ‘ blow ‘.
5 11 ,(lPuge 16, clause 5.11.7.1 ) -Add the following new Note after
. . . :
‘NOTE - Where deformed bars are used, the reinforcement percent of sectional
area ahould be the equivalent area of the bars used, compared to plain mild steel
bars. ’
( Page 17, foot-note with ‘ 7 ’ mark ) - Add the following new foot-
note after ‘ 1 ’ mark:
6**Specification for Portland poizolana cement (second revision ). ’
(BDC43)
3
Prlnted at SimCJ Printing Prelr. Delhi, India
AMENDMENT NO. 2 DECEMBER 1984
TO
/ First Revision )
Alteration%
( Page 18, foot-note with ‘ * ’ mark ) - Substitute the following for the
existing foot-note:
‘ *Specification for mild steel and medium tensile steel bars and hard drawn steel
wire for concrete reinforcement: Part 1 Mild steel and medium tensile steel bars
( thirdrcr~ision ). ’
( Page 22, clause 7.5.7, 4th and 5th sentences ) - Substitute the
following for the existing sentences:
( Pages 24, 25 and 26, clauses 8.2.2, 8.3.3 and 8.5.3 ) - Substitute ‘IS :
1343-198O’for c IS. 1343-1960 ‘.
( Pages 24, 25 and 26, foot-note for’IS : 1343 ) - Substitute the follow-
ing for the existing foot-note:
‘ Code of practice for prestressed concrete ( jrst reuision ). ’
( Page 26, clause 8.5.1, line 3 ) - Substitute ‘ IS : 1786-1979t ’ for
‘ IS : 1786-1966t ‘.
( Page 26, foot-note with ( y ’ mark ) - Substitute the following for the
existing foot-,note:
tSpecification for cold-worked steel high strength deformed bars for concrete rein-
forcement ( second rctisio~). ’
( Page 30, clause A-2.2, informal table read with Amendment No. 1, third
‘Q qo
entry ) - Substitute 5 for 25
--W+ Pea
n= w+p
( Page 33, clause B-1.2, equation after line 1 ) - Substitute the equation
for c n ’ as under:
2
2 and(3Page36, Table 3 ) - Substitute ( kgf/cms ’ for ‘ kg/cm% ’ in columns
Addenda
(Page 15, clause 5.11.7.1, line 1 ) - Add the following words after the
word ‘ reinforcement ‘:
‘ of any type or grade ’
( Page 18, clause 7.2, line 4 ) - Add the following after the word
‘ reinforcement ‘:
(BDC43)
3
Printed at Simco Printinp Press. Delhi. India
t
( First Revision )
( Page 9, clause 5.3.1.2, line 4 ) - Delete the words ‘ (see Appen-
dix B ) ‘.
( Page 11, clause 5.2.2, fourth andjifth sentences ) - Substitute the
following for the existing matter:
‘A recommended method for the determination of depth of fixity,
lateral deflection and maximum bending moment required for design is
given in Appendix B for fully or partially embedded piles. Other
accepted methods such as the method of Reese and Matlock for fully
embedded piles may also be used.’
I: ( Page 16, clause 5.11.7.3, lines 1 and 2 ( see also Amendment
No. 2 ) ] - Substitute ‘According to IS : 1786-1985* ’ for ‘ as per
IS : 1139-1966* or IS : 1786-1966 t’.
( Page 16, foot-notes ) - Substitute the following for the existing
foot-notes:
‘*Specification for high strength deformed steel bars and wires for concrete
reinforcement ( third revision ).’
‘APPENDIX B
( Clause 52.2 )
2
B-l.2 Determine the depth of fixity and hence the equivalent length ot
the cantilever using the plots given in Fig. 2.
where
FI
T= 5 K andR = A/g ( KI and Kz are constants
J 1
given in
NOTE - Fig. 2 is valid for long fiexible piles Mhere the embedded length L, is
2 4R or 4T.
293
-FREE HEAD PILE Q
SANDS
AND NORMALLY LOADED
CLAYS
FOR PILES IN
Id_ I PRELOADED C:LAYS
r, 6 8 151
L,/R OR Ll/T
3
TABLE 2 VALUES OF CONSTANT Kl ( kg/cm8 )
TYPE OF SOIL VALUE
_______~
Dry Submerged
Loose sand 0’260 0.146
Medium sand 0.775 0.525
Dense sand 2.075 1.245
Very loose sand under 0.040
repeated loading or
normally loading clays
B-l.3 Knowing the length of the equivalent cantilever the pile head
deflection ( Y ) shall be computed using the following equations:
= P(h+LF)3
.a,.for fixed head pile
12 EI
B-2.1 The fixed end moment ( MF > of the equivalent cantilever is higher
than the actual maximum moment ( M) of the pile. The actual maximum
moment is obtained by multiplying the fixed end moment of the
equivalent cantilever by a reduction factor, m given in Fig. 3. The fixed
end moment of the equivalent cantilever is given by:
MF = Q( d -f- Lr 1 . ..for free head pile
= Q(L + Lr 1
. ..for fixed head pile
2
The actual maximum moment ( M ) = m ( MF ).
4
----7
Submerged
O-146
O-525 -FOR PILES IN
l-245 PRELOADEO CLAY
oao ----FOR PILES IN
SANDS AND
NORMALLY
Ll+Lf LOADED CLAYS
)
LIE
0.2 I I 1
‘5
0 2 4 6 8 10 12
10
15 L,/R OR Ll/T
i0
3A FOR FRFE HEAD PILE
v'THE PILE
L,/R OR Ll/T
ilever is higher
:tual maximum 38 FOR FIXED HEAD PILE
lament of the
;. 3. The fixed FIG. 3 DETERMINATION OF REDUCTION FACTORS FOR
COMPUTATION OF MAXIMUM MOMENT IN PILE
( BDC 4.3 ).