Bond Project Updates
The Board approved Kencon Constructors, LLC as the Construction Manager at Risk for the New Central Administration Building project at the September 19 Board Meeting. The contract for this undertaking amounts to $865,000.00 and will be funded through the bond. Bids for the CMAR contract were solicited on August 29, 2023, resulting in the receipt of 10 bids. These bids encompassed costs for both the pre-construction and construction phases, ranging from $665,204.00 to $2,745,298.00. District Staff and RVK Architecture meticulously evaluated and ranked the bidding firms based on the selection criteria published in the solicitation. Out of the 10 submitted bids, Kencon Constructors was the highest-scoring firm. Crews have begun surveying and preparing the area for the first phase in the construction of the new building.
Feb 25 - Abatement is ongoing and scheduled to be completed on Feb. 29. The demolition subcontractor is set to mobilize on site on Mar. 1.